Waterstop

A waterstop is a concrete-joint seal identified by its manufacturer, profile number and cross-section, with product-specific cover and splice criteria. CETCO's WATERSTOP-RX RX-101 requires 3 inches of concrete cover, while RX-102 requires 2 inches. Measure that cover from the strip's outer surface to the concrete face. A passing material tensile certificate does not demonstrate that the installed joint resists the specified water head.

A strip cast into a concrete joint to block water from passing through the joint

Used across 2 Anvilfield field guides, most in Concrete.
Updated

Waterstop sizes and concrete cover

Sika's August 2014 PVC Waterstop Design Guide lists profiles from 4 to 12 inches wide and 1/8 to 1/2 inch thick. Measure the web separately from the ribs and centerbulb. A matching overall width does not establish matching rib positions, web thickness or bulb geometry at a replacement splice. Use the profile number and section drawing together; the waterstop construction guide covers placement sequencing.

CETCO's March 2025 WATERSTOP-RX data sheet requires 3 inches of concrete cover for RX-101 and RX-101T, versus 2 inches for RX-102. Measure the shortest distance from the strip's outer surface to the concrete face. The sheet specifies reinforced structural concrete with at least 3,000 psi compressive strength. RX-101 and RX-101T suit concrete at least 8 inches thick with two reinforcement rows; RX-102 is intended for one reinforcement row, with vertical concrete at least 6 inches thick or horizontal concrete at least 4 inches thick. Wall thickness, reinforcement arrangement and strip cover are separate selection checks.

Measurable rejection limits for PVC splices

Sika's August 2014 PVC splicing guide rejects centerbulb misalignment greater than 1/16 inch. It also rejects misalignment that removes more than 15% of the waterstop cross-sectional area, including combined losses from misalignment and incomplete bonding. Use a caliper across the cooled splice to record the bulb offset; matching the outside edges alone leaves the bulb alignment unresolved.

The same Sika guide requires splice tensile strength of at least 80% of the parent section. A visual inspection cannot establish that ratio. Sika also rejects visible pinholes, charred material and separation when a cooled splice is bent sharply by hand. Its sampling recommendation covers at least one field weld at the beginning and end of each day, with intervals set by the field engineer. Cut samples expose internal porosity that the surface bead conceals.

PVC material certificates versus weld acceptance

USACE still lists CRD-C 572-74, revised June 1, 1974, as its PVC waterstop specification. It sets minimum tensile strengths of 1,750 psi for finished PVC waterstop and 1,000 psi across factory or job-made splices, using CRD-C 573 die-C specimens. Those numbers describe stress in test specimens, not allowable water pressure at the joint.

With a parent tensile result of 2,000 psi, Sika's 80% criterion requires a splice result of at least 1,600 psi. A 1,300 psi splice exceeds the Corps' 1,000 psi minimum but fails Sika's criterion. Compare parent and splice results obtained by the same test method and specimen preparation.

ACI CODE-350-20, published in 2021, remains ACI's current environmental engineering concrete structures code as of November 5, 2026. Its design and construction scope is different from a PVC product qualification under CRD-C 572-74: naming ACI 350 on a drawing does not provide the supplied coil's material or weld test results.

Do WATERSTOP-RX ends overlap?

CETCO's March 2025 WATERSTOP-RX instructions require tightly butted coil ends and prohibit overlapping the waterstop. The same sheet permits up to 1 inch of overlap in the REVO-FIX retaining mesh over RX-101; that allowance belongs to the metal retainer. CETCO identifies REVO-FIX 101 specifically for WATERSTOP-RX 101. Use CETSEAL for RX-101T and RX-102 under the cited North American instructions. Mechanical fasteners alone are not an approved attachment for any of these three strips.

Distinctions

Hydrostatic head rating
A head test measures sealing under water pressure. A tensile result measures material stress at failure. Keep the test method and specimen or assembly configuration attached to each result; the two psi values are not interchangeable.

Field example

An 8 inch wall with two reinforcement rows uses RX-101, whose CETCO data sheet gives a 1 by 3/4 inch cross-section. With the 1 inch dimension centered across the wall thickness, side cover is (8 - 1) / 2 = 3.5 inches. Shifting the strip 3/4 inch toward a face reduces that cover to 2.75 inches, falling 1/4 inch short of CETCO's 3 inch requirement. At a form recess, calculate cover using the local wall thickness rather than the nominal 8 inches.

Frequently asked questions

Does a spark test prove a PVC waterstop weld is sound?

Sika's PVC splicing guide says a spark test alone does not establish weld quality: a partly bonded joint can pass it. Visual inspection and destructive samples address bond continuity and internal defects that a pinhole check leaves unresolved.

Sources checked

Also defined as

  • A continuous barrier cast into or applied across a concrete joint to block water

Where this shows up

Related guides

Next step: Find public concrete work

Back to the full field glossary