ANVILFIELD Try FieldOS

Concrete

Concrete pumping and placement field guide: boom and line pumps

When the truck can't reach, you pump. Boom or line, the pumpable mix, priming, blockages, power-line and hose-whip safety, and the continuous pour that beats a cold joint.

Concrete PumpingBoom PumpLine PumpACI 304.2RConcrete

Direct answer

Concrete pumping moves the mix from the truck to the placement through a pipeline when the truck cannot reach: the high pour, the far pour, the tight pour. A boom pump uses a truck-mounted arm; a line pump pushes through hose laid by hand. The mix has to be designed to pump, and the project spec controls.

Key takeaways

  • A boom pump carries the line overhead from a truck-mounted arm (reach roughly 56 ft to 200+ ft); a line pump pushes through hand-laid hose for tight, low-volume access.
  • Pumpable mix runs about 4 to 6 in slump with coarse aggregate under about a third of the smallest line inside diameter; never add water at the pump.
  • Prime the line with grout or slurry ahead of the concrete and waste it offsite; skipping the prime strips fines and plugs the first slug.
  • Keep the boom at least 20 ft from power lines up to 350 kV and 50 ft above 350 kV; boom contact is the leading cause of fatal pump accidents.
  • Clear a plug by reversing the pump to relieve pressure, then locate and break the section; never use compressed air in a placing line.

What concrete pumping is, and where it fits

Concrete pumping is how you get the mix from the truck to the placement when the chute will not reach. The ready-mix truck discharges into the pump's hopper, the pump pushes the concrete through a steel pipeline and a flexible end hose, and the crew places it where the truck could never back up to. That is the whole job in one sentence. Everything else is choosing the right pump, keeping the line moving, and not getting anyone hurt.

You pump for four reasons, and most pours hit at least one. The high pour, where the placement is up a wall or on a deck above the truck. The far pour, where the placement is past the reach of the chute, across a building or down into a footing run. The tight pour, where the truck physically cannot get to the forms because of structure, trees, or a fenced lot. And the fast pour, where the volume is large enough that a chute and wheelbarrows would never keep the placement continuous.

Pumping is a delivery method, not a finish. The pump puts the concrete where it goes; the placing and finishing crew still has to consolidate it, screed it, and work it on the right timing. How the surface comes out after the pump leaves is its own discipline, covered in the flatwork finishing guide. What this guide handles is everything from the hopper to the point of discharge.

Boom pump or line pump: which do you need?

A boom pump is a truck with a folding, hydraulic, remote-controlled arm that carries the pipeline overhead to the placement. A line pump, also called a trailer pump, is a stationary pump that feeds concrete through hose and pipe laid out by hand across the ground. The split is reach and volume against access and cost, and the pour decides it before you do.

Boom pumps win on height, speed, and obstacles. The operator swings the arm over walls, forms, and rebar from one setup, places at high volume, and is usually pumping inside half an hour of arriving. Reach commonly runs from roughly 56 ft on a small unit to over 200 ft on the big high-rise machines, and a boom can put concrete on a deck no chute could touch. The trade-off is footprint and money. The truck needs room to set its outriggers, and the day rate is a multiple of a line pump's.

Line pumps win on access, small volume, and tight sites. The pump is compact, you run the hose into a basement, through a gate, or down a hallway, and you place footings, slabs on grade, grout, and shotcrete where a boom can't park. The cost is labor and time. Someone lays out and breaks down hundreds of feet of line by hand, setup runs longer, and output drops as the line gets longer and adds friction. For a residential footing or a confined remodel, the line pump is the right tool. For a 200 cubic yard deck, it is the wrong one.

FactorBoom pump (truck-mounted)Line pump (trailer)
DeliveryHydraulic arm carries the line overheadHose and pipe laid by hand on the ground
ReachVertical and over obstacles, ~56 ft to 200+ ftHorizontal, hose can run several hundred ft
VolumeHigh, often well over 100 cu yd/hrLower, and slows as the line lengthens
SetupOften under 30 min once leveledLonger, hand-laid line takes 1 to 2 hr
Best forDecks, high-rise, walls, big slabsFootings, basements, tight access, grout, shotcrete
CostHigher day rate, needs setup roomLower day rate, more labor to lay out

Reach, access, and the setup before the truck

Reach is not how long the boom is. It is how far the boom can place once it is parked where the truck can actually sit, level, and get its outriggers down on ground that will hold. A boom rated at 140 ft on the spec sheet is worth nothing if the only place it can set up is on the far side of the building from the pour. The reach question and the access question are the same question, and you answer both at the walk before you book the pump.

Walk the site with the pump in mind. Where does the boom truck set up, and is the ground firm enough for outrigger loads or does it need mats and cribbing. Can the ready-mix trucks pull in behind the pump and discharge into the hopper without blocking each other, and is there room for the next truck to stage while one is dumping. Where do the overhead power lines run, because that answer can move the whole setup. The pump operator earns the fee here, reading the site and placing the truck so one setup covers the pour.

Tell the pump company the real numbers, not round ones. The volume, the mix, the maximum reach to the farthest corner, the height, the access width, and the overhead obstructions. They size the unit to that. A pour that needs 165 ft of reach and gets a 125 ft boom is a pour that stops halfway while someone scrambles for a bigger truck, and by then the concrete in the line is going off.

What mix do you need to pump concrete?

A pumpable mix has enough paste and enough well-graded sand to move through the line as a lubricated plug instead of separating into rock and water. The concrete rides on a thin film of paste and fines along the pipe wall, and the whole load behind it slides. Take away the fines or the paste and that film fails, the coarse aggregate locks against the wall, and the line plugs. Pumpability is a property you design for, not something you fix at the chute.

The numbers the trade carries: slump commonly runs 4 to 6 in for a pumped mix, wet enough to flow but not so wet it bleeds and segregates in the line. Coarse aggregate is held small relative to the pipe, a common guide being that the largest stone stays under about a third of the smallest line inside diameter for angular aggregate, and a bit more for rounded. The sand and the fine fraction matter more here than the coarse aggregate, because that is what carries the paste film. A mix short on fines, gap-graded, or harsh and rocky is the classic plugger.

This is the supplier's mix and the project's spec, not a field adjustment. The mix design and the water-cement ratio are set on paper and protected in the field, which is its own guide. The one rule that belongs on every pump job: you do not add water at the pump to make a stiff load flow. Water raises the water-cement ratio, weakens the concrete the engineer specified, and brings on the bleeding and segregation that plug the line worse than the stiffness did. If the load will not pump, the fix is an admixture the supplier approves at the truck, not a garden hose at the hopper.

Mix propertyPumps wellPlugs the line
Slump / flow~4 to 6 in, cohesiveStiff and harsh, or wet and bleeding
Coarse aggregateWell-graded, sized to the lineOversized stone, gap-graded
Sand / finesEnough to carry the paste filmShort on fines, sandy and harsh
Paste / cementAdequate for the line lengthToo lean to lubricate the wall
Field waterSet by the design, protectedAdded at the pump to chase flow

Priming the line, and why you never skip it

Before any concrete goes in, you prime the line. Priming coats the inside of the pipe and hose with a slurry so the concrete slides instead of giving up its own fines to a dry steel wall. Pump grout or a cement slurry through the system first, ahead of the concrete, and keep that prime moving in front of the load all the way to the discharge. The prime is sacrificial. It does not go in the forms.

Here is the mechanism, because it is the reason crews who skip the prime get punished. A dry line has nothing slippery on the wall, so the first concrete through it gives up its paste and fines to coat the steel. What is left in that first slug is rock and coarse sand with no lubrication, and that is exactly the harsh, fines-starved mix that plugs. Skip the prime and you do not save a step. You build a blockage on purpose.

Use a cement-rich slurry or a bagged priming grout, since that puts back the same material the wall would otherwise strip from the concrete. On a long line or a high-rise pump, the prime is richer and there is more of it, and the ACPA has moved away from priming with plain water for those, because thin water priming does not hold a film under pressure. When the prime comes out the end, you direct it to waste, not into the slab. It is watered-down grout that will never make strength, so it goes to the washout area for disposal, not into the structure.

Why does a concrete pump get blocked?

A plug comes from one of three places: the mix, the line, or the operator. Get that framework in your head and you diagnose a blockage in seconds instead of guessing. Most plugs trace back to the mix or to something the crew did, not to the machine.

The mix causes are the common ones. A harsh, fines-short, or gap-graded load that cannot hold its paste film. A wet mix that bleeds and segregates in the pipe, leaving water in one place and stone in another. A load that has gone stiff sitting in a slow line or in the hopper too long. The line causes come next: a dry, unprimed pipe, a section that was cleaned poorly and has set concrete narrowing the bore, a worn pipe, or a bad gasket or coupling that lets grout escape and starves the mix right there. The operator causes are real and avoidable: letting the hopper run low so air gets sucked into the line, pumping too fast for the mix, or stopping the pump long enough that the concrete sets in the pipe.

The tell that you are about to plug is pressure climbing while the concrete stops moving. The pressure gauge spikes, the stroke slows, and the discharge dribbles or quits. That is the moment to stop and deal with it, not to crank the pressure and force it. Forcing a plug builds the pressure that makes the clearing dangerous.

Blockage sourceWhat it looks likeHow you prevent it
Mix: harsh or short on finesPressure spikes early in the pourPumpable design, verify before the pour
Mix: wet, bleeding, segregatingWater and rock separate in the lineHold the spec slump, no water at the pump
Line: dry or poorly primedFirst slug plugs the systemPrime fully, keep prime ahead of concrete
Line: dirty, worn, bad gasketPlug or grout leak at one jointClean fully, inspect pipe and gaskets
Operator: low hopper, air in lineSurging, then a sudden stopKeep the hopper above the agitator, steady feed

Clearing a plug without hurting anyone

Clearing a blockage is where pump pressure becomes the hazard, so the first move is always to take the pressure off. Reverse the pump for several strokes to pull the concrete back and relieve the line, then stop. The reverse alone clears a fair share of plugs by sucking the slug back into the hopper where it can remix. Never start by cranking the pressure up to blow the plug forward, because all you are doing is loading the line with energy that has to go somewhere when the joint lets go.

If the reverse does not clear it, find the plug with the pressure already relieved. Tap along the pipe with a hammer or step on the hose, and the blocked section answers differently: the plug deadens the ring of the steel where the open pipe rings clear. Once you have located it, break that coupling, pull the section, stand it up, and knock the plug out, then reconnect and reprime that section before you pump on.

One rule has no exception: never use compressed air to clear a blockage in a placing line. If the pump's hydraulic pressure cannot move the plug, air will not move it either; it will just compress behind the plug until something fails, and then the plug and the fitting come out like a cannon. Air in the line is its own section below. When you restart after any plug, keep everyone clear of the end hose, because the first thing out is often the pocket of air and slurry behind the cleared plug.

The boom and the power line

A boom contacting an overhead power line is the leading cause of fatal concrete-pump accidents. That is not a statistic to soften. The boom is a long steel conductor on a hydraulic truck, the crew is touching the end hose and standing on wet ground, and a line strike energizes all of it. This is the single hazard that the setup decision exists to prevent, which is why the power lines get found on the site walk, not during the pour.

Treat every overhead line as live and stay clear of it by the distance OSHA requires for the voltage. The ACPA and OSHA call for keeping the boom at least 20 ft from any line up to 350 kV, and 50 ft above 350 kV, and where the voltage or the exposure pushes the required clearance higher, that controls. If the geometry of the pour means the boom cannot place where it has to without coming inside the clearance, you do not thread it. You move the setup, get the utility to de-energize and ground the line, or change the placement method.

Post a spotter whose only job is the boom-to-line distance when the geometry is tight, and brief the crew that if the boom ever does contact a line, nobody touches the truck, the hose, or anyone in contact with it. The operator stays in the cab if they can, and the truck stays put until the utility kills the line. Step off a live machine wrong and the ground gradient gets you. ASME B30.27, the material placement systems standard, and OSHA both treat power-line contact as a recognized, planned-for hazard, which is exactly what it is.

Hose whip, line burst, and air in the line

The end hose moves under pressure, and when something interrupts the flow it can move violently. Hose whip happens when a plug clears suddenly or air in the line releases, snapping the hose hard enough to break bones and knock people off a deck. Nobody wraps the end hose around themselves, nobody stands directly in front of the discharge on a restart, and the person on the hose keeps a footing that lets them ride a surge instead of being thrown by it.

Air in the line is what turns an ordinary restart into a whip. Concrete does not compress, but air does, so a pocket of air behind a plug stores energy and then dumps it the instant the plug moves, throwing slurry and snapping the hose. That is the whole reason compressed air never goes in a placing line to clear a plug, and the reason you keep the hopper full so air is not sucked in during normal pumping. After any stoppage where air may have entered, restart slow and keep the crew back from the tip.

A line burst is the pipe or hose failing under pressure, and worn pipe is the usual culprit (covered under wear below). The defenses are routine: pipe and hose rated for the pressure you are running, every coupling clamp seated and pinned, no kinked or sharp-bent hose that concentrates stress, and crew positioned so a burst at a joint sprays away from people. A clamp that pops at 1,000 psi behind it is not a leak. It is a projectile.

Outriggers, cribbing, and not tipping the truck

A boom pump stays upright because its outriggers spread the load onto ground that holds. The whole reaction to a fully extended boom swinging a load of concrete goes down through those pads, and if one sinks, the truck tips. Tip-overs put the boom into whatever is around it, including the crew and the power lines, so the setup under the outriggers is a primary safety item, not a formality.

Get the outriggers fully extended and pinned, and crib under every pad with material sized to the load, not whatever scrap is on the truck. Soft ground, fresh backfill, a buried trench, or a vault under the slab will all let a pad punch through, so you read the ground before you set, not after the boom is over the pour. Set an exclusion zone around each outrigger and crib stack so nobody disturbs it or parks against it during the pour, and check the pads through the pour, because ground that held at setup can soften as it loads or as water from the washout finds it.

If a pad starts to sink or the truck will not level on the available ground, the pour stops until it is fixed. Relocate, add cribbing, or build up the bearing. The unit that cannot be stabilized does not pump, full stop. ASME B30.27 covers the outriggers and structural setup, and the operator's manual gives the bearing and extension requirements for that specific machine, which is the document that actually governs the setup.

Placing off the pump without segregating the mix

The pump gets the concrete there; how it leaves the hose decides whether it stays a uniform mix or separates on the way down. Place in horizontal lifts and keep the discharge close to the surface, because a long free fall or a high arc out of the end hose lets the coarse aggregate separate from the paste, and you get rock piles in one spot and soup in another. Drop it close, move the hose, and build the placement in controlled layers.

Place into the face of what you already put down, not in scattered piles you drag together later. Dragging concrete with the hose across the forms segregates it and is hard on the crew. Keep the hose moving ahead of the pour line so each batch lands against fresh concrete and consolidates with it. On walls and columns, drop down a tremie or keep the hose down in the form to limit the fall, rather than firing concrete from the top and letting it rattle down the rebar, which strips the paste off the stone before it lands.

Consolidation still has to happen after the pump, with a vibrator on structural work, on the timing the placing crew owns. The pump can place faster than a thin crew can consolidate and finish, and a pour that outruns the finishers is its own failure. Match the pump rate to what the crew behind it can actually handle. What happens to the surface after that, the screed and the float and the trowel, is the flatwork finishing sequence, and the pumped pour feeds straight into it.

Pumping high-rise and elevated decks

Going up changes the pump from a reach problem to a pressure problem. Lifting a column of concrete hundreds of feet takes real pumping pressure, and that pressure is what the pipe, the couplings, and the prime all have to hold. On a tall building the line usually runs as a vertical standpipe up the core or the shaft, fed by a high-pressure pump at the base, with a separate placing boom on the working deck that the standpipe feeds. The base pump moves it up; the deck boom places it.

The prime gets more serious as the building gets taller. There is more line to coat, the pressure is higher, and a thin prime that works on a flat slab will not hold a film up a standpipe, which is why richer grout priming is used and plain water priming is discouraged for high-rise. Select the pipe wall thickness for the pressure, heavier near the base where the pressure peaks, and keep every clamp and gasket rated and seated, because a coupling failure on a vertical line drops the whole column and is dangerous below.

Plan the standpipe and the deck placement so the pour stays continuous as the building rises, and account for the concrete already in the vertical line when you stop, because gravity wants to pull it back down. A non-return setup at the base, or the procedure the manufacturer specifies, keeps the standing column from running back into the pump. This is specialized work, run to ACI 304.2R guidance and the pump manufacturer's procedures, not improvised off a slab crew's habits.

Pumping in cold and hot weather

Temperature works on the concrete in the line, and the line has a lot of surface area against the weather. Hot weather speeds the set, so a load that pumps fine at 60°F can stiffen in the pipe at 95°F before it reaches the discharge, especially on a long line or during a slow stretch. Keep the pour continuous, shade or cool the line where you can, and do not let loaded concrete sit in the pipe during a delay. The same retarding admixtures that protect the placement also buy time in the line, set by the supplier, not the pump crew.

Cold weather slows the set, which sounds helpful and brings its own traps. Concrete moves through the line fine, but everything downstream takes longer, and a line or hose left standing in freezing weather can hold concrete that never gets worked in time. Keep the prime and the first concrete moving so nothing freezes in a section, and protect the pour after placement the way cold-weather concreting requires. The pump does not change the cold-weather rule that concrete stops gaining strength as it approaches freezing.

Either way, the clock is shorter than the slab crew thinks once concrete is in a long line, because the line is more exposed than a form. Stage the trucks so the line is never sitting full and idle in extreme heat or cold.

Big continuous pours: mats and data center floors

Large monolithic pours, a foundation mat, a thick transfer slab, a data center floor placed in big sections, are where pumping stops being a convenience and becomes the only way to keep the placement continuous. The point of a mat or a large structural slab is to place it without a cold joint, and that means the concrete has to arrive and go in faster than a chute could ever feed it. One or more booms working a steady truck rotation is what holds the rate.

The bottleneck on a big pour is rarely the pump and almost always the supply. The pump can take concrete faster than the plant and the trucks can deliver it through real traffic, so the pour plan is a logistics plan: how many trucks in rotation, the cycle time to the plant and back, the staging so a truck is always ready at the hopper, and the backup plant if one cannot keep up. Run the pump faster than the trucks can feed and the hopper runs dry, air gets in, and you risk both a plug and a cold joint at the same time.

Plan these pours to the realistic delivery rate, hold the trucks in a tight rotation, and have a contingency for a breakdown, because a stalled pump or a missing truck mid-mat is how a planned monolithic pour becomes an unplanned cold joint. Sequencing the trucks and the pour rate is exactly the kind of timing pourclock is built to keep.

Cleanout, the go-ball, and washout

When the pour is done, the line is full of concrete that has to come out before it sets, and how you push it out is a safety step, not just a cleaning step. The common method runs a sponge ball, the go-ball or go-devil, through the line behind water or air to wipe the bore clean. The ball pushes the last concrete out the end and comes out behind it, and on an air-blow cleanout that ball exits at high speed, so a ball catcher goes on the discharge and the crew stays clear of the end. People have been hit by a go-ball fired out of an uncaught line.

Reverse-suck cleanout pulls the concrete back into the hopper on machines that allow it, which avoids blowing material out the discharge at all and is the safer method where the pump supports it. Whatever method, knock down the line pressure and follow the pump's cleanout procedure, and never improvise an air blow without a catcher and a clear zone past the end of the line.

Washout goes into a contained area, never into a storm drain, a gutter, or onto bare ground that drains off-site. Concrete washwater is highly alkaline and is regulated under stormwater rules, so the slurry, the prime you wasted, and the cleanout material go into a lined washout pit or a washout container for proper disposal. Letting washout run to the storm drain is the kind of thing that brings a stop-work order and a fine, on top of being avoidable with a pit and a plan.

Wear parts: pipe, hopper, and seals

Pumped concrete is an abrasive slurry under pressure, and it wears the system from the inside out. Steel pipe wears thinnest on the outside of every bend and along the bottom of horizontal runs, where the aggregate scours hardest. That thinning is exactly where a line burst starts, so worn pipe is a safety item, not just a maintenance one. Pipe gets gauged for wall thickness and rotated or retired before it gets thin enough to let go under pressure.

The hopper and the valve are the other wear concentration. The pumping valve, the wear plate and cutting ring on an S-tube machine, the agitator and the grates in the hopper, all take constant abrasion and lose efficiency as they wear: pressure drops, output falls, and grout starts leaking past worn seals. A pump that has lost its valve seal will surge and lose prime, which feels like a mix problem but is a worn-machine problem.

Gaskets and couplings are the cheap parts that cause the expensive failures. A worn gasket leaks grout at the joint, which starves the mix right there and starts a plug, and a clamp that is not rated, seated, and pinned is what comes apart under pressure. Inspect the gaskets and clamps every setup, replace the cheap rubber on schedule, and keep the line couplings matched to the working pressure. These are the parts the operator checks before pumping, and the parts that hurt people when nobody does.

What to document

The pump record ties the placement to the mix and the conditions, so that if a section cures wrong or a joint shows up where it should not, there is something to read back. The pump operator and the placing foreman both have pieces of it, and on a structural or inspected pour the special inspector wants the slump and the placement record regardless.

Capture the pour and date, the pump type and reach used, the mix and the slump as delivered, the placement rate, and the truck rotation. Note the prime method and where the prime was disposed, any blockage and how it cleared, and any delay where concrete sat in the line. If anything about the mix was adjusted, record what the supplier authorized and that no water was added at the pump. That last line is the one that protects the strength result when a break comes back low and someone asks what went in.

Field to recordWhy it matters
Pour ID and dateTies the record to the placement
Pump type and reachBoom or line, and the setup that covered it
Mix and slump as deliveredThe pumpable property, checked at placement
Placement rate / truck rotationShows the pour stayed continuous
Prime method and disposalPrime wasted offsite, not in the forms
Blockages and delaysTime the concrete sat, and how cleared
Mix adjustments authorizedProves no unauthorized water at the pump

Common mistakes

  • Ordering a stiff, harsh, or gap-graded mix that was never designed to pump, then fighting plugs all day.
  • Adding water at the pump to make a load flow, which weakens the concrete and brings on segregation.
  • Skipping or under-priming the line, so the first concrete strips its fines and plugs.
  • Disposing of the prime grout into the forms instead of wasting it offsite.
  • Setting the boom inside the power-line clearance instead of moving the setup or de-energizing the line.
  • Cribbing outriggers on soft or unchecked ground, or not watching the pads through the pour.
  • Free-dropping concrete from the end hose and segregating the mix on the way down.
  • Using compressed air to clear a plug, or standing over the end hose on a restart with air in the line.

Field checklist

0 of 10 complete

Want this checklist to run itself on every job — with photo proof and a signed record crews can hand the customer? That's FieldOS.

Standards and references

The placement and pumping framework comes from ACI. ACI 304.2R, the guide to placing concrete by pumping methods, covers the pump types, the pipeline and couplings, and the proportioning of a pumpable mix, and ACI 304R covers measuring, mixing, transporting, and placing concrete more broadly. These are guides, so they inform good practice rather than mandating a number, while the project specification and the structural drawings set the requirements that actually control the pour.

Pump and placing-equipment safety lives with ASME B30.27, the safety standard for material placement systems, which covers the boom, the outriggers, and the structural and system components, and with the ACPA, whose operator certification and safety guidance cover power-line clearance, blockage clearing, and hose handling. OSHA references these recognized-hazard practices for power-line contact, rigging, and the boom, and OSHA's minimum approach distances by voltage govern the clearance. The Concrete Pump Manufacturers Association and the pump manufacturer's own manual give the bearing, pressure, and operating limits for the specific machine, and that manual controls the unit in front of you.

Mix and materials are governed by the supplier's approved mix design and the project spec, with the slump checked to the methods in the applicable ASTM standards at the point of placement. Where any of these conflict, the stricter of the project specification and the controlling code edition wins. Confirm the current edition of each document, since these get revised on their own cycles.

Units, terms, and equipment

Pumping has its own vocabulary, and the same part goes by different names between the pump crew, the spec, and the manufacturer. Knowing the terms keeps the radio talk clear when a plug is building and the pour is live.

Volume is measured in cubic yards in the US and cubic meters elsewhere, and pump output is rated per hour. Slump is in inches on most US work and millimeters on metric drawings, with a common pumpable range of about 4 to 6 in. Line and hose are sized by inside diameter in inches, and pressure is in psi or bar. The terms below cover the parts and the actions a crew uses on a pump job.

Boom pump
Truck-mounted pump with a hydraulic, remote-controlled arm carrying the line to the placement
Line / trailer pump
Stationary pump that feeds concrete through hose and pipe laid out by hand
Priming
Coating the line with grout or slurry ahead of the concrete so it slides instead of plugging
Plug / blockage
Concrete that stops moving and jams the line, shown by pressure climbing as flow stops
End hose
The flexible discharge hose the crew handles, and the part that whips under pressure
Outriggers / cribbing
The extending legs and the bearing pads under them that keep the pump truck from tipping
Go-ball / go-devil
Sponge ball run through the line on cleanout to wipe the bore clear of concrete
Washout
The contained area for cleanout slurry and waste prime, kept out of storm drains and off-site soil

Related tools

Calculators and readiness checks for this work

Compare your options

FAQ

What is a concrete boom pump?

A concrete boom pump is a truck with a folding, remote-controlled hydraulic arm that carries a pipeline to the placement. The operator swings the boom over forms, walls, or a deck and feeds concrete to the tip hose. Booms commonly reach from about 56 ft to over 200 ft, sized to the pour.

Boom pump vs line pump: which one do I need?

A boom pump places fast over height and obstacles from a truck-mounted arm, best for slabs, decks, walls, and high-rise. A line pump pushes concrete through hose laid by hand, best for tight access, low volume, and footings or basements where a boom cannot set up. Volume and access decide it.

What mix is needed to pump concrete?

A pumpable mix carries enough paste and well-graded sand to slide through the line without segregating. Slump commonly runs 4 to 6 in, coarse aggregate is held small relative to the line diameter, and the fines are controlled. A harsh, gap-graded, or bleeding mix plugs. The mix design and project spec control.

Why does a concrete pump get blocked?

Blockages come from three places: the mix, the line, and the operator. A harsh or segregating mix, a dry unprimed line, a worn or dirty pipe, a bad gasket, or letting the hopper run low all plug it. Most plugs trace back to the mix or to skipping the prime.

How do you clear a concrete pump blockage safely?

Reverse the pump several strokes to pull pressure off the line, then stop. Find the plug by tapping the pipe; the blocked section sounds dead against the open pipe. Break that coupling, clear the section, and reconnect. Never use compressed air to blow a plug, and never stand over the end hose on restart.

How far does the boom have to stay from a power line?

Keep the boom clear of every overhead line by the distance OSHA sets for the voltage, and treat the line as live. The ACPA and OSHA call for at least 20 ft of clearance for pump booms on lines up to 350 kV, and 50 ft above 350 kV. A boom contacting a power line is the leading cause of fatal concrete-pumping accidents.

Can you add water at the pump to make concrete flow?

No. Adding water at the pump to chase a stiff load raises the water-cement ratio, weakens the concrete, and brings on the bleeding and segregation that plug the line worse. If the mix will not pump, fix it at the truck with an admixture the supplier approves, not with a hose.

What is priming a concrete pump line?

Priming coats the pipe walls with a slurry or grout so the concrete slides instead of giving up its fines to dry steel. You pump the prime ahead of the concrete and waste it offsite, never into the forms. Skip the prime and the first concrete strips its fines and plugs the line.

How much concrete can a pump place per hour?

Output depends on the pump, the mix, and the line. A truck-mounted boom can place well over 100 cubic yards an hour on an open pour, while a trailer line pump runs lower and slows as the line lengthens. Plan truck supply to the realistic rate, not the rated maximum.

People also ask

Codes cited in this guide

This guide is written and reviewed against the published standards below. Always confirm the current adopted edition with the authority having jurisdiction.

ASME B30.27ACI 304.2RACI 304R