Capacity test

A battery capacity test produces an ampere-hour or constant-power discharge result tied to one row of the manufacturer's rating table. At constant current, 100 A delivered for 6.8 hours is 680 Ah; against an 800 Ah rating under matching conditions, that is 85% capacity. A UPS test specified in watts needs its constant-power data instead. Keep the load, end voltage and starting battery temperature beside the result so the percentage can be checked and repeated.

A timed discharge at a defined rate to an end voltage, measuring delivered capacity against rating

Used across 2 Anvilfield field guides, most in Datacenter.
Updated

Choose the discharge duty before the test load

C&D Technologies identifies its TEL battery ratings in ampere-hours and its UPS ratings in watts. Read the discharge table for the installed model before selecting the tester: an eight-hour Ah rating cannot supply a fifteen-minute constant-power rating by simple division. With constant power, current increases as terminal voltage falls; the load bank must support the entire discharge curve.

C&D recommends repeating the acceptance-test discharge rate where possible. Match the original end voltage and temperature basis as well. Its discharge FAQ warns that pushing below the specified end voltage can reverse cells and damage the battery. Extra minutes obtained below that endpoint do not belong in the rated-capacity comparison.

Calculate ampere-hours without changing the rating basis

For the 800 Ah battery in the opening example, the eight-hour test current is 800 / 8 = 100 A. At the rating's reference temperature and endpoint, 100 x 6.8 = 680 Ah, and 680 / 800 x 100 = 85%. Changing the test current changes the discharge duty, so carry the manufacturer's corresponding rating into the denominator.

A test stopped at the scheduled finish without reaching the specified end voltage establishes at least the delivered output, not the battery's final discharge capacity. The report needs the reason for stopping. A planned time limit, a cell limit and the string end voltage are different termination conditions.

Keep starting battery temperature with the result

C&D Technologies directs battery sizing calculations to its manufacturer temperature-correction factors because available capacity changes with battery temperature. For test interpretation, use the correction method specified for the battery and selected discharge duty. Retain the starting battery temperature, uncorrected output, factor and corrected result together; a later room-temperature reading cannot reconstruct the initial condition.

The UPS battery maintenance program needs the battery model, string arrangement, discharge-table row, current or power, end voltage, elapsed time and recharge record. Those fields make the next test comparable even when a different technician or load bank performs it.

Use the manufacturer's aging trigger

C&D Technologies' maintenance FAQ calls for a capacity test every two years, increasing to annual testing when measured capacity reaches 85% of rating. That 85% is a testing-frequency trigger; it is not an acceptance criterion for a newly installed battery. Keep the acceptance requirement, maintenance trigger and replacement decision in separate report fields.

IEEE lists IEEE 1188-2025 as the active VRLA maintenance, testing and replacement reference, published October 19, 2026, superseding IEEE 1188-2005. Name the edition in the scope and retain it with the battery monitoring records.

Distinctions

State of charge
A state-of-charge reading describes how full the battery is relative to its present capacity. It does not establish how much capacity remains compared with the original rating.
UPS autonomy test
An autonomy test includes the UPS load and conversion path. A direct DC battery test measures the battery at its terminals; keep the measurement boundary explicit when comparing reports.

Estimators building a UPS battery-testing service use past public electrical awards in PorchRocket Bid Control to identify agencies that buy the work.

Frequently asked questions

Can I compare an Ah capacity result with a watts-per-cell rating?

Use the manufacturer's constant-power discharge table at the specified endpoint and temperature. An Ah rating counts charge, while a watts-per-cell test relates delivered power to duration. The current changes during a constant-power discharge, so multiplying one current reading by elapsed time does not recover the delivered charge.

Sources checked

Also defined as

  • A timed discharge at rated load that proves the actual runtime, distinct from a monitor reading

Where this shows up

Next step: Follow battery testing bids

Back to the full field glossary