ANVILFIELD Try FieldOS

Field calculator

Generator sizing calculator (running + surge)

A generator is undersized if it cannot carry everything running at once plus the jolt when the biggest motor starts. This calculator adds the total running watts of the loads that will be on together to the momentary starting surge of the largest motor, then applies a headroom percentage to land on a recommended size. Motors are the catch: an air conditioner, well pump, or compressor can pull several times its running watts for a moment on start, and that inrush sets the peak the generator must swallow without stalling or sagging the voltage. Enter the total running load in watts, the extra starting surge of the largest motor, and a headroom percentage. Build the running total from actual nameplate watts, use the locked-rotor or starting figures for the surge, and confirm the size, fuel type, and power factor against the equipment and the generator manufacturer, along with NEC sizing for the conductors, overcurrent, and transfer equipment.

Worked example

A site runs 6 kW steady with a 3 kW motor-starting surge. Size the generator with 25% headroom.

  • Running load6 kW
  • Starting surge3 kW
  • Headroom25%
  1. Peak demand = running + surge = 6 + 3 = 9 kW.
  2. With 25% headroom: 9 × 1.25 = 11.25 kW.

About 11.25 kW. Motor and compressor inrush drives the surge, so size for the peak, not just the running load.

Change the numbers in the calculator above to run your own.

More Electrical calculators

Standby generator replacements require a running load and motor surge estimate. To find installations for that service, PorchRocket's Asset Search returns visible outdoor generator locations with the owner of record at each site.

Next step: See public electrical bids

Generator sizing FAQ

How do I size a generator for running loads and motor starting surge?

Add the watts of the loads that will run together, then add the extra starting watts of the largest motor that may start while those loads are running. Apply the selected headroom percentage to that peak. This calculator estimates kW; confirm the generator's starting capability, fuel rating, voltage, phase, and power factor with its manufacturer.

Should I enter total starting watts or extra surge watts?

The surge field takes the extra watts above the motor's running watts, because its running load is already included in the running total. If a motor needs 5,000 W to start and 1,500 W to run, enter 3,500 W of extra surge. Adding the full starting watts on top of the running total would count that motor's running watts twice.

What generator size does 12,000 running watts plus 4,000 surge watts require?

The estimated peak is 16,000 W. With 20% headroom, the calculator returns 19,200 W, or 19.2 kW. Select equipment against the manufacturer's continuous and transient ratings rather than treating this arithmetic estimate as an approved equipment selection.

Why can a generator carry the running load but struggle to start a motor?

A compressor, pump, or other motor can demand substantially more power while starting than while running. The generator must support that transient without unacceptable voltage or frequency drop. Check the motor's starting data and the generator manufacturer's motor-starting guidance, including the sequence of starts and any other motors that can start together.

Does this generator estimate size the transfer switch or replace a load study?

No. It estimates running load plus a starting surge and headroom. Transfer equipment, conductors, overcurrent protection, load management, grounding, and installation requirements still need the adopted code, equipment instructions, and qualified design review. Site conditions, fuel choice, altitude, temperature, and simultaneous motor starts can change the required generator selection.

How do I qualify a public generator opportunity before preparing a bid?

Confirm the buyer, procurement stage, equipment schedule, transfer-switch count, access, shutdown window, and test requirements in the original bid package. Obtain actual supplier quotes and assign temporary power, civil work, fuel work, and testing responsibilities. Treat later maintenance as a separate opportunity rather than guaranteed installation revenue.

More in the Standby generator install field guide.