ASI
ASI means architect’s supplemental instruction: a document used to clarify the work or direct a minor change within the architect’s authority. The key decision is whether the instruction affects contract price or time. An ASI number tracks the communication; it does not settle entitlement when a supposedly minor revision adds labor, material, or schedule impact.
Architect's supplemental instruction; clarifies or makes a minor change to the contract documents without, by its terms, changing the sum or time
What G710 is intended to authorize
AIA describes G710-2017 as a form for interpretations, clarifications, and minor changes that do not adjust the contract sum or contract time. It is suitable for documenting a direction whose commercial consequences have already been resolved within that boundary.
A revised mounting height might leave price and time unchanged before layout but require patching, rework, and a replacement finish after installation. The drawing change is the same; the work already completed changes its effect. Record that condition when reviewing the instruction, before authorizing field execution.
Notice comes before the disputed work
AIA’s explanation of A201-2017 §7.4 says a contractor who believes a minor change affects price or time should notify the architect and not proceed as though it were cost-neutral. Under that provision, proceeding without the required notice waives the right to an adjustment arising from the changed work.
Connect the ASI to the affected sheet revision, work package, and notice in the construction document register. A later cost code does not replace timely notice. The useful record explains the actual impact: installed work removed, a changed product, a procurement delay, or a revised sequence.
Moving 24 already-installed devices at six minutes per device adds 144 minutes, or 2.4 labor hours, before patching or finish repairs. Put that quantity and the affected locations in the notice. A direction that changes no material quantity can still have a measurable labor effect.
Choose the document that matches the decision
AIA’s G710-2017 guidance points to G709 for a proposal request, G714 for a construction change directive, and G701 for a change order when the instruction requires a different change-management mechanism. These forms record different decisions rather than successive names for the same document.
A proposal request asks for price or time information. An agreed change order records the resulting adjustment. A construction change directive directs changed work through the contract’s separate process while the parties resolve the adjustment. Keep the instruction and its eventual disposition linked so an open proposal is not mistaken for an approved price.
Close the instruction in the installed record
After the authorized work is complete, carry the installed result into the record drawing and retain the ASI identifier. Where the direction was superseded, mark that disposition rather than leaving two apparently active instructions. The closeout reader should be able to follow the installed detail to the document that ultimately governed it.
Distinctions
- RFI response
- An RFI response answers a question. Its substance can reveal changed work, but the response title alone does not establish an agreed adjustment to price or time.
Frequently asked questions
Does an ASI have to be free of cost?
The AIA minor-change use of G710 assumes no adjustment to price or time. A real cost impact calls for notice and the appropriate contract change process, even when the architect issued the instruction on an ASI form.
Sources checked
Also defined as
- Datacenter: Architect's supplemental instruction, a minor design change directing the work without a cost or time change