Plumbing
Pipe penetration firestop and sleeves field guide for plumbers
Protect pipe penetrations in rated walls and floors with the approved firestop configuration. Match the pipe, barrier, opening, sealant or device, required ratings and inspection record.
Direct answer
Protect a pipe penetration in rated construction with the system or other protection permitted by the adopted code and approved documents. Match the barrier, pipe material and size, insulation, opening, annular space, firestop components and required ratings. A tube of fire sealant alone does not establish compliance; its listing controls the installed configuration.
On this page
Firestopping a pipe penetration, and what it puts backHow do firestopping, fireblocking and joint sealants differ?Why a breached rated assembly is a life-safety problemWhat is the difference between an F rating and a T rating?The firestop is a tested system, not a productHow do you find the right UL firestop system?Why does the pipe material matter?The intumescent that crushes a melting plastic pipeFirestop collars and wrap strips for plastic pipeFirestop sealant and caulk for metallic pipeWhich fire sealant should you specify?Mortar, putty, and pillows for larger openingsWhat is the annular space, and why does it have a min and max?How much fire sealant should you order?Pipe sleeves through rated walls and floorsCast-in-place firestop devices in concrete floorsFloor penetrations versus wall penetrationsMembrane penetrations on one side of an assemblyWater and DWV piping through rated shafts and floorsWhat is a firestop special inspection?Labels and the firestop record at the penetrationWho firestops, and leaving the opening rightWhat if no listed firestop system fits?How do you scope a recurring firestop inspection program?Rated shafts and data center penetrationsWhat to documentField checklistCommon mistakesStandards and referencesWhich code and standard editions apply in November 2026?Units, terms, and conversionsMethodologyOpen the related tool for the calculation, checklist, or packet.
FieldOS by AnvilfieldOffline-first FieldOS for job photos, proof packets, property memory, calculations, teams, billing, and owner-ready reports.Key takeaways
- A firestop is a listed, tested system matching the barrier, the penetrant, the firestop material, and the annular space; never an improvised seal or a single product.
- Plastic pipe (PVC, CPVC, ABS, PEX, PP) melts and burns away, so it needs an intumescent collar, wrap strip, or device that expands to crush the pipe shut; sealant alone does not firestop it.
- F rating is hours flame is held back; T rating is hours before the unexposed side rises about 325F, and T is usually equal to or lower than F because metal conducts heat.
- Annular space has a tested minimum and maximum (for example 1/4 in. to 1 in.); too small blocks proper depth, too large was never fire-tested, so the rating is not real.
- UL through-penetration systems sit under category XHEZ; the number reads barrier first (W wall, F floor, C either), then penetrant group, then the unique system number. Test standard is ASTM E814 / UL 1479, inspection per ASTM E2174.
Firestopping a pipe penetration, and what it puts back
Penetration firestopping protects an opening through rated construction using the accepted system for that condition. Fire performance, temperature transmission and air leakage are separate characteristics; verify each rating required for the location.
An unprotected opening can allow fire and smoke to move between compartments. Coordinate the penetration with the approved fire and smoke protection design before cutting the assembly.
The firestop is not a tube of caulk. It is a specific combination of the pipe, the wall or floor it passes through, the firestop material, and the gap around the pipe, tested together and listed as a system. You match the field condition to a system that was tested for that condition. This guide covers how those systems work, why the pipe material changes everything, and what you record so the job survives inspection. Pipe support and slope through the same walls and floors are covered in the pipe hangers and DWV guides.
How do firestopping, fireblocking and joint sealants differ?
Firestopping protects openings in rated construction. Fireblocking interrupts concealed paths within combustible construction. Structural fireproofing protects members such as steel columns. These are different scopes; a fireblocking foam or an intumescent steel coating is not interchangeable with penetration firestop.
A head-of-wall gap is a joint, not a pipe penetration. Joint systems tested to ASTM E1966 or UL 2079 address the joint configuration and specified movement. Perimeter barriers at curtain walls use a different test, ASTM E2307. Select by the opening and assembly first, then the named materials. A tube carrying several test references still needs the applicable system drawing.
Why a breached rated assembly is a life-safety problem
Rated walls and floors contribute to compartmentation. Their penetrations need the protection required for the actual barrier, opening and service.
Record unprotected or altered openings as unresolved conditions and arrange the authorized protection or repair. Keep the opening accessible until system selection and inspection requirements are resolved.
Do not treat a fire-test rating as a promise of an identical duration in every real fire, or an F rating as proof of a particular smoke-leakage limit. Those are different performance questions.
What is the difference between an F rating and a T rating?
The F rating addresses flame passage under the firestop test, including its applicable hose-stream criteria. The T rating also limits the temperature rise on the unexposed side, including the penetrant. The referenced test criterion is a 325 degree F rise, equal to 180.6 degrees C rounded.
Heat can travel along a penetrant while the seal continues to prevent flame passage. Obtain both ratings from the exact system rather than inferring one from the other. W-L-2244, for example, gives different T-rating conditions for its ordinary and movement configurations.
ASTM E814 and UL 1479 are recognized penetration-firestop test references. Use the test and ratings accepted for the project. The adopted code establishes the F- and T-rating requirements and any exceptions; location alone is not a complete selection rule.
| Rating | What it addresses | Selection check |
|---|---|---|
| F rating | Flame performance under the specified test | Required rating and accepted system |
| T rating | Temperature rise as well as flame performance | Required value and applicable exceptions |
| L rating | Measured air leakage | Required smoke-leakage criteria |
| W rating | Water resistance under its specified test | Required water-exposure performance |
The firestop is a tested system, not a product
This is the idea the whole trade turns on, and the one that gets missed most: a firestop is a listed, tested system, not a tube of material you pick off a shelf. A system is the whole assembly tested together. The barrier (the specific wall or floor type and its rating), the penetrant (the pipe, by material and size), the firestop material, and the annular space all have to match what was actually tested.
A listing for a metallic pipe in a concrete floor does not automatically cover plastic pipe in a gypsum wall. Barrier construction, pipe behavior, insulation, movement and installation geometry all affect the accepted system. Use permitted variations only within the listing or approved project detail.
So you do not engineer a firestop in the field and you do not improvise one. You find a published system that matches the condition in front of you, and you install it exactly the way the listing describes, including the parts that feel optional. The depth of the sealant, the size of the wrap strip, the fastener spacing on the collar, the minimum and maximum gap, those are not suggestions. They are what was tested. Build something different and you have a hole with caulk in it, not a rated penetration.
How do you find the right UL firestop system?
Use a current system drawing that matches the field condition. UL identifies through-penetration firestop systems under XHEZ. The designation helps locate the system; the complete drawing establishes its limits.
In W-L-2244, W identifies a wall and L identifies framed-wall construction. The 2000 numeric series identifies nonmetallic pipe, conduit or tubing. The middle letters do not identify the penetrant. Copy the full designation, including any five-digit numeric sequence.
Attach the current system sheet to the submittal and location record. Check the barrier, pipe, insulation, supports, annular space, component identity, depth and ratings against the actual installation.
Why does the pipe material matter?
Pipe material affects heat conduction, deformation and how the opening changes during fire exposure. Those effects are evaluated in the firestop system for the specified penetrant.
Metal pipes conduct heat and can deform or melt under fire exposure. Do not rely on the claim that every metallic penetrant remains intact. Verify the exact metal, size, wall thickness and insulation permitted by the system.
Plastic piping can soften and leave a larger opening. Listed systems address that behavior with their specified sealants, collars, wraps or devices. Closed process or supply piping and vented DWV piping are not automatically interchangeable within a listing.
The intumescent that crushes a melting plastic pipe
Intumescent materials expand when heated. In a listed plastic-pipe system, their placement and restraint provide the tested response as the pipe softens. Expansion temperature and performance are product-specific.
A sealed-looking gap does not prove that the system matches. Some listings use a separate collar or wrap; others permit an intumescent sealant without a collar. Verify the exact configuration.
Install the listed amount, depth, restraint and attachment. Ordinary sealant cannot replace the named intumescent component merely because it fills the visible gap.
Firestop collars and wrap strips for plastic pipe
A firestop collar restrains the specified intumescent material around a penetrant. Its permitted pipe material, diameter, orientation and fasteners come from the system drawing. Do not apply a generic pipe-size cutoff to every collar family.
A wrap strip is the same intumescent idea in a flexible form. You wrap the strips around the pipe and recess them into the opening, often held by the structure or by a steel retainer, so the expanding char fills the annular space and closes the pipe. Some cast-in and pre-fab devices use wrap strip inside a metal housing. The collar and the wrap strip do the same job, and the listing tells you which the system uses and how many strips or what collar size.
On a wall, the usual practice is a collar on each face, because the fire can come from either side. On a floor, the collar typically goes on the underside, where the fire is expected from below, but the system drawing is the authority on placement, fastener count, and pipe size. The two failures with collars are simple and both fail the penetration: leaving the collar off entirely, and using the wrong size or the wrong number of fasteners so the band cannot hold the expanding force.
Firestop sealant and caulk for metallic pipe
For a metallic-pipe system, use the sealant and installation geometry identified in its listing. Matching the annular gap alone is insufficient; pipe type, insulation, barrier, backing and required ratings also matter.
Chemical base and fire response describe different properties. Select the exact product identified in the system, then verify backing, depth and installation conditions. A product's movement or temperature claim does not transfer automatically to every system containing it.
Where backing is required, use the specified material, packing and recess. Check sealant depth during installation and retain that evidence before finishing conceals it.
Which fire sealant should you specify?
Start with the system number, then match the exact product name. Acrylic describes a chemical base; intumescent describes expansion under heat. They are not mutually exclusive: Hilti FS-ONE MAX is a water-based acrylic dispersion with intumescent behavior. Color and an advertised hourly rating do not establish suitability.
A separate collar is not always required. Hilti publishes W-L-2244 with FS-ONE MAX intumescent sealant for specified closed PVC or CPVC piping through gypsum walls. The listed use does not extend to vented DWV piping. Check the complete wall, pipe, support, gap and rating conditions.
Check substrate preparation, application temperature, shelf life, cure conditions and pipe compatibility on the current product data. Do not substitute a generic backer rod for specified mineral wool, or transfer a movement percentage from a product brochure to every listed system.
| Material or system | Selection question |
|---|---|
| Acrylic firestop sealant | Does the listing cover this joint or penetration and its movement? |
| Intumescent sealant | Does the exact system permit this plastic pipe, insulation or cable arrangement? |
| Silicone firestop sealant | Do the listing and product instructions cover the movement and exposure? |
| Collar, wrap or cast-in device | Are the pipe size, attachment and orientation correct? |
| Re-enterable cable system | Can future cable additions remain within the listed fill and closure limits? |
Mortar, putty, and pillows for larger openings
Large or mixed-penetrant openings need systems evaluated for their dimensions and contents. Those systems can use mortar, putty, pillows, sealant or other specified components; opening size alone does not select the product.
Firestop mortar is a cementitious mix you pour or pack into a large opening around the penetrants, often over forming, to build a rated plug that carries the firestop across a wide span. It suits big floor openings and sleeved openings where a lot of area has to be closed. Putty is a moldable, often intumescent material for sealing around penetrants and for small, irregular openings where a gunnable caulk is awkward, and it stays workable so it can be repenetrated.
Firestop pillows, sometimes called bags, are fabric-wrapped intumescent units you stack into an opening, especially in shafts and large multi-pipe or mixed cable-and-pipe openings, because they can be pulled out and reinstalled when a trade adds or removes a penetrant later. That re-enterable quality is why they live in busy shafts. All three are still systems. The opening size, the penetrants allowed, the depth or the stacking, and the rating all come from the listing for that mortar, putty, or pillow assembly, not from filling the hole until it looks closed.
What is the annular space, and why does it have a min and max?
Annular space is the distance between the penetrant and opening edge. Check it around the full perimeter against the selected system's limits. W-L-2244 permits point contact through a 5/8 in maximum gap in its stated ordinary configuration, with additional sealant at point contact.
A gap outside the permitted range needs a different accepted system or an approved correction. Some listings permit eccentric positioning or point contact, while others require a positive minimum gap. Follow the actual system rather than applying a universal minimum.
Measure the finished opening and pipe position before selecting or installing the seal. Record irregular or oversized areas so the system review covers the actual geometry.
How much fire sealant should you order?
Anvilfield takeoff analysis gives 40 W-L-2244 penetrations 151.711 in3 of sealant including the 15 percent purchasing allowance. The case uses a centered 2.375 in outside-diameter pipe in a 3 in opening, with 5/8 in sealant at both wall faces. Confirm that the actual wall, closed piping and supports match the listed ordinary configuration.
The radial gap is 0.3125 in and the sealant volume is 3.298 in3 per penetration. Use measured outside diameter, not nominal pipe size, when checking the gap and material quantity.
At Hilti's published 18.9 in3 cartridge volume, procurement is nine whole cartridges. Price access, preparation, inspection, labels and repairs separately. Recalculate the volume when sleeves, eccentric openings, depths or penetrants change.
| Quantity step | Result |
|---|---|
| One penetration, both faces | 3.298 in³ |
| Forty penetrations | 131.922 in³ |
| Waste allowance | 151.711 in³ |
| Cartridges | 8.03; purchase 9 |
Pipe sleeves through rated walls and floors
A pipe sleeve is a short piece of pipe or a manufactured fitting set through the wall or floor that the service pipe runs inside. Sleeves let the pipe move, protect it from the edge of a cored or poured opening, and on a floor they can be set to stand up above the slab as a curb so water on the floor does not run down the penetration. A sleeve does not firestop anything by itself.
With a sleeve, you still have annular spaces to seal, and now there are two of them: the gap between the service pipe and the inside of the sleeve, and the gap between the sleeve and the opening. The firestop system tells you what gets sealed and how. Some systems firestop the annulus inside the sleeve. Some treat the sleeve as part of the opening. Either way the sleeve is part of the tested assembly, and a sleeved condition needs a system listed for a sleeve, not a system tested without one.
Where the project requires a sleeve curb or water-resistant penetration, use its approved height and sealing detail. A W rating describes the tested firestop condition; it does not replace the floor's complete waterproofing design.
Cast-in-place firestop devices in concrete floors
A cast-in firestop device is located and secured before concrete placement. Its listing determines slab and deck conditions, permitted penetrants and any required finishing components. Verify the actual rating rather than treating every cast-in sleeve as a complete watertight firestop.
Cast-in devices can reduce later drilling when locations are coordinated before placement. Inspect support, position and protection during concrete work, then complete the device's required installation after the pipe is fitted.
The trade-off is planning. The devices have to be laid out and set during the slab work, which means the plumbing layout has to be right before the pour, and a missed or mislocated device becomes a core-and-retrofit anyway. As with everything else here, the cast-in device is a listed system: it covers specific pipe types and sizes, a specific deck and slab condition, and a rating. It is not a universal sleeve.
Floor penetrations versus wall penetrations
Floor and wall penetrations have different exposure and assembly conditions. Select a system explicitly permitted for the actual orientation and barrier, and verify the required T rating and any code exception. Water resistance is a separate project requirement.
A wall can be exposed to fire from either side, so wall systems are often symmetrical, with a collar on each face for plastic pipe and sealant worked into both sides of the annulus where the system calls for it. Walls bring their own variable: the construction. A concrete or masonry wall, a single-layer gypsum wall, and a multi-layer shaft wall are different barriers with different systems, and the gypsum systems care about which layers and how the opening is framed.
Some systems explicitly cover both wall and floor orientations; others cover only one. Confirm that the listed construction, orientation, exposure and ratings match the actual penetration.
Membrane penetrations on one side of an assembly
A membrane penetration breaches only one face of a rated wall or floor-ceiling, instead of passing all the way through. The classic example is a recessed box or a fixture mounted into a rated wall that does not go through to the other side. It still has to be protected so the breach in that one layer does not defeat the assembly.
Check recessed valve boxes and similar openings against the assembly and adopted membrane-penetration provisions. Accepted protection can involve a listed device, tested assembly or applicable code exception. Do not assign through-penetration F and T criteria to every membrane condition.
Water and DWV piping through rated shafts and floors
Plumbing puts a lot of pipe through rated assemblies, and most of it is in the worst places. DWV stacks run up rated shafts floor to floor. Water risers do the same. Branch waste and water lines cross rated corridor and demising walls. Every one of those is a penetration that needs a system, and the shaft penetrations are the ones that matter most, because an unsealed pipe in a shaft turns the shaft into a vertical smoke highway for the whole building.
Match each water, waste or vent pipe to a system that covers its material, size and service. Plastic-pipe protection can use a listed intumescent sealant, collar, wrap or device. A missing component required by that system is a deficiency; the absence of a separate collar alone does not establish one.
Coordinate the firestop with how the pipe is sized, sloped, and supported, because they share the same holes. The DWV venting and pipe sizing guide covers how the stack and branches are sized and sloped through those walls and floors, and the pipe hangers and seismic bracing guide covers how the riser is supported and how it is allowed to move at the penetration. Firestop is the third thing that happens at the same opening, and it has to suit a pipe that may move thermally and may carry water down a floor penetration.
What is a firestop special inspection?
Where required, a qualified independent inspector checks installed penetration firestops under ASTM E2174 and joints or perimeter barriers under ASTM E2393. The accepted inspection plan sets observation and sampling requirements. Do not describe a sampled inspection as destructive verification of every opening.
Determine the special-inspection requirement from the adopted code, occupancy, risk category, building characteristics and project specification. Confirm the applicable trigger with the responsible reviewer before estimating inspection access and repairs.
Record the system, components, gap, depth, attachments and required ratings at each location. Installation photographs support that record but do not replace the observation or destructive sampling required by the inspection plan.
Labels and the firestop record at the penetration
A firestop label is a tag or marking left at the penetration that identifies the system installed, so anyone who comes later, an inspector, the next trade, the owner's maintenance crew, can read what is in the hole without destroying it. Many specs require labeling, and the label typically names the installer, the system number or detail, the rating, and the date.
The reason is maintenance over the life of the building. Penetrations get disturbed constantly. A cable contractor pulls a new run through a shaft, a remodel adds a pipe, somebody cores a new hole next to an old one. If the original system is labeled, the next person knows what they are working in and how to restore it. If it is not, the firestop gets degraded one undocumented change at a time until the rating is fiction.
Backstop the label with a real record. A list of every penetration, its location, the barrier and rating, the penetrant, the system number, and a photo as installed, is what carries the job through special inspection and turns over to the owner as proof. The label is for the wall. The record is for the file. You want both, and you want them to agree.
Who firestops, and leaving the opening right
Assign firestopping responsibility before pipe installation. The pipe trade and firestop installer must agree on system selection, opening geometry, pipe position, supports and the inspection hold. Put the division of work in the approved scope.
Core or frame openings to the accepted system and keep the pipe within its permitted position and annular range. Some systems allow point contact or multiple penetrants; those options need to be present in the actual accepted detail.
Sequence matters too. If insulation, a sleeve, or support steel is supposed to be part of the tested system, it has to be there before the firestop, not added later. The support and movement details are their own coordination, and the pipe hangers and seismic bracing guide covers how the pipe is anchored and allowed to move through the same wall or floor. The crew that says the firestop is somebody else's problem still owns the opening, and a bad opening fails no matter who fills it.
What if no listed firestop system fits?
Hold the location before concealment. Record the actual barrier, dimensions, penetrants, insulation and movement, then request a matching system or a project-specific engineering judgment through the firestop manufacturer and design team. Obtain acceptance through the authority having jurisdiction before installation. An engineering judgment is not a new tested listing. Keep the accepted detail with the location record and arrange the inspection hold point.
How do you scope a recurring firestop inspection program?
Build the scope around locations and access. Separate the initial barrier survey, document recovery, repairs to known systems, investigation of unknown seals and return visits after other trades work. Count inaccessible locations as unresolved, with an access allowance and owner, rather than reporting them complete.
For public plumbing service packages, PorchRocket's Bid Control lists public plumbing bids. Check the issued scope for firestop surveys, repair access and inspection responsibilities before pricing the program.
Rated shafts and data center penetrations
Data centers and other dense, high-value buildings push firestopping hard, because they are full of rated walls and floors and full of penetrations crossing them. The piping side, chilled water, condenser water, makeup water, and drainage, runs large and runs through rated mechanical rooms, shafts, and slab penetrations alongside enormous cable and busway penetrations.
Two things make these jobs unforgiving. The penetrations are constantly changing as the facility is built out and reconfigured, so re-enterable systems, pillows and putty and devices that can be opened and resealed, are worth their cost where the listing allows them. And the consequence of a smoke or fire event is severe, so the inspection and documentation are tight, often with full special inspection and a complete penetration log.
Maintain the location register as services change. Match each alteration to an accepted system and record the completed inspection and repair. A previously accepted penetration needs review when its contents or construction change.
What to document
Keep the installation and inspection record with the penetration location. Photos before concealment help later review, while the approved inspection plan still determines any required sampling or opening of completed seals.
Capture, for each penetration: the location and a mark that ties it to the drawings, the barrier type and its fire rating, the penetrant by material and size, the system number installed, the F and T ratings, the annular space, who installed it and when, and a photo of the installed firestop before it is covered. If a sleeve or cast-in device was used, note that too. The penetrant and the barrier together point to the system, so record both.
| Field to record | Why it matters |
|---|---|
| Location and drawing reference | Ties the penetration to a place and a plan |
| Barrier type and fire rating | Half of what selects the system |
| Penetrant material and size | The other half; plastic vs metal changes everything |
| System number (UL/listed) | Identifies the accepted system to compare with the work |
| F and T ratings | Records the required and achieved system ratings |
| Annular space measured | The fastest tell that it matches the listing |
| Photo as installed, installer, date | Supports traceability and required inspection records |
Field checklist
Want this checklist to run itself on every job — with photo proof and a signed record crews can hand the customer? That's FieldOS.
Common mistakes
- No firestop at all, or a non-tested improvised seal stuffed in the hole.
- Installing a system whose number does not match the barrier, the penetrant, or the rating.
- Omitting an intumescent component required by the accepted plastic-pipe system.
- Annular space outside the tested minimum or maximum from an oversized or off-center opening.
- Ordinary spray foam or general-purpose caulk instead of a listed firestop material.
- Sealant without the required backer, or short of the tested depth.
- Treating a floor penetration like a wall, or ignoring a needed T rating.
- The pipe trade leaving the wrong opening for whoever firestops it.
- No label and no record, so the system cannot be verified or maintained later.
Standards and references
The adopted building code establishes penetration and joint protection, required ratings, permitted exceptions and special inspection. Use the approved system and project documents for the specific opening rather than applying one rating rule to all walls and floors.
ASTM E814 and UL 1479 are penetration-firestop test references. F and T ratings describe different criteria, and supplementary L and W ratings address air leakage and water resistance. ASTM E2174 covers installed penetration inspection; ASTM E2393 covers joints and perimeter barriers.
Use current directory and manufacturer system drawings for the installed condition. Record the full designation, revision and components. When no listing fits, retain the project-specific accepted resolution and its inspection requirements.
Which code and standard editions apply in November 2026?
This guide uses 2024 IBC Sections 714 and 715 for penetration and joint review and Chapter 17 for special inspection. The permit edition, local amendments and approved details govern. Apply the relevant exceptions only to the conditions they actually cover.
For coordinated electrical work, use the 2026 National Electrical Code (NEC) where adopted and the 2023 NEC where that edition remains adopted. The electrical reference basis here is 2023 NEC unless the permit jurisdiction has adopted 2026; verify local amendments before work. Plumbing firestop selection still follows the building assembly and its accepted system.
Current ASTM catalog editions checked are E814-26 for penetration testing, E1966-24 for joint testing, E2174-24 for installed penetration inspection and E2393-24 for joint and perimeter inspection. A newer publication does not automatically replace the edition referenced by the adopted code or contract. Keep that edition and the installed system revision in the submittal.
Units, terms, and conversions
Ratings are in hours; annular gaps and depths are dimensions. Distinguish a temperature rise from an absolute temperature when converting test criteria.
Anvilfield conversion of a 325 degree F temperature rise gives 180.6 degrees C, rounded. UL system designations identify barrier orientation first, barrier construction in the following letters, and penetrant category in the numeric series.
- Through-penetration
- A breach through both sides of a rated wall or floor for a pipe or other item
- Membrane penetration
- A breach in only one face of a rated assembly
- Annular space
- The gap between the pipe and the edge of the opening, with a tested min and max
- F rating / T rating
- Firestop test classifications addressing flame performance and additional unexposed-side temperature-rise criteria
- Intumescent
- Firestop material that expands with heat to crush a melting plastic pipe and fill the opening
- Penetrant
- The item passing through, here the pipe, by material and size
- XHEZ
- UL category code for through-penetration firestop systems in the directory
Methodology
Anvilfield quantity analysis uses a circular annulus: pi/4 x (3 squared - 2.375 squared) x 0.625 in depth x two faces. Multiply the unrounded volume by 40 penetrations and 1.15, then divide by Hilti's published 18.9 in3 cartridge volume and round up. The result is nine cartridges. The case is based on the stated ordinary, closed-piping configuration of W-L-2244; it does not select a firestop for another wall or service.
Temperature-rise conversion uses 325 x 5/9 = 180.5556 degrees C, rounded to 180.6. Subtracting 32 is used for an absolute Fahrenheit temperature, not a temperature difference. The saved AF-VR3 estimate script reproduces both calculations.
ASTM, UL, ICC and manufacturer documents were opened November 5, 2026. Test classifications and published system conditions remain distinct from jurisdiction-specific acceptance and the inspection plan.
FAQ
What is firestopping a pipe penetration?
Penetration firestopping protects an opening through rated construction using the system or other protection accepted under the adopted code. Match the barrier, pipe, components, geometry and required ratings to the approved detail.
What is the difference between an F rating and a T rating?
The F rating addresses flame performance; the T rating also addresses unexposed-side temperature rise. A 325 degree F rise converts to 180.6 degrees C, rounded. Use the values and conditions in the exact system.
Do plastic pipes need a firestop collar?
Only when the accepted system requires one. W-L-2244 permits FS-ONE MAX intumescent sealant without a separate collar for its specified closed PVC or CPVC wall penetration. Other configurations need their listed collars, wraps or devices.
What is a firestop system?
A firestop system is a specific combination of the rated wall or floor, the pipe by material and size, the firestop material, and the annular space, all tested together and listed with a number. You match the field condition to a listed system and install it exactly as drawn. You cannot improvise one and call it rated.
How do I find the right UL firestop system?
Match the actual construction to a current system drawing. In W-L-2244, W identifies a wall, L identifies framed-wall construction and the 2000 series identifies nonmetallic penetrants. Read the full drawing for permitted pipe, gap, components and ratings.
Can I use spray foam or regular caulk to seal a pipe penetration?
Use only materials permitted by the accepted protection detail. A general-purpose foam or caulk label does not establish a rated penetration. A product approved for fireblocking is not automatically approved for penetration firestopping.
What is the correct annular space around a pipe penetration?
Use the selected system's measured gap limits. W-L-2244 permits point contact through 5/8 in in its stated ordinary configuration, with additional sealant at point contact. Other systems have different conditions.
Do floor penetrations need a different firestop than walls?
Use a system explicitly covering the actual floor or wall. Some listings cover either orientation; others cover only one. Check the barrier construction, required ratings, collar placement and any water-resistance requirement.
Who is responsible for firestopping pipe penetrations?
It varies by project. Sometimes the pipe trade firestops its own penetrations; sometimes a dedicated firestop subcontractor does all of them. Either way the pipe trade controls the opening and the annular space, so leave the hole the right size and the pipe positioned to hold the tested gap, or the firestop cannot match a system.
What happens at a firestop special inspection?
The inspector checks the accepted system and required installation evidence under the project's ASTM E2174 inspection plan. That can include observation and destructive sampling. Photographs do not waive the specified inspection method.
People also ask
Codes cited in this guide
This guide is written and reviewed against the published standards below. Always confirm the current adopted edition with the authority having jurisdiction.
Sources checked
- UL: fireblocking versus firestopping
- ICC: 2024 IBC significant changes Penetration and perimeter provisions, slides 56 and 57.
- ICC: Group R firestop inspection provisions 2021 change history; verify the permit edition.
- ASTM E814-26: penetration fire tests
- ASTM E1966-24: joint fire tests
- ASTM E2174-24: penetration inspection
- ASTM E2393-24: joint and perimeter inspection
- UL: firestop penetration numbering
- Hilti: UL W-L-2244 system Closed piping, wall construction, sealant depth and configuration limits.
- Hilti: FS-ONE MAX product data Chemistry, preparation, cure conditions and cartridge volume.
- Hilti: firestop sealant families
- Hilti: engineering judgments
- NFPA: NFPA 70, National Electrical Code 2026 and 2023 editions; confirm local adoption.
- Hilti Firestop Resource Guide: ASTM E814 / UL 1479 test criteria Manufacturer-hosted guide excerpt describes flame exposure, hose-stream testing and the 325 degree F temperature rise. Celsius difference is calculated in Methodology.