Field glossary · business
Backlog
Backlog is contracted work still to be performed, expressed as remaining contract value, work hours, or months at a stated revenue rate. A backlog figure needs a reporting date and a consistent denominator. Six months of backlog means six months at the revenue rate used in the calculation; it does not establish that every crew has six uninterrupted months of scheduled work.
Work under contract but not yet built; sureties limit it against your capital
The denominator changes the months reported
ABC’s published Construction Backlog Indicator methodology converts backlog to months by dividing current backlog dollars by prior fiscal-year revenue and multiplying by 12. A contractor with $2.4 million of remaining work and $4.8 million of prior-year revenue reports six months on that basis.
ABC South Texas’s 2026 explanation instead demonstrates a trailing-12-month revenue denominator. Both bases convert a contract balance into months, but they can produce different results during rapid growth or contraction. Label the chosen basis in an internal dashboard rather than switching silently between them.
With the same $2.4 million backlog and $6 million of trailing revenue, the result becomes 4.8 months. The contracts did not change; the pace used to express them did. A comparison with another report must first reconcile that pace.
Reconcile awards, production, and cancellations
ABC South Texas describes the backlog numerator as remaining signed contract value, including approved change orders, and excludes unsigned proposals. An estimator’s likely award belongs in the sales forecast until the company’s contract-recognition rule is met.
Use a roll-forward to expose errors: opening backlog plus new signed awards and approved changes, less work earned and canceled scope, equals closing backlog. Starting at $2.4 million, adding $600,000 of awards, earning $450,000, and removing $50,000 of canceled scope leaves $2.5 million. Collections do not replace earned work in this calculation; unpaid completed work belongs in receivables.
Translate contract dollars into crew demand
A material-heavy equipment package and a labor-heavy renovation can carry the same backlog dollars but consume different field capacity. Pair the revenue measure with remaining hours by trade and scheduled release dates in the business KPI dashboard. This reveals a bottleneck hidden by a company-wide average. A package with 2,000 field hours remaining needs four weeks at 500 productive crew-hours per week. Place those weeks at the project’s release date; dividing dollars by annual revenue cannot show an idle crew waiting for access.
ABC’s national methodology surveys nonresidential contractors monthly and separates commercial/institutional, heavy industrial, and infrastructure work. Use the relevant market comparison and preserve your own project mix. A growing total does not explain whether the added work uses the crew, equipment, or cash that is already constrained.
Distinctions
- Pipeline
- Pipeline includes opportunities that have not become qualifying contracts. Probability-weighting a pipeline produces a forecast, not an interchangeable backlog balance.
Frequently asked questions
Is a maintenance work-order backlog the same measure?
A service department often counts open work orders or estimated labor hours. State that unit explicitly; an hours-based maintenance queue cannot be compared directly with a contractor’s months-of-revenue backlog.
Sources checked
Also defined as
- Signed work not yet performed, measured in dollars or weeks of work ahead