Field glossary · measurement
Jam ratio
Jam ratio compares a raceway's actual inside diameter with a cable's actual outside diameter to screen a pull for wedging. Use the cable manufacturer's ratio definition and probability chart together. Some methods apply a bend-ovality correction in the calculation; others already include it in the chart. Mixing the two conventions, or assuming every ratio above 3.0 is clear, can misclassify a pull that satisfies conduit fill.
Conduit inside diameter over cable outside diameter for three same-size cables; a band near 2.8 to 3.0 risks jamming
Use one ratio convention from start to finish
Southwire's Power Cable Installation Guide defines jam ratio as conduit inside diameter divided by cable outside diameter. Southwire's jamming-probability chart already incorporates a 5 percent allowance for oval conduit bends. Multiplying the ratio by 1.05 and then using that same chart would apply the ovality adjustment twice.
Southwire also directs installers to measure cable diameter because actual dimensions can differ from published nominal values. Record the cable measurement, conduit bore, ratio convention, and chart source on the pull plan. A trade-size label is not a measurement of the raceway's clear inside diameter.
A ratio above 3.0 still deserves a chart check
Southwire's chart shows a small jamming probability between ratios of 3.0 and 3.2, rather than declaring jamming impossible above 3.0. American Wire Group identifies a 2.8 to 3.1 jamming band in its engineering guide, discussing the condition where bend sidewall pressure exceeds 1,000 lb/ft. The published methods describe risk under their stated assumptions.
For three equal cables with measured OD 1.35 in, compare a 4.10 in bore with a 5.10 in bore using Southwire's raw D/d definition. The smaller bore passes a 40 percent area-fill screen while its ratio remains in a charted jamming region. A nominal 3.0 cutoff would discard that risk information.
| Measured bore | Raw jam ratio | Three-cable area fill |
|---|---|---|
| 4.10 in | 3.04 | 32.5 percent |
| 5.10 in | 3.78 | 21.0 percent |
Check clearance after changing the conduit
Southwire recommends clearance above the uppermost cable of at least 10 percent of the conduit ID, or 1 in for large cables or installations with numerous bends. Clearance depends on whether the cables are triangular or cradled; the vertical gap is not simply bore minus three cable diameters.
After a bore change, recalculate cable configuration, clearance, tension, and sidewall pressure for the changed route. Keep the revised result with the conduit-fill calculation so the larger raceway has a documented installation basis.
Distinctions
- Conduit fill
- Fill compares cross-sectional areas. Jam ratio addresses cable arrangement and wedging, so a passing fill calculation does not settle it.
- Sidewall bearing pressure
- Sidewall pressure measures force per bend length. It interacts with wedging risk but is not the dimensionless diameter ratio.
Frequently asked questions
Can I calculate jam ratio from AWG size?
Use the complete cable's outside diameter, including insulation and any jacket, rather than the metal conductor diameter implied by AWG.
Does the three-equal-cable chart cover unequal cables?
The equal-diameter geometry does not describe an unequal set. Use the cable supplier's guidance for that actual arrangement rather than substituting an average diameter.
Sources checked
Also defined as
- 1.05 times conduit ID over cable OD; about 2.8 to 3.0 is the danger zone for three same-size cables