HVAC
Commercial RTU replacement cost by ton: equipment, crane and curb tables
Compare installed 5-, 10- and 20-ton gas/electric replacements from equipment prices, measured connection allowances, paid labor and shared crane logistics.
Direct answer
Anvilfield estimates commercial RTU replacement at about $22,000 to $27,000 installed for 5 tons, $41,000 to $48,000 for 10 tons, and $79,000 to $90,000 for 20 tons, before tax, for the gas/electric configurations and accessible-roof scope priced November 5, 2026. Central budgets are $24,861, $44,617 and $84,646, built from HVAC365 equipment listings, St. Louis crane rates published by Missouri Crane, and stated Anvilfield labor and material allowances for curb adaptation, connections and startup. Equipment alone costs about $9,803, $21,470 and $43,954 respectively; the installed dollars per ton come from pricing the complete job.
On this page
How much does commercial RTU replacement cost by ton?Which 5-, 10- and 20-ton jobs are comparable?What does equipment-only pricing leave out?Dated equipment, labor and material rate registerHow much does an RTU crane mobilization cost?How do multiple RTUs share one crane mobilization?What do curb reuse and curb adapters add?Which connection and roof quantities belong in the estimate?How many crew-hours and startup hours are included?Worked example: what does one 10-ton replacement cost?What changes the range and the final bid?Which equipment and refrigerant differences change scope?Field checklist: what must be verified before firm pricing?Open the related tool for the calculation, checklist, or packet.
FieldOS by AnvilfieldOffline-first FieldOS for job photos, proof packets, property memory, calculations, teams, billing, and owner-ready reports.How much does commercial RTU replacement cost by ton?
Use the capacity table for an accessible-roof gas/electric replacement with suitable existing structure and electrical service. Each case buys one R-32, 208/230 V, three-phase unit, one adapter, limited reconnections and daytime installation. Street closures, structural reinforcement, a new feeder and temporary conditioning require separate scope.
| Nominal cooling | Named selection | Equipment only | Installed range | Central installed estimate | Central installed dollars per nominal ton |
|---|---|---|---|---|---|
| 5 tons | Daikin DSG0603DL00001S | $9,803 | $22,400 to $27,321 | $24,861 | $4,972 |
| 10 tons | Daikin DSG1203DL00001S | $21,470 | $41,050 to $48,184 | $44,617 | $4,462 |
| 20 tons | Daikin DSG2403DL00001S | $43,954 | $79,207 to $90,086 | $84,646 | $4,232 |
Table A reports USD before tax, rebates and financing. Equipment inputs are the 5-ton, 10-ton and 20-ton HVAC365 listings checked November 5, 2026; installed results are Anvilfield estimates using the rate register and calculation below.
Dollars per ton are the result of the estimate. A smaller replacement still needs access, lifting, permit coordination and startup, so those costs do not fall in direct proportion to cooling capacity. The declining per-ton figures here describe these three complete scopes.
The ranges vary labor and purchased allowances within the defined scope. Reprice access changes, conversions and redesigns as measured additions.
Which 5-, 10- and 20-ton jobs are comparable?
A rooftop unit packages heating and cooling equipment for ducted building service. These selections hold gas heat, refrigerant, voltage and the installation boundary constant, using one manufacturer's standard-efficiency, standard-static products. Nominal cooling tons and gas heating input remain separate selections.
DOE's undated Advanced RTU Campaign decision tree asks whether the existing unit is properly sized before procurement. Review load, ventilation and changed occupancy before retaining the old capacity; use the RTU portfolio repair-or-replacement survey to establish the capital work that needs pricing.
| Field | 5 tons | 10 tons | 20 tons |
|---|---|---|---|
| Model | DSG0603DL00001S | DSG1203DL00001S | DSG2403DL00001S |
| Cooling at published rating basis | 57,500 Btu/h | 116,000 Btu/h | 230,000 Btu/h |
| High-stage gas heat input, seller and OEM model tables | 90,000 Btu/h | 130,000 Btu/h | 260,000 Btu/h |
| Refrigerant / voltage / phase | R-32 / 208/230 V / 3 | R-32 / 208/230 V / 3 | R-32 / 208/230 V / 3 |
| Seller label, confirmed against OEM selected-model table | 13.7 SEER2 | 15.2 IEER | 14 IEER |
| OEM base MCA / maximum overcurrent protection at 208/230 V | 28.1 A / 40 A | 53.8 A / 70 A | 98.7 A / 125 A |
| Ventilation accessory estimate | 1 economizer assembly | 1 economizer assembly | 1 economizer assembly |
| Curb treatment | 1 adapter on serviceable curb | 1 adapter on serviceable curb | 1 adapter on serviceable curb |
| Central paid labor | 44 person-hours | 64 person-hours | 96 person-hours |
| Crane budget basis | 4 h at $265/h | 4 h at $265/h | 8 h at $375/h plus $500 hauling allowance |
Daikin's June 2026 SS-DSG3-R32, SS-DSG7-R32 and SS-DSG15-R32 list cooling capacities of 57,500, 116,000 and 230,000 Btu/h for the selected models, marketed as 5, 10 and 20 tons. Use nominal tons for this comparison and selected performance at design conditions for engineering.
Match the full model and option schedule
Record the ordering code, voltage/phase, heat input, refrigerant, fan/static selection, ventilation assembly and controls interface. The 5-ton selection uses SEER2; the larger selections use IEER. Those labels measure different rating bases and cannot be ranked as one efficiency scale.
Table B's minimum circuit ampacity (MCA) and maximum overcurrent protection (MOP) come from pages 16, 13 and 11 of the respective June 2026 sheets. Verify the retained circuit against the ordered options and installed nameplate, including conductor and protective-device suitability. The priced crane classes require confirmation against the actual load chart.
Price a second brand, intermediate capacity or heat-pump alternate by replacing its equipment and affected connections together. A heat-pump conversion can change backup heat, feeder demand, controls and defrost drainage; interpolating a gas/electric dollars-per-ton figure leaves those quantities unresolved.
What does equipment-only pricing leave out?
An equipment purchase buys the ordered cabinet and factory components. An installed replacement also buys removal, a watertight roof interface, working connections and documented startup. Show those direct costs separately from estimating contingency and contractor markup so the owner can compare the same deliverable.
| Scope line | Equipment purchase | Installed replacement budget here | Bid verification |
|---|---|---|---|
| Packaged cabinet and factory-selected components | Included as ordered | 1 unit | Complete model and options |
| Economizer/ventilation accessory | Confirm separately | 1 assembly allowance | Part number, controls and relief requirements |
| Delivery/unloading | Seller advertises qualifying shipping | Ordinary shipping assumed included; receiving in labor | Freight, liftgate, unloading and storage terms |
| Crane/operator/basic rigging | Excluded | Published rental basis | Portal time, minimum, rigging and extra transport |
| Curb adapter/gasket/internal transition | Excluded | 1 adapter assembly | Old/new dimensions, supplier drawing |
| Roofing | Excluded | Local repair allowance | Measured repair and warranty detail |
| Duct, gas, drain, electrical | Excluded | Short reconnections | Lengths, counts and capacity verification |
| Thermostat and control wiring | Excluded unless selected | 1 basic controller plus reconnection | Staging and network boundary |
| Removal and refrigerant recovery | Excluded | Labor plus handling/disposal allowance | Recovery and receiving records |
| Startup and airflow verification | Excluded | Dedicated person-hours | OEM startup form and test scope |
| Design/permit coordination | Excluded | Budget allowance | Actual fee schedule and design scope |
| Temporary service / structural steel / new feeder | Excluded | Separately priced additions | Quantity and owner authorization |
Table C is the bid-leveling matrix: assign a responsible trade and an included quantity to every line. “By others” is complete only when the corresponding work appears in another accepted scope. Separate allowances, fixed-price work and owner-direct contracts so an omitted electrical or roofing package cannot masquerade as a cheaper installation.
Normalize model/options, freight, tax, connections and acceptance tests. Add quoted exclusions before comparing totals, and remove duplicate charges only where written inclusions overlap.
Define completion as the selected equipment and accessories installed, roof interface closed, connections operating, unit airflow/startup recorded and controls tested. Full-building testing, adjusting and balancing (TAB), network integration and a seasonal return visit need additional quantities when specified. The RTU installation and startup guide describes the execution work this estimate purchases.
Record locally adopted code editions, permit fees and the permit authority's requirements for this alteration. Assign ventilation/economizer controls, roof attachment, access and inspection work to priced scope lines. Daikin IOD-1069B, December 2024, directs installation to applicable local codes; the economizer allowance here is an estimating selection, not a universal code threshold.
Dated equipment, labor and material rate register
The equipment amounts below are public seller asking prices checked November 5, 2026. The method note retains source cents for reproduction; obtain purchase-date freight, tax and validity terms. These are seller listings, not negotiated contractor quotes or manufacturer price schedules.
| Input | Rate / amount | Unit and scope | Basis / edition |
|---|---|---|---|
| 5-ton equipment | $9,803 | DSG0603DL00001S, 1 unit | S1, live seller listing, accessed 2026-11-05 |
| 10-ton equipment | $21,470 | DSG1203DL00001S, 1 unit | S2, same date |
| 20-ton equipment | $43,954 | DSG2403DL00001S, 1 unit | S3, same date |
| HVAC/mixed-trade labor budget | $85 | Per paid person-hour, loaded cost | A1, November 2026 estimating input |
| 40-ton crane rental class | $265 | Per portal-to-portal hour, 4-hour minimum; operator/basic rigging included | S4, undated rate page accessed 2026-11-05 |
| 60-ton crane rental class | $375 | Per portal-to-portal hour, 8-hour minimum; engineer/oiler included; counterweight hauling extra | S4, same |
| Counterweight transport, 20-ton job | $500 | One allowance, separate from published rental | A1, not a Missouri Crane quote |
| Accessories/materials/services other than equipment and crane | $5,050 / $7,300 / $11,300 | Per 5/10/20-ton job, itemized in Table H | A1 |
| Contingency | 10% | Direct cost | A1, defined-scope estimating reserve |
| Overhead and profit markup | 15% | Direct cost plus contingency | A1, markup rather than margin |
| Purchase/customer tax | Outside displayed totals | Actual taxable basis and jurisdiction | Obtain job-specific tax treatment |
A1 denotes Anvilfield's November 5, 2026 estimating inputs throughout the tables. The $85 paid-person-hour cost includes wages, payroll burden and benefits, excluding business overhead and profit. Labor productivity, accessory prices, material/service allowances, the $500 transport allowance, contingency and markup are Anvilfield estimates.
Keep each crane vendor's rate, minimum, billing clock and inclusions together. Obtain a new equipment price for a different voltage or heat package.
Retain each item/model, quantity, price source, date/expiry, freight, tax and exclusions. Update installation hours when replacing an assembly allowance. Ordinary freight is assumed included; price special delivery, unloading or storage separately.
How much does an RTU crane mobilization cost?
Missouri Crane's published 40-ton rental rate, checked November 5, 2026, is $265 per portal-to-portal hour with a four-hour minimum and operator and basic rigging included, producing a $1,060 minimum charge before extra services. Its St. Louis rate schedule prices the 60-ton class at $375 per hour with an eight-hour minimum, or $3,000 before required counterweight hauling.
| Company / region | Rental class | Hourly rate | Minimum | Calculated base minimum | Included or additional |
|---|---|---|---|---|---|
| Missouri Crane / St. Louis | 30 ton | $195 | 3 h | $585 | Operator, basic rigging; portal-to-portal |
| Missouri Crane / St. Louis | 40 ton | $265 | 4 h | $1,060 | Operator, basic rigging; portal-to-portal |
| Missouri Crane / St. Louis | 60 ton | $375 | 8 h | $3,000 | Engineer/oiler; counterweight hauling additional |
| Keweenaw / Michigan | 40 ton | $275 | 4 h | $1,100 | Shop-to-shop; rigging additional; $150/day December-March surcharge |
| Central Maine | 40 or 45 ton | $205 | 4 h | $820 | Operator; portal-to-portal; fuel surcharge announced 2026-04-06 |
Crane rental tons describe lifting capacity class; RTU tons describe cooling capacity. OSHA 29 CFR 1926.1417(o), checked November 5, 2026, requires rated-capacity compliance and load-weight verification. Supply radius, reach, configured load including rigging, access, ground support, power-line exposure and staging constraints for the crane selection.
Obtain standard-time, overtime/weekend, travel, waiting and cancellation terms with the rate. OSHA 29 CFR 1926.1402 addresses ground support, and 1926.1408 addresses power-line exposure for equipment operations up to 350 kV. Price required ground preparation, mats, traffic control or utility coordination separately from the crane rental.
What do curb reuse and curb adapters add?
Anvilfield's November 2026 purchase allowances are $1,200, $1,800 and $3,000 for one adapter on the respective 5-, 10- and 20-ton jobs. Installation labor is separate. The allowance buys the assembly, gasket and internal transitions; external duct reconnections and local roof repair remain separate lines.
MicroMetl Form 4153-1P, March 2006 calls for existing-unit identification, measured curb dimensions and labeled supply/return openings. Its described adapter arrangement uses side-by-side ducts rather than concentric ducts. Cooling tons alone cannot identify the opening geometry or establish fit.
MicroMetl's Form 2371-6P requires the installer to verify support for the adapter and replacement RTU and account for the adapter's added external static pressure, so curb compatibility must include structure and airflow as well as dimensions. The installation instructions, copyright 1993 with no separate revision shown supply the installation scope; the purchase allowances here are Anvilfield estimates.
| Curb condition | Purchased assembly | Change in direct cost from adapter case | Revised installed budget before tax |
|---|---|---|---|
| Existing curb compatible and serviceable | 1 replacement gasket kit, $150 A1 allowance, instead of $1,800 adapter assembly | -$1,650 | $42,530 |
| Serviceable curb requiring adaptation | 1 adapter including gasket/internal transitions, $1,800 A1 allowance | $0 | $44,617 |
| Existing curb damaged or unsuitable | New curb, demolition, support, duct modification and roof closure, separately measured and quoted | Replace the adapter allowance and affected quantities with quoted work | Recalculate from the measured alternate |
The compatible-curb alternate changes only the purchased assembly and its contingency and markup; inspection, preparation, sealing, duct and roof work remain.
A damaged or unsupported curb needs a measured new-curb, support and roofing alternate. Use the rooftop support guide and penetration flashing guide to define those interfaces. The base adapter contributes $2,277 after contingency and markup; combined with the crane minimum it contributes $3,618, before separately counted field labor.
Which connection and roof quantities belong in the estimate?
Count assemblies and measure connection lengths before assigning money. Table H contains Anvilfield purchase and service allowances dated November 5, 2026; installation labor appears in Table I. Each dollar amount extends the listed quantity, so the owner can replace an allowance without losing its scope.
| Line | 5-ton quantity / cost | 10-ton quantity / cost | 20-ton quantity / cost |
|---|---|---|---|
| Economizer accessory | 1 assembly / $1,200 | 1 / $1,800 | 1 / $2,500 |
| Adapter with gasket and internal transitions | 1 assembly / $1,200 | 1 / $1,800 | 1 / $3,000 |
| Roof repair materials | 20 sq ft at $15 / $300 | 25 sq ft at $16 / $400 | 40 sq ft at $15 / $600 |
| External duct sealing/connection materials | 2 connections at $100 / $200 | 2 at $150 / $300 | 2 at $250 / $500 |
| Disconnect and electrical reconnection material kit | 1 disconnect, 6 ft connection / $350 | 1, 6 ft / $500 | 1, 10 ft / $900 |
| Controller/control materials | 1 controller, retained wiring / $350 | 1 / $450 | 1 / $650 |
| Gas reconnection materials | 6 ft plus valve/fittings / $200 | 6 ft / $250 | 10 ft / $400 |
| Condensate trap and line materials | 1 trap, 10 ft / $100 | 1, 15 ft / $150 | 1, 20 ft / $200 |
| Recovery consumables, transport and disposal service | 1 retired unit / $350 | 1 / $450 | 1 / $700 |
| Permit/design allowance | 1 job / $500 | 1 / $750 | 1 / $1,250 |
| Truck/material handling expense, excluding paid labor | 1 job / $300 | 1 / $450 | 1 / $600 |
| Total | $5,050 | $7,300 | $11,300 |
The electrical line buys one compatible disconnect and a short reconnection kit. Verify voltage, phase and selected-option MCA and MOP before retaining the feeder. Select conductor size, protective devices and gas diameter for the actual application; the kit prices cover the stated assemblies.
Controls include one conventional controller with viable retained wiring. Price BAS gateways, licenses, graphics, point mapping and network commissioning by their own quantities. List factory-supplied and field-added interfaces separately so a detection assembly or controller is not purchased twice.
The economizer line buys one selected accessory. Ventilation and economizer commissioning also requires a defined scope for relief, demand-control functions and applicable interlocks. Record ordered options and functional tests together; an accessory price alone does not settle the ventilation acceptance scope.
Roof materials cover local repairs around the curb, with labor below. External duct materials cover two connections; expanded duct leakage testing and sealing requires additional scope. Recovery consumables, transport and disposal exclude recovery technician hours already carried in labor.
Localize changes through quantities and selections: hot/humid ventilation or dehumidification, cold-climate heating, coastal protection, high-static fans and roof access. Replace the affected equipment, materials and hours instead of applying an unsupported climate or city percentage to the whole job.
How many crew-hours and startup hours are included?
Anvilfield's November 2026 central estimates carry 44, 64 and 96 paid person-hours at $85 per hour, producing direct labor costs of $3,740, $5,440 and $8,160. Multiply each worker's paid time by the worker count and sum across trades. Four workers for four elapsed hours consume 16 person-hours.
| Work package | 5 tons | 10 tons | 20 tons |
|---|---|---|---|
| Survey, travel, access, planning and receiving | 6 | 8 | 10 |
| Isolation, recovery, disconnection and removal preparation | 6 | 8 | 12 |
| Lift-day HVAC crew, adapter preparation and setting | 12 | 16 | 24 |
| Roof/duct/accessory fitting and utility/control reconnections | 12 | 20 | 34 |
| Startup, airflow/ESP verification, functional checks and turnover | 8 | 12 | 16 |
| Total person-hours | 44 | 64 | 96 |
| At $85/person-hour | $3,740 | $5,440 | $8,160 |
The crane operator is already included in the rental. Startup buys unit-level airflow and external static pressure (ESP) verification plus the ordered model's functional tests; whole-building TAB, BAS integration or seasonal return work need their own hours.
Buy a startup record showing voltage and phase checks, operating amperage, airflow/ESP, heating input and temperature rise, condensate drainage, controls and ordered accessory tests. Use the replacement manual's acceptance conditions. For the selected 20-ton family, Daikin IOD-1069B, December 2024, page 17 limits refrigeration startup below 55°F outdoor ambient to readiness checks, with final checks and calibration above 55°F. Price that return visit when it applies.
Turn paid hours into a tenant outage schedule
Anvilfield's worked 10-ton schedule assigns eight paid person-hours before shutdown, 32 on the lift day and 24 on the completion day. That totals 64 paid person-hours across two field workdays plus advance preparation, with a 30-hour shutdown-to-release window.
| Phase | Paid staffing and duration | Person-hours | Unit availability |
|---|---|---|---|
| Survey, travel, planning and receiving before shutdown | 2 workers × 4 h | 8 | Existing unit remains available |
| Day 1, 08:00 to 10:00, isolation/recovery/removal preparation | 4 workers × 2 h | 8 | Offline |
| Day 1, 10:00 to 14:00, adapter/lift-day work | 4 workers × 4 h | 16 | Offline; crane has a separate four-hour portal allowance |
| Day 1, 14:00 to 16:00, roof/duct/accessory/connections | 4 workers × 2 h | 8 | Offline |
| Day 2, 08:00 to 11:00, remaining connections | 4 workers × 3 h | 12 | Offline |
| Day 2, 11:00 to 14:00, startup/airflow/tests/turnover | 4 workers × 3 h | 12 | Released after acceptance |
| Total | Two field workdays plus advance preparation | 64 | 30 elapsed hours from shutdown to release |
The lift-day phase includes crew preparation while the crane travels and sets up. Place the removal/set inside the quoted portal window. Unit outage runs through recovery, roof closure, connections and acceptance testing.
Work backward from the permitted interruption. Confirm delivery, inspect freight damage, verify the adapter and stage parts before booking the lift. Obtain supplier and fabricator lead times for the ordered package; advertised stock or shipping speed does not establish installation completion. Temporary conditioning and restricted weekend work are separately measured additions.
Worked example: what does one 10-ton replacement cost?
Anvilfield's November 2026 estimate for a Daikin DSG1203DL00001S 10-ton gas/electric replacement is $44,617 before tax, including a $21,470 equipment purchase, 64 paid labor hours, one four-hour crane minimum, an adapter, connections, startup, contingency and markup.
The job uses existing suitable structure and service, one economizer accessory and limited connections. Add purchased equipment, labor, crane and Table H allowances to obtain direct cost. Increase that sum by the contingency percentage, then apply overhead and profit markup to the resulting subtotal.
| Line | 5-ton case | 10-ton worked case | 20-ton case |
|---|---|---|---|
| Equipment | $9,803 | $21,470 | $43,954 |
| Labor | 44 × $85 = $3,740 | 64 × $85 = $5,440 | 96 × $85 = $8,160 |
| Crane | 4 × $265 = $1,060 | 4 × $265 = $1,060 | 8 × $375 + $500 = $3,500 |
| Table H allowances | $5,050 | $7,300 | $11,300 |
| Direct cost | $19,653 | $35,270 | $66,914 |
| 10% contingency | $1,965 | $3,527 | $6,691 |
| 15% markup on direct plus contingency | $3,243 | $5,820 | $11,041 |
| Calculated installed budget, before tax | $24,861 | $44,617 | $84,646 |
| Divide by nominal tons | $4,972/ton | $4,462/ton | $4,232/ton |
Method and rounding
Anvilfield estimates use HVAC365 equipment prices and Missouri Crane rental terms checked November 5, 2026, plus the labor hours and purchased allowances listed here. Direct cost is equipment plus paid labor, crane and the itemized allowances; the budget adds 10% contingency and then 15% overhead and profit markup. The labor and allowance ranges vary within the defined scope, while equipment price and crane selection remain fixed; tax, rebates, financing and separately measured scope additions are outside the displayed totals.
P = (E + H × L + C + A) × 1.10 × 1.15, where E is equipment, H is paid person-hours, L is loaded hourly labor cost, C is crane and A is Table H allowances. Exact equipment inputs are $9,802.82, $21,470.31 and $43,953.96 for 5, 10 and 20 tons. Retain those cents in calculation and round displayed outputs to whole dollars; rounded components can differ from the total by $1.
The 10% contingency reserves money for quantity and productivity uncertainty within the defined work. Known feeder, structural, BAS or temporary-service additions belong in measured line items. The 15% markup equals a 13.04% margin on the contingency-inclusive selling-price basis, calculated by dividing 15 by 115; actual profitability also reflects reserve spending.
Apply tax to the project's actual taxable basis and contracting treatment. Show a confirmed incentive as an owner funding credit after the work price, with financing separate. Neither an assumed rebate nor the owner's payment method reduces the contractor's installation scope.
What changes the range and the final bid?
Anvilfield's low case uses 75% of central labor hours and 80% of Table H allowances; its high case uses 125% and 120%, respectively. Equipment, crane, contingency and markup stay fixed. These are defined estimating settings for the same scope.
| Capacity | Low labor / Table H | Central labor / Table H | High labor / Table H | Low result | Central result | High result |
|---|---|---|---|---|---|---|
| 5 tons | 33 h / $4,040 | 44 h / $5,050 | 55 h / $6,060 | $22,400 | $24,861 | $27,321 |
| 10 tons | 48 h / $5,840 | 64 h / $7,300 | 80 h / $8,760 | $41,050 | $44,617 | $48,184 |
| 20 tons | 72 h / $9,040 | 96 h / $11,300 | 120 h / $13,560 | $79,207 | $84,646 | $90,086 |
Adding 16 paid person-hours at $85 per hour increases Anvilfield's worked 10-ton replacement budget by $1,720 after its stated 10% contingency and 15% overhead-and-profit markup, before tax. Changing only the loaded labor rate to $100 for the original 64 hours adds $1,214 to the installed budget.
| Change | Direct-cost delta | Installed-budget delta | Revised installed budget |
|---|---|---|---|
| Add 16 paid hours | +$1,360 | +$1,720 | $46,337 |
| Change loaded labor from $85 to $100/h, same 64 h | +$960 | +$1,214 | $45,831 |
| Add second crane minimum plus 8 paid hours | +$1,740 | +$2,201 | $46,818 |
| Add $2,000 of defined roof/controls work | +$2,000 | +$2,530 | $47,147 |
| Add second 4-hour crane minimum only | +$1,060 | +$1,341 | $45,958 |
| Increase equipment price 10% | +$2,147 | +$2,716 | $47,333 |
| Share original 4-hour lift among four comparable units | -$795 per unit | -$1,006 per unit | $43,611 per unit |
Waiting crews, repeat travel, cancellation fees and temporary conditioning enter the worksheet as separate costs when incurred. The crane-only row isolates the rental effect.
Request waiting, weather, cancellation and rescheduling terms when booking the crane. An equipment delivery date that slips past the approved shutdown can change staffing and tenant-service costs as well as rental time. Reprice the changed sequence instead of applying the crane-only delta to every delay.
Localize a firm bid by replacing equipment/freight, trade labor rates, permit/design fees and crane terms, then recounting the work. Emergency premiums, structural steel, a new roof opening, feeder upgrades and BAS conversions require revised scope. Keep those known additions visible beside the base price so the owner can decide what changed.
Which equipment and refrigerant differences change scope?
Use the replacement model's instructions for installation and acceptance. Daikin's June 2026 DSG sheets identify the selected R-32 families; Carrier's 48TC-4-16-01SM, May 2014 identifies legacy R-410A equipment. A legacy service manual helps describe removal and existing records; the new model's manual determines its startup tasks.
EPA's sector restrictions page, updated August 28, 2026, distinguishes self-contained products from field-assembled systems. Record equipment classification, manufacture/import date and the applicable transaction when procuring equipment. Apply the category-specific rule rather than borrowing a split-system installation deadline for a packaged RTU.
EPA's safe-disposal guidance, updated March 23, 2026, requires refrigerant recovery before disposal for equipment dismantled on site. Carry technician time, consumables, handling, transport and disposal once each, and retain the recovery and receiving records with the retired unit tag.
| Sources / editions | Verified difference | Estimating action |
|---|---|---|
| Daikin SS-DSG3/7/15-R32, 06/26 vs Carrier 48TC-4-16-01SM, 05/14 | R-32 selected replacement family vs R-410A legacy family | Use selected replacement instructions and required service equipment; price removal separately |
| MicroMetl 4153-1P, 03/06 and 2371-6P | Existing side-by-side geometry, structural support and added pressure loss affect adapter suitability | Measure the arrangement and obtain the selected adapter drawing; no universal pressure-loss allowance |
| NREL/FS-5500-95286, 09/25 vs model-specific instructions | General maintenance guidance is not a substitute for OEM instructions | Carry maintenance handover and records; refer detailed calendar to existing PM guide |
| Daikin SS-DSG7-R32, 06/26, pp. 13 and 86 | Selected-model and installation-family tables give conflicting shipping and operating weights | Obtain OEM/supplier confirmation of the exact configured lifting load before crane selection |
The 10-ton weight conflict affects crane procurement directly. Daikin SS-DSG7-R32, June 2026, page 13 gives the selected model 1,199 lb shipping and 1,161 lb operating; page 86 labels its family row 1,161 lb shipping and 1,233 lb operating, with corner loads totaling 1,161 lb. Obtain supplier/OEM confirmation of the exact configured lifting load; reversing labels or selecting the largest printed number does not resolve it.
The 5-ton sheet gives 607 lb shipping/537 lb operating, and the 20-ton sheet gives 2,290 lb shipping/2,175 lb operating for the selections. Include actual accessories and lifting gear in the applicable load. Daikin IOD-1069B, December 2024, covers R-32 15-25-ton DSG equipment and includes refrigerant-detection instructions: include the selected 20-ton installation's room-area/duct conditions and specified detection/mitigation interfaces in the scope, with their checks in startup. Separate factory equipment from field work.
NREL/FS-5500-95286, September 2025, supplies general maintenance guidance while retaining manufacturer-specific instructions. Hand over the ordered-unit manuals and task calendar through the preventive maintenance program; price recurring maintenance separately from replacement capital.
Field checklist: what must be verified before firm pricing?
Turn each unknown into a recorded quantity, assigned quotation request or priced alternate. An item marked “existing” needs evidence that it suits the replacement selection. Keep the equipment schedule, photographs, dimensioned curb sketch, crane basis, quotes, hours and acceptance scope together under the unit tag.
Replace each allowance with the surveyed quantity or confirmed factory inclusion. Record the price source and responsible trade when reconciling the survey against the proposal.
At turnover, connect the accepted replacement record to the maintenance agreement's scope and exclusions. That keeps future service findings attached to the installed configuration and separates capital authorization from the recurring contract.
- Record unit tag, existing and proposed full model, cooling selection, heat input, voltage, phase and refrigerant.
- Record load/ventilation selection basis and any change in space use; identify who approved capacity.
- Measure curb exterior, supply/return openings, orientation and duct connection arrangement; obtain adapter drawing.
- Record existing curb/roof condition, support review, added assembly weight and roofing repair quantity.
- Record crane location, radius, reach, load including accessories/rigging, approach and setup constraints; request matched rental terms.
- Identify each unit sharing the mobilization, readiness date, removal/set sequence and allocation method.
- Record feeder/disconnect suitability against selected voltage, MCA and MOP; price any replacement separately.
- Count and measure gas, drain, duct, electrical and controls reconnections; identify ventilation accessories.
- List BAS points/gateway/licenses, alarm and refrigerant-detection interfaces, factory inclusions and required functional tests when applicable.
- Price recovery labor, consumables, handling, transport and disposal; retain the receiving/recovery record.
- Separate labor person-hours from crane hours and tenant outage; include paid preparation/travel.
- Assign startup, airflow/ESP and accessory acceptance records, weather-dependent return work and maintenance handover.
- Record equipment/adapter/crane quote dates, freight, tax, expiry and exclusions; reconcile duplicate inclusions.
- Identify permit/design fees, temporary service, overtime, crane delay/cancellation terms and known scope additions; approve the final bid boundary.
Source review: November 5, 2026. Update log: rechecked seller/OEM/rental evidence and all calculations; clarified permit scope, crane allocation, R-32 interfaces and startup acceptance, including weather-dependent return work.
Reference calculations: worked installed cost, shared crane allocation and dated rate register.
How to cite this page: Anvilfield, Commercial RTU replacement cost by ton: equipment, crane and curb tables, 2026, https://anvilfield.com/field-guides/hvac/rtu-replacement-cost-by-ton-installed-scope/.
FAQ
How much does commercial rooftop unit replacement cost by ton?
Anvilfield's November 2026 central estimates are $4,972, $4,462 and $4,232 per nominal ton for the defined 5-, 10- and 20-ton gas/electric replacements, before tax. Table A gives the full scope and ranges.
What is a 10-ton RTU installed cost breakdown?
The worked Anvilfield estimate totals $44,617 before tax: $21,470 equipment, $5,440 labor, $1,060 crane and $7,300 other allowances, plus 10% contingency and 15% markup. The method note preserves the exact equipment inputs.
How much do a rooftop HVAC crane and curb adapter cost?
The 10-ton case carries Missouri Crane's $1,060 published minimum and a separate $1,800 Anvilfield adapter purchase allowance. Installation labor is counted elsewhere; the adapter amount is an estimate, not a supplier quotation.
What does multiple-unit replacement save in mobilization?
Four comparable removal/set cycles inside one four-hour crane mobilization save an Anvilfield-estimated $3,180 in crane charges versus four separate $1,060 visits. Table F assumes one setup, ready equipment and prepared crews.
Does a 10-ton RTU need a 10-ton crane?
No. Cooling tons describe thermal capacity; crane selection follows configured load weight, reach, radius and the rated-capacity chart, as addressed by OSHA 29 CFR 1926.1417(o).
Can the existing curb be reused?
Price reuse after dimensions, duct arrangement, condition, structural support and the selected unit's attachment requirements are confirmed. Table G's compatible-curb alternate retains a gasket allowance and the other connection work.
Are controls and electrical upgrades included?
The worked estimate covers basic controls and short reconnections. New feeders, service upgrades and BAS integration require separate measured quantities and pricing.
How long does an RTU replacement take?
Anvilfield's 10-ton schedule uses two field workdays plus advance preparation, 64 paid person-hours and a 30-hour shutdown-to-release window. The crane carries a separate four-hour portal allowance; Table J gives the staffing and acceptance sequence. Weather-dependent acceptance or a specified seasonal return visit adds time and labor.
Does equipment price include startup and disposal?
The listed equipment prices buy the units. The installed estimate separately includes startup labor, refrigerant recovery, consumables, transport and disposal in Tables H and I.
Should maintenance or replacement be priced first?
Confirm the repair-or-replacement decision from condition and operating needs, following the DOE decision-tree sequence. Compare complete capital scopes separately from recurring maintenance fees.
Why are two RTU replacement quotes so different?
Model/options, feeder or BAS scope, curb/roof work, access, freight, tax and acceptance tests change the installed work. Reconcile Table C's scope lines and each allowance before comparing totals.
Does a heat-pump RTU replacement cost the same as gas/electric?
Price the conversion as a separate selection with its equipment, backup heat, feeder capacity, controls and condensate/defrost scope. The gas/electric budget rows cover their stated configurations.
People also ask
Codes cited in this guide
This guide is written and reviewed against the published standards below. Always confirm the current adopted edition with the authority having jurisdiction.
Sources checked
- S1. HVAC365, 5-ton commercial rooftop listings Checked November 5, 2026. Live seller listing: DSG0603DL00001S, $9,802.82; public asking price.
- S2. HVAC365, 10-ton commercial rooftop listings Checked November 5, 2026. Live seller listing: DSG1203DL00001S, $21,470.31; public asking price.
- S3. HVAC365, 20-ton commercial rooftop listings Checked November 5, 2026. Live seller listing: DSG2403DL00001S, $43,953.96; public asking price.
- S4. Missouri Crane, Crane Rental Checked November 5, 2026. Undated St. Louis rental schedule: hourly rates, minimums, portal billing, operator/rigging and hauling terms.
- S5. Keweenaw Crane Service, published rental rates Checked November 5, 2026. Undated Michigan rental schedule: 40-ton rate, shop-to-shop billing, rigging and winter surcharge.
- S6. Central Maine Crane, Boom Truck Rates Checked November 5, 2026. Live Maine rate schedule; fuel surcharge notice effective April 6, 2026.
- S7. DOE Advanced RTU Campaign, Decision Tree for RTU Replacements or Retrofits Checked November 5, 2026. Undated full one-page decision tree prepared by NREL: inventory, sizing, evaluation and procurement sequence.
- S8. NREL, Rooftop Unit (RTU) Maintenance Guide Checked November 5, 2026. NREL/FS-5500-95286, September 2025, four pages: equipment types and manufacturer-specific maintenance handover.
- S10. Daikin SS-DSG3-R32 Checked November 5, 2026. June 2026, supersedes April 2026: selected-model ratings p. 16; base weights p. 140.
- S11. Daikin SS-DSG7-R32 Checked November 5, 2026. June 2026, supersedes April 2026: selected-model ratings/weights p. 13; conflicting family weight labels p. 86, retained in Table N.
- S12. Daikin SS-DSG15-R32 Checked November 5, 2026. June 2026, supersedes April 2026: selected-model ratings p. 11; weights p. 94.
- S13. MicroMetl Special Roofcurb Adaptor worksheet Checked November 5, 2026. Form 4153-1P, March 2006: adapter dimensional survey, duct configuration, support and pressure loss.
- S14. MicroMetl Curb Adaptor Installation Instructions Checked November 5, 2026. Form 2371-6P, copyright 1993; no separate revision shown. OEM instructions hosted by distributor: support, dimensions, pressure loss and sealing.
- S15. Carrier 48TC sizes 04-16 Service and Maintenance Instructions Checked November 5, 2026. 48TC-4-16-01SM, May 2014: legacy R-410A identity and startup record, p. 151. Applies to the named Carrier equipment.
- S16. EPA, Technology Transitions HFC Restrictions by Sector Checked November 5, 2026. Updated August 28, 2026: product/system classification and category-specific restrictions.
- S17. OSHA 29 CFR 1926.1417, Operation Checked November 5, 2026. Current online text, subsection (o): rated capacity and load-weight verification. Read through the web tool; curl returned HTTP 403.
- S18. EPA, Stationary Refrigeration Safe Disposal Requirements Checked November 5, 2026. Updated March 23, 2026: recovery before disposal for equipment dismantled on site.
- S19. Daikin DSG 15-25 Ton Installation Instructions Checked November 5, 2026. IOD-1069B, December 2024: R-32 15-25-ton DSG instructions; room-area/duct conditions pp. 5-8, startup and below-55°F readiness/return condition p. 17, electrical/airflow checks p. 18, refrigerant-detection system p. 27.
- S20. OSHA 29 CFR 1926.1402, Ground conditions Checked November 5, 2026. Current online text: ground preparation, support and known subsurface hazards. Read through the web tool.
- S21. OSHA 29 CFR 1926.1408, Power line safety (up to 350 kV), equipment operations Checked November 5, 2026. Current online text: work-zone assessment and power-line encroachment precautions. Read through the web tool.