ASD / VESDA
ASD, or aspirating smoke detection, must be specified at the sampling holes as well as at the detector; VESDA is Xtralis's detector brand. Air from a small smoke source mixes with cleaner samples before reaching the chamber, so chamber sensitivity alone cannot describe installed performance. Xtralis's VEP-EBTI Class A configuration pairs hole sensitivity better than 1.5% obscuration per metre with transport under 60 seconds. Model suffix, regional approval and pipe calculation belong beside those numbers.
Aspirating smoke detection, the active method that draws air through sampling pipe to a high-sensitivity detector; VESDA is a common brand
How sampling-hole sensitivity changes with airflow
Xtralis's September 2023 VEP-A00-UL Product Guide makes sampling-hole sensitivity a calculated result of the airflow entering each hole. Compare the least sensitive hole with the required detection performance, then retain that hole's location and the ASPIRE calculation revision in the acceptance record. An average across the network would hide its weakest sampling point.
Xtralis's VEP-A00-UL Product Guide recommends at least 50% hole balance, expressed as a sensitivity ratio no worse than 1:2, and identifies 70% as a tighter target. Its older VEP engineering specification, 29712_07, instead specifies a 70% minimum. A submittal therefore needs the document revision and model approval beside its balance criterion; a bare 70% note conceals which requirement was selected.
VEP-EBTI sensitivity and transport limits
Xtralis installation instruction 48041_A3 pairs each VEP-EBTI detection class with both a sampling-hole sensitivity and a transport limit. The values below describe that product's EN 54-20 configuration and are verified in ASPIRE; a fast transport result cannot compensate for an insufficiently sensitive hole.
BSI lists BS EN 54-20:2006 as the current aspirating-detector standard. NFPA lists the 2025 edition of NFPA 72 as current for fire alarm systems; the adopted edition governs the installation. Neither publication's name replaces the detector's model-specific approval and instructions.
| VEP-EBTI class | Required hole sensitivity | Smoke transport time |
|---|---|---|
| A | Better than 1.5% obscuration/m | Less than 60 seconds |
| B | Better than 3% obscuration/m | Less than 90 seconds |
| C | Better than 8% obscuration/m | Less than 110 seconds |
Use the airflow baseline to interpret a fault
For its EN 54-20 flow-monitoring configuration, Xtralis 48041_A3 sets minor low- and high-flow thresholds at 85% and 115%, with ASPIRE-predicted detector flow greater than 20 litres per minute. On a 40 L/min reference flow, those percentages correspond to 34 and 46 L/min. These calculations describe airflow supervision, not smoke alarm thresholds.
Save the original and revised airflow baselines with their pipe calculations after network changes. A freshly normalized 100% reading can describe a different physical flow than the commissioning baseline. Use the aspirating detection field tests with the matching model limits, and keep measured transport time separate from programmed alarm delay.
Distinctions
- Detection class versus alarm stage
- Assigning a Fire 2 relay does not establish Class A sensitivity. The class concerns the sampling network's approved detection performance; the relay assignment belongs to the programmed response. Record both to connect detection evidence to the cause-and-effect sequence.
Frequently asked questions
Does a lower detector threshold make every sampling hole equally sensitive?
Compare ASPIRE's individual hole results. A lower chamber threshold changes the alarm setting, but it leaves unequal air contributions from the holes in place; it does not balance the pipework.
Which VESDA document should accompany the submittal?
Use the product guide for the exact suffix and regional approval, the matching installation instruction, and the calculated network report. A family brochure omits configuration limits.
Sources checked
- Xtralis: VESDA-E VEP-A00-UL Product Guide, 35710_A5, September 2023
- Xtralis: VESDA-E VEP-EBTI installation instructions, 48041_A3, February 2021
- Xtralis: VESDA-E VEP Engineering Specification, 29712_07, November 2018
- NFPA 72: National Fire Alarm and Signaling Code, current 2025 edition
- BSI: BS EN 54-20:2006, current release of Aspirating smoke detectors
Also defined as
- Aspirating smoke detection, which actively draws air through sampling pipe for very-early warning; VESDA is a common brand