Construction change directive (CCD)

An AIA G714-2017 construction change directive needs owner authorization within the signatory's spending authority; the architect alone cannot commit additional funds. The directive records the proposed way to value work that must proceed before compensation or time is fully settled. Preserve that proposed method, the contractor's response and any undisputed payment separately, so an instruction to build does not obscure which adjustments remain open.

The owner's written direction to proceed with a change before price or time is settled

Used across 2 Anvilfield field guides, most in HVAC.
Updated

Confirm who authorized the directive

AIA's G714-2017 execution instructions limit an owner's representative to the expenditure that person is empowered to authorize. Verify that authority against the proposed change before distributing the directive. Enter its number, issue date, authorized scope and drawing revision in the change log so a field instruction traces to the correct owner authorization.

AIA's G714 summary identifies A201-2017 and A104-2017 as the contract documents for which the form was prepared. Check the project's actual contract family before treating a document headed CCD as carrying those procedures. A superintendent's field note and an executed G714 create different records even if they describe the same work.

Choose a valuation method that matches the open issue

AIA's G714-2017 instructions describe unit pricing as appropriate when the parties expect agreement on a rate but cannot yet determine the quantity. That is a different uncertainty from not knowing the cost of the work itself. Record the measured units and their acceptance separately from labor used to produce them.

AIA's G714-2017 summary identifies separate fields for the contractor's fee and the definition or determination of reimbursable Cost of the Work. Record both. A fee percentage without a cost base leaves the calculation incomplete, and a subcontract total alone does not identify the permitted markup.

Separate undisputed payment from final settlement

AIA's G714 instructions permit undisputed amounts to enter payment applications before the final determination, supported by written agreement. Track those amounts separately from unresolved cost and time. A payment entry for the agreed portion does not close the directive's remaining items.

Use a directive-specific cost code and cross-reference the affected drawing revision, daily labor, materials, equipment and subcontract records. Add measured, submitted, agreed and billed quantity columns to the field change-order takeoff. Carry prior billings forward as cumulative quantities so a revised takeoff cannot re-enter the same work as a new payment item.

Track the response to the proposed method

AIA directs the contractor to notify the architect whether the proposed adjustment method is acceptable. Log that response and its date beside the directive. Preserve each pricing revision and its supporting quantities, then reconcile the settled adjustments to the closing change order.

Distinctions

Change order
A change order records agreement on the change and its adjustments. A CCD's unsettled items remain identifiable until that agreement is recorded.

Field example

A directive contains 12 additional supports. Nine are measured and undisputed on the current application; three remain pending verification. A later application includes only the newly verified three, bringing the cumulative quantity to 12. Re-entering all 12 as new work would bill 21 units across the two applications, a nine-unit duplication.

Frequently asked questions

Does agreeing to unit pricing settle the number of units?

No. An agreed rate establishes the valuation method. Measured quantity and any contract-time adjustment still need their own disposition in the directive record.

Sources checked

Also defined as

  • Datacenter: An owner-and-architect instrument directing the work to proceed before the price and time are agreed, settled later by change order

Where this shows up

Next step: Prepare the next bid

Back to the full field glossary