Paving
- In-place asphalt density is reported as percent of Gmm; a common field target is 92 to 93 percent of Gmm, about 7 to 8 percent air voids.
- Percent of Gmm equals core bulk specific gravity (Gmb) divided by theoretical maximum (Gmm, the Rice value), times 100; run Gmm on the day's mix.
- Each extra 1 percent of air voids costs roughly 10 percent of pavement service life, per long-standing agency research.
- Cores are the referee and settle acceptance; gauges only estimate density and must be correlated to cores, and the core wins disputes.
- The longitudinal joint is tested and paid separately, often against a minimum near 90 percent of Gmm, because it runs lean and fails first.
Codes ASTM D2041, ASTM D2726, ASTM D2950, ASTM D979
Paving
- Field density target on a dense-graded asphalt mat commonly runs about 92 to 93 percent of Gmm, set by the agency spec.
- Asphalt yield runs roughly 110 lb per square yard for each inch of compacted thickness, so a 2-inch lift is near 220 lb/SY.
- Tack coat must break (water evaporated, color turned black) before the mat covers it, or trapped steam causes a debonding slip plane.
- Most specs require a surface and air minimum near 40 to 50 degrees F for surface courses; the compaction window sets the real limit.
- Probe mat temperature behind the screed, not the truck ticket, because compaction starts from the temperature in the mat.
Codes ASTM D2041, ASTM D2726, ASTM D2950, ASTM D979
Paving
- Saw contraction joints to one quarter to one third of slab depth (D/4 to D/3); early-entry saws cut shallower, often near 1 in on slabs up to 9 in.
- Saw timing: conventional wet saw about 4 to 12 hours after placement, early-entry (green) saw about 1 to 4 hours, before random cracking starts.
- Space contraction joints at roughly 24 to 36 times slab thickness (2 to 3 ft per inch); keep panels under 1.5 to 1 length-to-width.
- Dowels are smooth, cross transverse joints, transfer load and slide; tie bars are deformed, cross longitudinal joints, hold lanes together and do not slide.
- Cure with white-pigmented ASTM C309 liquid membrane compound right behind texture, about 1 gallon per 200 sq ft, two coats on tined surfaces; open to traffic on measured strength (often 350 to 450 psi flexural), not the calendar.
Codes ASTM C1074, ASTM C309, ASTM C39, ACI 325, ACI 330
Paving
- Aggregate base is commonly compacted to 95 percent of modified Proctor maximum dry density near optimum moisture; subgrade top often 95 percent, deeper fill about 90 percent.
- The project geotechnical report and earthwork specification set the actual targets and name which Proctor governs, so confirm before rolling, never assume.
- Modified Proctor (ASTM D1557) uses roughly 4.5 times the energy of standard Proctor (ASTM D698), giving higher density at lower optimum moisture.
- Proof rolling drives a heavy loaded vehicle, often a 20 ton tandem dump truck, slowly over the surface to reveal soft areas by pumping and rutting.
- The accepted base is a hold point: do not pave until density tests and proof roll pass and are documented, because buried defects are expensive.
Codes ASTM D1556, ASTM D1557, ASTM D6938, ASTM D698
Paving
- Crack seal working cracks that move more than about 1/8 in with flexible hot-pour sealant; fill non-working cracks with stiffer asphalt emulsion.
- Never seal or coat alligator cracking; it is base fatigue failure that needs full-depth patching, then preserve sound pavement around it.
- Apply sealcoat as two thin coats at roughly 0.15 to 0.22 gallons per square yard total; two thin coats outlast one heavy coat.
- Sealcoat needs at least 50F surface and air temperature, no rain about 24 hours before and after, 24 hours before foot traffic, 48 before vehicles.
- Run the lot sequence crack seal, patch, sealcoat, stripe; rate condition with PCI (0 to 100, ASTM D6433) where above about 70 is preservation territory.
Codes ASTM D6433, ASTM D6690