For general industry roof work, a designated area uses a warning line to keep employees within an eligible work zone. OSHA permits this option from 6 feet to less than 15 feet from a low-slope roof edge only for work that is both infrequent and temporary; at 15 feet or more, recurring work also qualifies. The line needs specified strength, height, visibility and support, and workers must stay inside it during operations.

Warning-line-bounded zone allowed for infrequent, temporary low-slope work away from the edge

Used across 2 Anvilfield field guides, most in Roofing.
Updated

Choose the protection from the work distance

OSHA 29 CFR 1910.28(b)(13) separates general industry low-slope roof work into three distance zones. Measure to the unprotected edge from every position the task requires, including the side of equipment where the employee stands. A unit centered 16 feet from the edge does not establish a 15-foot setback for someone working on its edge-facing side.

At 15 feet or more, OSHA 1910.28(b)(13)(iii)(B) also requires an implemented and enforced rule preventing entry into the inner 15-foot zone without the protection required there. This work rule accompanies the designated-area option as well as the exception for infrequent, temporary work without fall-protection equipment.

Read the roof hatch and access guide when laying out the approach. The designated-area boundary does not protect a worker from falling through a skylight or open hatch inside the zone.

Distance from roof edgeOSHA 1910.28(b)(13) protection options
Less than 6 feetGuardrail, safety net, travel restraint or personal fall arrest; a designated area does not qualify.
6 feet to less than 15 feetThose same systems, or a designated area when the work is both infrequent and temporary.
15 feet or moreThose systems or a designated area, including for recurring work. Infrequent, temporary work qualifies for the separate no-equipment exception; enforce the setback work rule in either case.

Check warning-line strength, sag and visibility

OSHA 1910.29(d)(2) sets a 200-pound minimum breaking strength for the warning line and places its lowest point, including sag, between 34 and 39 inches above the walking surface. Read the line's rated strength and measure the low point of each installed span. A 36-inch stanchion label does not establish the height of a sagging span.

OSHA requires the boundary to remain visible from 25 feet away and from every position inside it. Walk the intended work positions and access direction to establish that equipment screens and stored materials do not conceal it. Supports must also prevent a pull on one span from drawing slack out of the next and dropping that span below the height limit.

Position the line as close to the task as practicable. OSHA 1910.29(d)(2)(vi) sets its minimum edge setback at 6 feet for infrequent, temporary work and 15 feet for other work; employees remain inside the boundary throughout operations.

Mobile equipment changes the setback geometry

For temporary, infrequent work using mobile mechanical equipment, OSHA 1910.29(d)(3) sets warning-line offsets of at least 6 feet from edges parallel to equipment travel and 10 feet from edges perpendicular to travel. Mark the travel direction on the layout. Turning the operating route changes which edge receives the larger offset.

A rectangular roof with equipment traveling along its length needs the perpendicular-edge allowance at the ends of that route. Measure from the unprotected roof edge, then locate the warning line and the work inside it. The permanent rooftop protection guide addresses the owner's wider access system.

Distinctions

Designated hot-work area
The same words describe a location established for controlled welding or cutting in the hot-work permit guide. That fire-prevention designation does not establish a rooftop fall-protection zone.

Frequently asked questions

Can a painted roof stripe serve as the warning line?

OSHA 1910.29(d) specifies a perimeter line made from rope, wire, tape, or chain, installed to its line and support criteria. A stripe painted on the walking surface does not provide that installation.

Which roof slope qualifies for this rule?

OSHA 1910.21(b) defines a low-slope roof as having a slope of 4:12 or less. Use that definition when applying the general industry designated-area provisions.

Sources checked

Also defined as

  • Electrical: A location built and maintained as safe for hot work, such as a noncombustible shop bay, where routine hot work can be permit-free

Where this shows up

Related guides

Next step: Track roof access projects

Back to the full field glossary