Under AIA G701-2017, a change order records an agreed adjustment; under FAR 43.103, the same label also covers an order issued by the contracting officer before its adjustment is negotiated. Treat direction, settlement and incorporation into the contract total as separate register fields. A CO with a zero price adjustment can still change completion time, while an unsigned price proposal establishes only the amount being requested.

A written, signed agreement fixing the change in scope, contract sum, and contract time; the settled change

Used across 3 Anvilfield field guides, most in Datacenter.
Updated

Why a federal change order can precede agreement

FAR 43.103 classifies the issuance of a change order as a unilateral modification signed only by the contracting officer, while a negotiated equitable adjustment is a bilateral modification. A direction and its eventual settlement can therefore have different modification numbers. Cross-reference them so the original instruction remains traceable after the adjustment is agreed.

AIA G701-2017 requires signatures from the architect, contractor and owner; a contractor-signed proposal therefore has a different status from a federal order signed only by the contracting officer. Use the field change-order takeoff guide to connect measured scope to its authorization record, and identify an AIA construction change directive separately.

FAR 52.243-4(a), Changes, June 2007, limits the contracting officer's written change-order authority under that paragraph to work within the contract's general scope. A unilateral document number alone does not establish that an unrelated addition falls within that authority.

When the agreed price adjustment is zero

AIA G701-2017 provides separate selections for increasing, decreasing or leaving unchanged the contract sum and contract time. A scope revision can have an agreed net price of zero while adding days, or reduce the price while leaving the completion date intact. Record the actual combination rather than treating every CO as an extra charge.

An equipment substitution credits $18,000 for the deleted assembly and adds $18,000 for its replacement. The net change is $0. If the agreement also adds four calendar days, the money line stays unchanged and the time line increases by four days. The revised equipment description still belongs in the record drawings.

Reconcile the new contract sum

The G701-2017 calculation separates the original contract amount, earlier authorized changes and the present change. For a $480,000 original contract, prior additions of $32,000 and prior deductions of $7,000 produce a current value of $505,000. A new $12,500 deduction makes the revised contract sum $492,500.

The earlier net change is positive $25,000; the present change is negative $12,500. Entering the cumulative net change of $12,500 as this order's adjustment would apply the earlier changes twice. Reconcile against the executed orders, then carry the resulting value into the schedule of values.

The federal adjustment clock

FAR 52.243-4(e), Changes, June 2007, ordinarily requires the contractor to assert its adjustment right within 30 days after receiving the written change order or furnishing the specified written notice, unless the Government extends the period. The submission describes the proposal's general nature and amount. The clause prescription permits agencies to vary that period, so enter the period actually included in the contract into the change register.

FAR 52.243-4(d) adds a separate limit for changes arising from other written or oral contracting-officer orders under paragraph (b): except for defective specifications, the adjustment excludes costs incurred more than 20 days before the contractor's written notice. That cost lookback and the 30-day adjustment assertion are different clocks. Log the instruction, notice and assertion dates separately.

FAR 52.243-4(f) bars an adjustment proposal first asserted after final payment. A pending negotiation and an unasserted proposal are different statuses: retain the dated assertion alongside the unresolved amount.

Distinctions

Change-order proposal
Proposal COP-14 requesting a $12,500 credit is a different record from executed CO-14 authorizing that credit. Put the proposal identifier in the requested-adjustment field and the executed document identifier in the authorization field so similar numbering does not settle a pending amount.

Frequently asked questions

Does CO always mean change order?

Federal correspondence also uses CO for contracting officer. Write out the role or document in the register heading so a reference to CO approval cannot be mistaken for a numbered modification.

Can an order settle only some directed work?

Yes. G701-2017 excludes directive adjustments until their cost and time have been agreed. Identify the settled scope precisely and keep the remaining directive items visible as unresolved.

Sources checked

Also defined as

  • HVAC: The written, signed document that changes the contract scope, price, or schedule
  • A documented change to scope, cost, or time that the as-built has to reflect and reference