Field glossary · component

Firestop

A firestop is selected as a tested combination of opening, wall or floor, penetrant and sealing components. Read the system's ratings separately: F addresses fire passage, T adds a temperature-rise criterion, and optional L, W and M ratings address air leakage, water and movement. UL's 2024 application guide sets the T-rating temperature-rise limit at 325 F above the initial temperature, so a two-hour F rating alone does not establish two-hour temperature protection.

The separate trade that seals penetrations through rated walls and floors, tested to ASTM E814 or UL 1479

Used across 2 Anvilfield field guides, most in Concrete.
Updated

Read F and T before the supplemental ratings

ASTM E814-26, active as of November 5, 2026, evaluates penetration firestop assemblies using fire exposure and a hose-stream test. UL's 2024 application guide describes T as the time that limits the maximum unexposed-side temperature rise, including the penetrating item, to 325 F above its starting temperature. This is a temperature rise, not an absolute surface temperature of 325 F.

STI's W-J-3180 sheet shows why the two hourly ratings matter: its F rating is 2 hours, while the listed cable configurations carry different T ratings. At an opening, match the wall construction, opening size, cable or pipe type, supports and installed components to the selected system detail before comparing the ratings.

Fireproofing sprayed onto a steel member does not provide the penetrant-specific dimensions and ratings needed for that comparison. Use the structural-fireproofing guide for the member protection and the penetration system detail for the opening.

Read the leakage units beside an L rating

UL Solutions' 2024 Firestop and Joint Application Guide describes L-rating measurements at ambient and/or 400 F air temperatures under a 0.30 in. water-column pressure difference. Preserve the temperature and pressure basis with the leakage result.

The same UL guide reports penetration leakage in cfm per square foot of opening, or cfm per unit for fixed-size opening units. Those denominators are different. A result stated per unit must not be treated as a rate per square foot when comparing systems or assembling the room's leakage information.

Keep the required smoke-leakage classification on the submittal as its own line. The cabling-pathways guide covers penetration selection and records; the L-rating field adds the tested leakage performance that an hourly classification alone does not express.

What does a Class 1 W rating establish?

UL Solutions defines its Class 1 W evaluation as no water passage through the firestop under a 3 ft water head, approximately 1.3 psi, for 72 hours at ambient conditions. This is a specific tested exposure, rather than a general description such as 'waterproof caulk'.

Identify the exact water-rated configuration, including any additional surface seal or component identified in its listing. Water that passes elsewhere through the floor, a sleeve interface or adjoining construction is a different path. Coordinate the rated penetration detail with the floor's water-management details.

Movement needs its own evidence

ASTM E3037-20 standardizes cyclic movement of a penetration system before a fire-resistance test. Its published scope covers relative movement in two distinct planes. Obtain the tested amplitudes and directions for a moving service, then identify the fire test conducted after that movement. UL's guide calls the supplementary movement classification M.

What changes when cable fill increases?

STI's W-J-3180 system sheet, revised April 14, 2016, lists the Series 44+ pathway at 1.5 cfm per module for 1 to 25% visual cable fill and 2.3 cfm per module for 26 to 50% fill, with the permitted cables. Those values apply at both ambient and 400 F conditions in that sheet.

In that STI listing, increasing visual fill from 25% to 26% changes leakage from 1.5 to 2.3 cfm per module. Further increases through the listed 26% to 100% bands retain 2.3 cfm; cable additions do not always change the rating. Two separately compliant modules at 2.3 cfm total 4.6 cfm at the listing's test conditions.

Record the fill band, permitted cable types and module count with the dated system detail. The pipe-penetration guide provides the surrounding inspection workflow; these leakage fields let the room-integrity team identify the tested opening configuration without assuming that the F rating measures airflow.

Frequently asked questions

Does a two-hour firestop automatically stop water?

The hourly rating establishes fire-test performance. Read the W rating and the listed water-resistant configuration to establish the separate water exposure that was evaluated.

Can an L rating replace a clean-agent room integrity test?

UL measures L at a 0.30 in. water-column pressure difference through the listed opening. That result supplies no measurement of the other joints, doors and leakage paths in the room, so it cannot establish whole-room enclosure performance.

Sources checked

Also defined as

  • Datacenter: A rated penetration seal at a pathway through a fire barrier; an identified element under TIA-606 that is the one most often left unlabeled