Single vs double interlock

Single-interlock pre-action permits the detection system to release water while sprinkler piping still holds its normal air pressure. An electric/pneumatic double-interlock arrangement also requires pressure loss in that piping. The second input therefore proves a pressure condition, not that a sprinkler sensed heat; pipe damage can produce it too. Read the trim schematic with the signal history to distinguish detection, pipe-pressure loss and actual valve release.

Single admits water on detection alone; double requires both detection and a fused sprinkler head before water enters the pipe

Used across 2 Anvilfield field guides, most in Datacenter.
Updated

What happens with detection alone or low pipe pressure?

Viking's Preaction System Manual bases single-interlock admission on the detection release, while electric/pneumatic double interlock needs both the detection release and loss of sprinkler-pipe pressure. The table describes valve admission from the normal set condition, with each input active as listed. It does not describe discharge through a closed automatic sprinkler.

Inputs presentSingle interlock admits waterElectric/pneumatic double interlock admits water
Neither inputNoNo
Detection release onlyYesNo
Sprinkler-pipe pressure loss onlyNoNo
Detection release and sprinkler-pipe pressure lossYesYes

Two interlocks do not necessarily mean two smoke detectors

Viking's Preaction System Manual distinguishes electric/pneumatic double interlock, with a pneumatic actuator in the release arrangement, from electric/pneu-lectric double interlock, where a pressure switch supplies the second electrical signal. Both use a detection condition and a sprinkler-piping pressure condition, but they implement the second condition differently.

Cross-zoned detection describes how detection signals are combined. It is a different question from whether loss of sprinkler-pipe pressure is also required. Write each input by function on the cause-and-effect matrix instead of treating two detectors as a complete description of double interlock.

A pipe leak can supply the pneumatic condition

With detection present and pressure lost through damaged piping, a double-interlock arrangement can satisfy both release conditions even though no sprinkler has opened from heat. The pneumatic input does not identify the physical reason for the pressure loss.

This is why an unexplained low-air condition remains a system defect while water is still held back. The suppression systems comparison covers the choice between protection strategies. The release record must additionally show whether the pressure condition arose before, during or after the detection event.

The same interlock name can require different air settings

Viking F_070889, revision 01 of June 2025, requires at least 30 psi pneumatic pressure for its electric/pneumatic double-interlocked arrangement when the maximum water supply is 175 psi or less. For water supply above 175 psi through 250 psi, that Viking sheet requires at least 50 psi pneumatic pressure.

The sheet assigns low-air supervisory operation at 25 psi for the first range and 45 psi for the higher-pressure range. A water-supply change from 160 psi to 200 psi crosses the manufacturer's stated breakpoint; carrying the old air-setting schedule into the altered supply condition would misidentify the required configuration.

Attach the valve model, trim revision and maximum water-supply condition to the settings record. The words double interlock alone are insufficient to reproduce those settings, and values from another valve family do not establish them.

Frequently asked questions

Does double interlock remove the need to repair an air leak?

No. An air leak can provide the pressure-loss input and consume the separation the second interlock was intended to provide. Restore the documented supervisory condition through the system's impairment and service process.

What should the acceptance record identify?

The detection input, pneumatic input, release mechanism, supervisory thresholds and observed sequence. Name the actual signals and devices so the record distinguishes detection logic from sprinkler-piping supervision.

Sources checked

Where this shows up

Next step: Track fire-control upgrades

Back to the full field glossary