Field glossary · process
As-built
An as-built record captures what was actually installed, including departures from the issued design. Its value depends on recoverable evidence: a buried route needs measurable location references, and a changed circuit needs an identifiable endpoint. Separate field observations from assumptions carried forward from design drawings so the final record tells the next crew which information was verified.
The marked-up set showing what was actually built, maintained as the work goes in and used to produce record drawings at closeout
Record buried work from two lasting references
UFGS 01 78 00, revised August 2026, specifies underground utility locations using offsets from two permanent surface features at run ends and changes of direction. Two references make a location recoverable after temporary stakes disappear. A single offset from an unnamed curb leaves both the reference point and direction unresolved.
The same UFGS section calls for the average depth of an underground run and dimensional locations of valves, splice boxes, and similar features along it. Record a dimension before concealment and identify the observation date. A photograph supports the measurement but does not supply a missing scale, elevation reference, or endpoint identity.
A valve record reading “24 ft east of grid A, 18 ft north of grid 1” supplies two named plan references. Add the measured depth and identify whether it reaches the pipe crown, centerline, or invert. A 38-inch cover measurement and a 38-inch centerline depth describe different elevations, even when the plan coordinates match.
A color legend that survives the closeout handoff
UFGS 01 78 00 uses red for deletions, green for additions, and blue for special information in its record-drawing marking scheme. It permits another color scheme when a legend explains it. Those conventions are requirements when the project adopts the specification; they are not a universal meaning of the word redline.
Mark associated plans, sections, and details together. A relocated sleeve shown only on the plan leaves a contradictory section in the same record set. Link each change to its instruction or observation in the drawing-control register, then resolve the conflicting views before closeout.
Make the delivered PDF navigable
The Army-tailored PDF requirements in UFGS 01 78 00 call for parent bookmarks by discipline and child bookmarks for individual sheets. Sheet bookmarks should lead to the actual final sheets, including replacements, rather than retaining the navigation from an earlier issue.
AIA A201-2017 §3.11 requires a current site record of field changes and selections and delivery of that record to the architect for the owner at completion. Keeping the evidence current avoids a closeout reconstruction based on memory. Preserve the marked source set and the issued final version as separately identified records.
Distinctions
- Record drawing
- A record drawing is the compiled deliverable prepared from the available construction information. Identify the extent of field verification rather than assuming that a clean CAD drawing represents a new survey.
Frequently asked questions
Does an as-built cable record need physical dimensions?
Dimensions locate concealed pathways; cable and port identifiers locate logical connections. Preserve both where they are needed, with the endpoint identifiers matching the administration system used for testing and maintenance.
Sources checked
Also defined as
- Datacenter: Records that show what was actually installed and changed, reconciled to the field, not the original design intent