Commercial RTU replacement cost by ton: equipment, crane and curb tables

Compare installed 5-, 10- and 20-ton gas/electric replacements from equipment prices, measured connection allowances, paid labor and shared crane logistics.

Commercial HVACRooftop UnitReplacement CostHVAC EstimatingCrane Mobilization

Direct answer

Anvilfield estimates commercial RTU replacement at about $22,000 to $27,000 installed for 5 tons, $41,000 to $48,000 for 10 tons, and $79,000 to $90,000 for 20 tons, before tax, for the gas/electric configurations and accessible-roof scope priced November 5, 2026. Central budgets are $24,861, $44,617 and $84,646, built from HVAC365 equipment listings, St. Louis crane rates published by Missouri Crane, and stated Anvilfield labor and material allowances for curb adaptation, connections and startup. Equipment alone costs about $9,803, $21,470 and $43,954 respectively; the installed dollars per ton come from pricing the complete job.

On this pageHow much does commercial RTU replacement cost by ton?Which 5-, 10- and 20-ton jobs are comparable?What does equipment-only pricing leave out?Dated equipment, labor and material rate registerHow much does an RTU crane mobilization cost?How do multiple RTUs share one crane mobilization?What do curb reuse and curb adapters add?Which connection and roof quantities belong in the estimate?How many crew-hours and startup hours are included?Worked example: what does one 10-ton replacement cost?What changes the range and the final bid?Which equipment and refrigerant differences change scope?Field checklist: what must be verified before firm pricing?

How much does commercial RTU replacement cost by ton?

Use the capacity table for an accessible-roof gas/electric replacement with suitable existing structure and electrical service. Each case buys one R-32, 208/230 V, three-phase unit, one adapter, limited reconnections and daytime installation. Street closures, structural reinforcement, a new feeder and temporary conditioning require separate scope.

Table A. Installed replacement budgets by nominal capacity.
Nominal coolingNamed selectionEquipment onlyInstalled rangeCentral installed estimateCentral installed dollars per nominal ton
5 tonsDaikin DSG0603DL00001S$9,803$22,400 to $27,321$24,861$4,972
10 tonsDaikin DSG1203DL00001S$21,470$41,050 to $48,184$44,617$4,462
20 tonsDaikin DSG2403DL00001S$43,954$79,207 to $90,086$84,646$4,232

Table A reports USD before tax, rebates and financing. Equipment inputs are the 5-ton, 10-ton and 20-ton HVAC365 listings checked November 5, 2026; installed results are Anvilfield estimates using the rate register and calculation below.

Dollars per ton are the result of the estimate. A smaller replacement still needs access, lifting, permit coordination and startup, so those costs do not fall in direct proportion to cooling capacity. The declining per-ton figures here describe these three complete scopes.

The ranges vary labor and purchased allowances within the defined scope. Reprice access changes, conversions and redesigns as measured additions.

Which 5-, 10- and 20-ton jobs are comparable?

A rooftop unit packages heating and cooling equipment for ducted building service. These selections hold gas heat, refrigerant, voltage and the installation boundary constant, using one manufacturer's standard-efficiency, standard-static products. Nominal cooling tons and gas heating input remain separate selections.

DOE's undated Advanced RTU Campaign decision tree asks whether the existing unit is properly sized before procurement. Review load, ventilation and changed occupancy before retaining the old capacity; use the RTU portfolio repair-or-replacement survey to establish the capital work that needs pricing.

Table B. Equipment configuration register, checked 2026-11-05.
Field5 tons10 tons20 tons
ModelDSG0603DL00001SDSG1203DL00001SDSG2403DL00001S
Cooling at published rating basis57,500 Btu/h116,000 Btu/h230,000 Btu/h
High-stage gas heat input, seller and OEM model tables90,000 Btu/h130,000 Btu/h260,000 Btu/h
Refrigerant / voltage / phaseR-32 / 208/230 V / 3R-32 / 208/230 V / 3R-32 / 208/230 V / 3
Seller label, confirmed against OEM selected-model table13.7 SEER215.2 IEER14 IEER
OEM base MCA / maximum overcurrent protection at 208/230 V28.1 A / 40 A53.8 A / 70 A98.7 A / 125 A
Ventilation accessory estimate1 economizer assembly1 economizer assembly1 economizer assembly
Curb treatment1 adapter on serviceable curb1 adapter on serviceable curb1 adapter on serviceable curb
Central paid labor44 person-hours64 person-hours96 person-hours
Crane budget basis4 h at $265/h4 h at $265/h8 h at $375/h plus $500 hauling allowance

Daikin's June 2026 SS-DSG3-R32, SS-DSG7-R32 and SS-DSG15-R32 list cooling capacities of 57,500, 116,000 and 230,000 Btu/h for the selected models, marketed as 5, 10 and 20 tons. Use nominal tons for this comparison and selected performance at design conditions for engineering.

Match the full model and option schedule

Record the ordering code, voltage/phase, heat input, refrigerant, fan/static selection, ventilation assembly and controls interface. The 5-ton selection uses SEER2; the larger selections use IEER. Those labels measure different rating bases and cannot be ranked as one efficiency scale.

Table B's minimum circuit ampacity (MCA) and maximum overcurrent protection (MOP) come from pages 16, 13 and 11 of the respective June 2026 sheets. Verify the retained circuit against the ordered options and installed nameplate, including conductor and protective-device suitability. The priced crane classes require confirmation against the actual load chart.

Price a second brand, intermediate capacity or heat-pump alternate by replacing its equipment and affected connections together. A heat-pump conversion can change backup heat, feeder demand, controls and defrost drainage; interpolating a gas/electric dollars-per-ton figure leaves those quantities unresolved.

What does equipment-only pricing leave out?

An equipment purchase buys the ordered cabinet and factory components. An installed replacement also buys removal, a watertight roof interface, working connections and documented startup. Show those direct costs separately from estimating contingency and contractor markup so the owner can compare the same deliverable.

Table C. Equipment versus installed-work scope.
Scope lineEquipment purchaseInstalled replacement budget hereBid verification
Packaged cabinet and factory-selected componentsIncluded as ordered1 unitComplete model and options
Economizer/ventilation accessoryConfirm separately1 assembly allowancePart number, controls and relief requirements
Delivery/unloadingSeller advertises qualifying shippingOrdinary shipping assumed included; receiving in laborFreight, liftgate, unloading and storage terms
Crane/operator/basic riggingExcludedPublished rental basisPortal time, minimum, rigging and extra transport
Curb adapter/gasket/internal transitionExcluded1 adapter assemblyOld/new dimensions, supplier drawing
RoofingExcludedLocal repair allowanceMeasured repair and warranty detail
Duct, gas, drain, electricalExcludedShort reconnectionsLengths, counts and capacity verification
Thermostat and control wiringExcluded unless selected1 basic controller plus reconnectionStaging and network boundary
Removal and refrigerant recoveryExcludedLabor plus handling/disposal allowanceRecovery and receiving records
Startup and airflow verificationExcludedDedicated person-hoursOEM startup form and test scope
Design/permit coordinationExcludedBudget allowanceActual fee schedule and design scope
Temporary service / structural steel / new feederExcludedSeparately priced additionsQuantity and owner authorization

Table C is the bid-leveling matrix: assign a responsible trade and an included quantity to every line. “By others” is complete only when the corresponding work appears in another accepted scope. Separate allowances, fixed-price work and owner-direct contracts so an omitted electrical or roofing package cannot masquerade as a cheaper installation.

Normalize model/options, freight, tax, connections and acceptance tests. Add quoted exclusions before comparing totals, and remove duplicate charges only where written inclusions overlap.

Define completion as the selected equipment and accessories installed, roof interface closed, connections operating, unit airflow/startup recorded and controls tested. Full-building testing, adjusting and balancing (TAB), network integration and a seasonal return visit need additional quantities when specified. The RTU installation and startup guide describes the execution work this estimate purchases.

Record locally adopted code editions, permit fees and the permit authority's requirements for this alteration. Assign ventilation/economizer controls, roof attachment, access and inspection work to priced scope lines. Daikin IOD-1069B, December 2024, directs installation to applicable local codes; the economizer allowance here is an estimating selection, not a universal code threshold.

Dated equipment, labor and material rate register

The equipment amounts below are public seller asking prices checked November 5, 2026. The method note retains source cents for reproduction; obtain purchase-date freight, tax and validity terms. These are seller listings, not negotiated contractor quotes or manufacturer price schedules.

Table D. Rate register.
InputRate / amountUnit and scopeBasis / edition
5-ton equipment$9,803DSG0603DL00001S, 1 unitS1, live seller listing, accessed 2026-11-05
10-ton equipment$21,470DSG1203DL00001S, 1 unitS2, same date
20-ton equipment$43,954DSG2403DL00001S, 1 unitS3, same date
HVAC/mixed-trade labor budget$85Per paid person-hour, loaded costA1, November 2026 estimating input
40-ton crane rental class$265Per portal-to-portal hour, 4-hour minimum; operator/basic rigging includedS4, undated rate page accessed 2026-11-05
60-ton crane rental class$375Per portal-to-portal hour, 8-hour minimum; engineer/oiler included; counterweight hauling extraS4, same
Counterweight transport, 20-ton job$500One allowance, separate from published rentalA1, not a Missouri Crane quote
Accessories/materials/services other than equipment and crane$5,050 / $7,300 / $11,300Per 5/10/20-ton job, itemized in Table HA1
Contingency10%Direct costA1, defined-scope estimating reserve
Overhead and profit markup15%Direct cost plus contingencyA1, markup rather than margin
Purchase/customer taxOutside displayed totalsActual taxable basis and jurisdictionObtain job-specific tax treatment

A1 denotes Anvilfield's November 5, 2026 estimating inputs throughout the tables. The $85 paid-person-hour cost includes wages, payroll burden and benefits, excluding business overhead and profit. Labor productivity, accessory prices, material/service allowances, the $500 transport allowance, contingency and markup are Anvilfield estimates.

Keep each crane vendor's rate, minimum, billing clock and inclusions together. Obtain a new equipment price for a different voltage or heat package.

Retain each item/model, quantity, price source, date/expiry, freight, tax and exclusions. Update installation hours when replacing an assembly allowance. Ordinary freight is assumed included; price special delivery, unloading or storage separately.

How much does an RTU crane mobilization cost?

Missouri Crane's published 40-ton rental rate, checked November 5, 2026, is $265 per portal-to-portal hour with a four-hour minimum and operator and basic rigging included, producing a $1,060 minimum charge before extra services. Its St. Louis rate schedule prices the 60-ton class at $375 per hour with an eight-hour minimum, or $3,000 before required counterweight hauling.

Table E. Published crane rental comparison.
Company / regionRental classHourly rateMinimumCalculated base minimumIncluded or additional
Missouri Crane / St. Louis30 ton$1953 h$585Operator, basic rigging; portal-to-portal
Missouri Crane / St. Louis40 ton$2654 h$1,060Operator, basic rigging; portal-to-portal
Missouri Crane / St. Louis60 ton$3758 h$3,000Engineer/oiler; counterweight hauling additional
Keweenaw / Michigan40 ton$2754 h$1,100Shop-to-shop; rigging additional; $150/day December-March surcharge
Central Maine40 or 45 ton$2054 h$820Operator; portal-to-portal; fuel surcharge announced 2026-04-06

Crane rental tons describe lifting capacity class; RTU tons describe cooling capacity. OSHA 29 CFR 1926.1417(o), checked November 5, 2026, requires rated-capacity compliance and load-weight verification. Supply radius, reach, configured load including rigging, access, ground support, power-line exposure and staging constraints for the crane selection.

Obtain standard-time, overtime/weekend, travel, waiting and cancellation terms with the rate. OSHA 29 CFR 1926.1402 addresses ground support, and 1926.1408 addresses power-line exposure for equipment operations up to 350 kV. Price required ground preparation, mats, traffic control or utility coordination separately from the crane rental.

How do multiple RTUs share one crane mobilization?

Divide the complete crane charge among the replacements served by that mobilization. Allocate common travel and setup equally, then assign unit-specific lifting time to the unit that uses it. Equal total allocation fits comparable picks. Anvilfield's shared-lift estimate allows one hour total travel, one hour setup/teardown and half an hour for each combined removal/set cycle.

Table F. Crane allocation for comparable replacement cycles.
Units in one mobilizationCalculated portal hoursBillable hoursCrane totalAllocated per unitSeparate visits totalGroup saving
12.54$1,060$1,060$1,060$0
234$1,060$530$2,120$1,060
444$1,060$265$4,240$3,180
655$1,325$221$6,360$5,035

Four comparable RTU replacements completed within one four-hour crane mobilization at Missouri Crane's published rate allocate $265 per unit and save an Anvilfield-estimated $3,180 against four separate minimum-charge mobilizations, before contractor markup and tax. The half-hour cycles are Anvilfield estimates covering removal, adapter placement and setting with prepared crews, ready equipment and one viable setup. New-curb construction or roof repairs between removal and setting need their own crane timeline.

The four-unit 10-ton installed budget is $174,445 before tax with a shared lift, versus $178,468 with separate lifts: a $4,023 saving after contingency and markup. Each unit retains its labor and other allowances; calculate group totals from unrounded costs. That saving is 2.25% of the separate-lift budget. Compare it with the cost of retiring serviceable equipment early when choosing which units to replace together.

Six replacements use five billed hours at the same standard-time rate; their allocation rounds to $221 each. Four replacements requiring two minimum-charge setups instead cost $2,120 for the crane, saving $2,120 against four visits. Repositioning, waiting and a missed delivery must enter the timeline before claiming a group saving.

Build a grouped replacement survey program

Group work by buyer, shutdown permission, equipment readiness and feasible crane position. Estimators organizing multi-unit replacement surveys use PorchRocket's Ground Control to find commercial buildings with two or more visible rooftop HVAC units in their service area. Record capacity and condition from nameplates and service records; the aerial-survey limits guide separates visible equipment counts from the field information needed for a replacement price.

What do curb reuse and curb adapters add?

Anvilfield's November 2026 purchase allowances are $1,200, $1,800 and $3,000 for one adapter on the respective 5-, 10- and 20-ton jobs. Installation labor is separate. The allowance buys the assembly, gasket and internal transitions; external duct reconnections and local roof repair remain separate lines.

MicroMetl Form 4153-1P, March 2006 calls for existing-unit identification, measured curb dimensions and labeled supply/return openings. Its described adapter arrangement uses side-by-side ducts rather than concentric ducts. Cooling tons alone cannot identify the opening geometry or establish fit.

MicroMetl's Form 2371-6P requires the installer to verify support for the adapter and replacement RTU and account for the adapter's added external static pressure, so curb compatibility must include structure and airflow as well as dimensions. The installation instructions, copyright 1993 with no separate revision shown supply the installation scope; the purchase allowances here are Anvilfield estimates.

Table G. Ten-ton curb alternatives, Anvilfield estimates, November 2026.
Curb conditionPurchased assemblyChange in direct cost from adapter caseRevised installed budget before tax
Existing curb compatible and serviceable1 replacement gasket kit, $150 A1 allowance, instead of $1,800 adapter assembly-$1,650$42,530
Serviceable curb requiring adaptation1 adapter including gasket/internal transitions, $1,800 A1 allowance$0$44,617
Existing curb damaged or unsuitableNew curb, demolition, support, duct modification and roof closure, separately measured and quotedReplace the adapter allowance and affected quantities with quoted workRecalculate from the measured alternate

The compatible-curb alternate changes only the purchased assembly and its contingency and markup; inspection, preparation, sealing, duct and roof work remain.

A damaged or unsupported curb needs a measured new-curb, support and roofing alternate. Use the rooftop support guide and penetration flashing guide to define those interfaces. The base adapter contributes $2,277 after contingency and markup; combined with the crane minimum it contributes $3,618, before separately counted field labor.

Which connection and roof quantities belong in the estimate?

Count assemblies and measure connection lengths before assigning money. Table H contains Anvilfield purchase and service allowances dated November 5, 2026; installation labor appears in Table I. Each dollar amount extends the listed quantity, so the owner can replace an allowance without losing its scope.

Table H. Purchased allowance quantities, excluding installation labor.
Line5-ton quantity / cost10-ton quantity / cost20-ton quantity / cost
Economizer accessory1 assembly / $1,2001 / $1,8001 / $2,500
Adapter with gasket and internal transitions1 assembly / $1,2001 / $1,8001 / $3,000
Roof repair materials20 sq ft at $15 / $30025 sq ft at $16 / $40040 sq ft at $15 / $600
External duct sealing/connection materials2 connections at $100 / $2002 at $150 / $3002 at $250 / $500
Disconnect and electrical reconnection material kit1 disconnect, 6 ft connection / $3501, 6 ft / $5001, 10 ft / $900
Controller/control materials1 controller, retained wiring / $3501 / $4501 / $650
Gas reconnection materials6 ft plus valve/fittings / $2006 ft / $25010 ft / $400
Condensate trap and line materials1 trap, 10 ft / $1001, 15 ft / $1501, 20 ft / $200
Recovery consumables, transport and disposal service1 retired unit / $3501 / $4501 / $700
Permit/design allowance1 job / $5001 / $7501 / $1,250
Truck/material handling expense, excluding paid labor1 job / $3001 / $4501 / $600
Total$5,050$7,300$11,300

The electrical line buys one compatible disconnect and a short reconnection kit. Verify voltage, phase and selected-option MCA and MOP before retaining the feeder. Select conductor size, protective devices and gas diameter for the actual application; the kit prices cover the stated assemblies.

Controls include one conventional controller with viable retained wiring. Price BAS gateways, licenses, graphics, point mapping and network commissioning by their own quantities. List factory-supplied and field-added interfaces separately so a detection assembly or controller is not purchased twice.

The economizer line buys one selected accessory. Ventilation and economizer commissioning also requires a defined scope for relief, demand-control functions and applicable interlocks. Record ordered options and functional tests together; an accessory price alone does not settle the ventilation acceptance scope.

Roof materials cover local repairs around the curb, with labor below. External duct materials cover two connections; expanded duct leakage testing and sealing requires additional scope. Recovery consumables, transport and disposal exclude recovery technician hours already carried in labor.

Localize changes through quantities and selections: hot/humid ventilation or dehumidification, cold-climate heating, coastal protection, high-static fans and roof access. Replace the affected equipment, materials and hours instead of applying an unsupported climate or city percentage to the whole job.

How many crew-hours and startup hours are included?

Anvilfield's November 2026 central estimates carry 44, 64 and 96 paid person-hours at $85 per hour, producing direct labor costs of $3,740, $5,440 and $8,160. Multiply each worker's paid time by the worker count and sum across trades. Four workers for four elapsed hours consume 16 person-hours.

Table I. Paid person-hour allowance, A1 November 2026 estimate.
Work package5 tons10 tons20 tons
Survey, travel, access, planning and receiving6810
Isolation, recovery, disconnection and removal preparation6812
Lift-day HVAC crew, adapter preparation and setting121624
Roof/duct/accessory fitting and utility/control reconnections122034
Startup, airflow/ESP verification, functional checks and turnover81216
Total person-hours446496
At $85/person-hour$3,740$5,440$8,160

The crane operator is already included in the rental. Startup buys unit-level airflow and external static pressure (ESP) verification plus the ordered model's functional tests; whole-building TAB, BAS integration or seasonal return work need their own hours.

Buy a startup record showing voltage and phase checks, operating amperage, airflow/ESP, heating input and temperature rise, condensate drainage, controls and ordered accessory tests. Use the replacement manual's acceptance conditions. For the selected 20-ton family, Daikin IOD-1069B, December 2024, page 17 limits refrigeration startup below 55°F outdoor ambient to readiness checks, with final checks and calibration above 55°F. Price that return visit when it applies.

Turn paid hours into a tenant outage schedule

Anvilfield's worked 10-ton schedule assigns eight paid person-hours before shutdown, 32 on the lift day and 24 on the completion day. That totals 64 paid person-hours across two field workdays plus advance preparation, with a 30-hour shutdown-to-release window.

Table J. Worked 10-ton labor and outage schedule, A1.
PhasePaid staffing and durationPerson-hoursUnit availability
Survey, travel, planning and receiving before shutdown2 workers × 4 h8Existing unit remains available
Day 1, 08:00 to 10:00, isolation/recovery/removal preparation4 workers × 2 h8Offline
Day 1, 10:00 to 14:00, adapter/lift-day work4 workers × 4 h16Offline; crane has a separate four-hour portal allowance
Day 1, 14:00 to 16:00, roof/duct/accessory/connections4 workers × 2 h8Offline
Day 2, 08:00 to 11:00, remaining connections4 workers × 3 h12Offline
Day 2, 11:00 to 14:00, startup/airflow/tests/turnover4 workers × 3 h12Released after acceptance
TotalTwo field workdays plus advance preparation6430 elapsed hours from shutdown to release

The lift-day phase includes crew preparation while the crane travels and sets up. Place the removal/set inside the quoted portal window. Unit outage runs through recovery, roof closure, connections and acceptance testing.

Work backward from the permitted interruption. Confirm delivery, inspect freight damage, verify the adapter and stage parts before booking the lift. Obtain supplier and fabricator lead times for the ordered package; advertised stock or shipping speed does not establish installation completion. Temporary conditioning and restricted weekend work are separately measured additions.

Worked example: what does one 10-ton replacement cost?

Anvilfield's November 2026 estimate for a Daikin DSG1203DL00001S 10-ton gas/electric replacement is $44,617 before tax, including a $21,470 equipment purchase, 64 paid labor hours, one four-hour crane minimum, an adapter, connections, startup, contingency and markup.

The job uses existing suitable structure and service, one economizer accessory and limited connections. Add purchased equipment, labor, crane and Table H allowances to obtain direct cost. Increase that sum by the contingency percentage, then apply overhead and profit markup to the resulting subtotal.

Table K. Complete worked inputs and outputs.
Line5-ton case10-ton worked case20-ton case
Equipment$9,803$21,470$43,954
Labor44 × $85 = $3,74064 × $85 = $5,44096 × $85 = $8,160
Crane4 × $265 = $1,0604 × $265 = $1,0608 × $375 + $500 = $3,500
Table H allowances$5,050$7,300$11,300
Direct cost$19,653$35,270$66,914
10% contingency$1,965$3,527$6,691
15% markup on direct plus contingency$3,243$5,820$11,041
Calculated installed budget, before tax$24,861$44,617$84,646
Divide by nominal tons$4,972/ton$4,462/ton$4,232/ton

Method and rounding

Anvilfield estimates use HVAC365 equipment prices and Missouri Crane rental terms checked November 5, 2026, plus the labor hours and purchased allowances listed here. Direct cost is equipment plus paid labor, crane and the itemized allowances; the budget adds 10% contingency and then 15% overhead and profit markup. The labor and allowance ranges vary within the defined scope, while equipment price and crane selection remain fixed; tax, rebates, financing and separately measured scope additions are outside the displayed totals.

P = (E + H × L + C + A) × 1.10 × 1.15, where E is equipment, H is paid person-hours, L is loaded hourly labor cost, C is crane and A is Table H allowances. Exact equipment inputs are $9,802.82, $21,470.31 and $43,953.96 for 5, 10 and 20 tons. Retain those cents in calculation and round displayed outputs to whole dollars; rounded components can differ from the total by $1.

The 10% contingency reserves money for quantity and productivity uncertainty within the defined work. Known feeder, structural, BAS or temporary-service additions belong in measured line items. The 15% markup equals a 13.04% margin on the contingency-inclusive selling-price basis, calculated by dividing 15 by 115; actual profitability also reflects reserve spending.

Apply tax to the project's actual taxable basis and contracting treatment. Show a confirmed incentive as an owner funding credit after the work price, with financing separate. Neither an assumed rebate nor the owner's payment method reduces the contractor's installation scope.

What changes the range and the final bid?

Anvilfield's low case uses 75% of central labor hours and 80% of Table H allowances; its high case uses 125% and 120%, respectively. Equipment, crane, contingency and markup stay fixed. These are defined estimating settings for the same scope.

Table L. Defined-scope range, A1.
CapacityLow labor / Table HCentral labor / Table HHigh labor / Table HLow resultCentral resultHigh result
5 tons33 h / $4,04044 h / $5,05055 h / $6,060$22,400$24,861$27,321
10 tons48 h / $5,84064 h / $7,30080 h / $8,760$41,050$44,617$48,184
20 tons72 h / $9,04096 h / $11,300120 h / $13,560$79,207$84,646$90,086

Adding 16 paid person-hours at $85 per hour increases Anvilfield's worked 10-ton replacement budget by $1,720 after its stated 10% contingency and 15% overhead-and-profit markup, before tax. Changing only the loaded labor rate to $100 for the original 64 hours adds $1,214 to the installed budget.

Table M. One change at a time to the 10-ton case.
ChangeDirect-cost deltaInstalled-budget deltaRevised installed budget
Add 16 paid hours+$1,360+$1,720$46,337
Change loaded labor from $85 to $100/h, same 64 h+$960+$1,214$45,831
Add second crane minimum plus 8 paid hours+$1,740+$2,201$46,818
Add $2,000 of defined roof/controls work+$2,000+$2,530$47,147
Add second 4-hour crane minimum only+$1,060+$1,341$45,958
Increase equipment price 10%+$2,147+$2,716$47,333
Share original 4-hour lift among four comparable units-$795 per unit-$1,006 per unit$43,611 per unit

Waiting crews, repeat travel, cancellation fees and temporary conditioning enter the worksheet as separate costs when incurred. The crane-only row isolates the rental effect.

Request waiting, weather, cancellation and rescheduling terms when booking the crane. An equipment delivery date that slips past the approved shutdown can change staffing and tenant-service costs as well as rental time. Reprice the changed sequence instead of applying the crane-only delta to every delay.

Localize a firm bid by replacing equipment/freight, trade labor rates, permit/design fees and crane terms, then recounting the work. Emergency premiums, structural steel, a new roof opening, feeder upgrades and BAS conversions require revised scope. Keep those known additions visible beside the base price so the owner can decide what changed.

Which equipment and refrigerant differences change scope?

Use the replacement model's instructions for installation and acceptance. Daikin's June 2026 DSG sheets identify the selected R-32 families; Carrier's 48TC-4-16-01SM, May 2014 identifies legacy R-410A equipment. A legacy service manual helps describe removal and existing records; the new model's manual determines its startup tasks.

EPA's sector restrictions page, updated August 28, 2026, distinguishes self-contained products from field-assembled systems. Record equipment classification, manufacture/import date and the applicable transaction when procuring equipment. Apply the category-specific rule rather than borrowing a split-system installation deadline for a packaged RTU.

EPA's safe-disposal guidance, updated March 23, 2026, requires refrigerant recovery before disposal for equipment dismantled on site. Carry technician time, consumables, handling, transport and disposal once each, and retain the recovery and receiving records with the retired unit tag.

Table N. Source differences and estimating action.
Sources / editionsVerified differenceEstimating action
Daikin SS-DSG3/7/15-R32, 06/26 vs Carrier 48TC-4-16-01SM, 05/14R-32 selected replacement family vs R-410A legacy familyUse selected replacement instructions and required service equipment; price removal separately
MicroMetl 4153-1P, 03/06 and 2371-6PExisting side-by-side geometry, structural support and added pressure loss affect adapter suitabilityMeasure the arrangement and obtain the selected adapter drawing; no universal pressure-loss allowance
NREL/FS-5500-95286, 09/25 vs model-specific instructionsGeneral maintenance guidance is not a substitute for OEM instructionsCarry maintenance handover and records; refer detailed calendar to existing PM guide
Daikin SS-DSG7-R32, 06/26, pp. 13 and 86Selected-model and installation-family tables give conflicting shipping and operating weightsObtain OEM/supplier confirmation of the exact configured lifting load before crane selection

The 10-ton weight conflict affects crane procurement directly. Daikin SS-DSG7-R32, June 2026, page 13 gives the selected model 1,199 lb shipping and 1,161 lb operating; page 86 labels its family row 1,161 lb shipping and 1,233 lb operating, with corner loads totaling 1,161 lb. Obtain supplier/OEM confirmation of the exact configured lifting load; reversing labels or selecting the largest printed number does not resolve it.

The 5-ton sheet gives 607 lb shipping/537 lb operating, and the 20-ton sheet gives 2,290 lb shipping/2,175 lb operating for the selections. Include actual accessories and lifting gear in the applicable load. Daikin IOD-1069B, December 2024, covers R-32 15-25-ton DSG equipment and includes refrigerant-detection instructions: include the selected 20-ton installation's room-area/duct conditions and specified detection/mitigation interfaces in the scope, with their checks in startup. Separate factory equipment from field work.

NREL/FS-5500-95286, September 2025, supplies general maintenance guidance while retaining manufacturer-specific instructions. Hand over the ordered-unit manuals and task calendar through the preventive maintenance program; price recurring maintenance separately from replacement capital.

Field checklist: what must be verified before firm pricing?

Turn each unknown into a recorded quantity, assigned quotation request or priced alternate. An item marked “existing” needs evidence that it suits the replacement selection. Keep the equipment schedule, photographs, dimensioned curb sketch, crane basis, quotes, hours and acceptance scope together under the unit tag.

Replace each allowance with the surveyed quantity or confirmed factory inclusion. Record the price source and responsible trade when reconciling the survey against the proposal.

At turnover, connect the accepted replacement record to the maintenance agreement's scope and exclusions. That keeps future service findings attached to the installed configuration and separates capital authorization from the recurring contract.

  • Record unit tag, existing and proposed full model, cooling selection, heat input, voltage, phase and refrigerant.
  • Record load/ventilation selection basis and any change in space use; identify who approved capacity.
  • Measure curb exterior, supply/return openings, orientation and duct connection arrangement; obtain adapter drawing.
  • Record existing curb/roof condition, support review, added assembly weight and roofing repair quantity.
  • Record crane location, radius, reach, load including accessories/rigging, approach and setup constraints; request matched rental terms.
  • Identify each unit sharing the mobilization, readiness date, removal/set sequence and allocation method.
  • Record feeder/disconnect suitability against selected voltage, MCA and MOP; price any replacement separately.
  • Count and measure gas, drain, duct, electrical and controls reconnections; identify ventilation accessories.
  • List BAS points/gateway/licenses, alarm and refrigerant-detection interfaces, factory inclusions and required functional tests when applicable.
  • Price recovery labor, consumables, handling, transport and disposal; retain the receiving/recovery record.
  • Separate labor person-hours from crane hours and tenant outage; include paid preparation/travel.
  • Assign startup, airflow/ESP and accessory acceptance records, weather-dependent return work and maintenance handover.
  • Record equipment/adapter/crane quote dates, freight, tax, expiry and exclusions; reconcile duplicate inclusions.
  • Identify permit/design fees, temporary service, overtime, crane delay/cancellation terms and known scope additions; approve the final bid boundary.

Source review: November 5, 2026. Update log: rechecked seller/OEM/rental evidence and all calculations; clarified permit scope, crane allocation, R-32 interfaces and startup acceptance, including weather-dependent return work.

Reference calculations: worked installed cost, shared crane allocation and dated rate register.

How to cite this page: Anvilfield, Commercial RTU replacement cost by ton: equipment, crane and curb tables, 2026, https://anvilfield.com/field-guides/hvac/rtu-replacement-cost-by-ton-installed-scope/.

Related tools

Next step: Find multi-unit rooftops

FAQ

How much does commercial rooftop unit replacement cost by ton?

Anvilfield's November 2026 central estimates are $4,972, $4,462 and $4,232 per nominal ton for the defined 5-, 10- and 20-ton gas/electric replacements, before tax. Table A gives the full scope and ranges.

What is a 10-ton RTU installed cost breakdown?

The worked Anvilfield estimate totals $44,617 before tax: $21,470 equipment, $5,440 labor, $1,060 crane and $7,300 other allowances, plus 10% contingency and 15% markup. The method note preserves the exact equipment inputs.

How much do a rooftop HVAC crane and curb adapter cost?

The 10-ton case carries Missouri Crane's $1,060 published minimum and a separate $1,800 Anvilfield adapter purchase allowance. Installation labor is counted elsewhere; the adapter amount is an estimate, not a supplier quotation.

What does multiple-unit replacement save in mobilization?

Four comparable removal/set cycles inside one four-hour crane mobilization save an Anvilfield-estimated $3,180 in crane charges versus four separate $1,060 visits. Table F assumes one setup, ready equipment and prepared crews.

Does a 10-ton RTU need a 10-ton crane?

No. Cooling tons describe thermal capacity; crane selection follows configured load weight, reach, radius and the rated-capacity chart, as addressed by OSHA 29 CFR 1926.1417(o).

Can the existing curb be reused?

Price reuse after dimensions, duct arrangement, condition, structural support and the selected unit's attachment requirements are confirmed. Table G's compatible-curb alternate retains a gasket allowance and the other connection work.

Are controls and electrical upgrades included?

The worked estimate covers basic controls and short reconnections. New feeders, service upgrades and BAS integration require separate measured quantities and pricing.

How long does an RTU replacement take?

Anvilfield's 10-ton schedule uses two field workdays plus advance preparation, 64 paid person-hours and a 30-hour shutdown-to-release window. The crane carries a separate four-hour portal allowance; Table J gives the staffing and acceptance sequence. Weather-dependent acceptance or a specified seasonal return visit adds time and labor.

Does equipment price include startup and disposal?

The listed equipment prices buy the units. The installed estimate separately includes startup labor, refrigerant recovery, consumables, transport and disposal in Tables H and I.

Should maintenance or replacement be priced first?

Confirm the repair-or-replacement decision from condition and operating needs, following the DOE decision-tree sequence. Compare complete capital scopes separately from recurring maintenance fees.

Why are two RTU replacement quotes so different?

Model/options, feeder or BAS scope, curb/roof work, access, freight, tax and acceptance tests change the installed work. Reconcile Table C's scope lines and each allowance before comparing totals.

Does a heat-pump RTU replacement cost the same as gas/electric?

Price the conversion as a separate selection with its equipment, backup heat, feeder capacity, controls and condensate/defrost scope. The gas/electric budget rows cover their stated configurations.