ASTM E2174-24 governs site inspection of penetration firestops against approved inspection documents. Coverage is counted by system type and installing contractor, with floor and inspection-area boundaries retained. Published FCIA guidance uses at least 10 percent witnessed during installation, or at least 2 percent destructively checked after installation with a minimum of one per type in each inspection area. The inspection verifies the installed configuration; the approved system supplies its fire-performance basis.

Current edition: ASTM E2174-24 (2024)
Updated

Official publisher page

Applies to

Approved inspection agencies need access to the installation sequence or to completed seals selected for destructive examination. Designers identify the accepted systems, contractors identify who installed each population, and owners receive the corrected inspection record. Connect the register to pipe-penetration locations and cable-pathway openings before splitting the work into sampling areas.

Key topics

Define each system and installer as a sampling population

FCIA's August 2023 inspection webinar defines the sampled type by firestop system and installing contractor. Its E2174 guidance describes observation of 10 percent of each service-penetration system type on each floor during installation. Two contractors installing the same listed system therefore need distinguishable records. Pooling their work under the product name alone loses the installer distinction used in that inspection guidance.

Budget witnessed work or destructive verification

FCIA's August 2023 guidance sets post-installation destructive coverage at no less than 2 percent of each system-and-contractor type, with at least one in each 10,000-square-foot inspection area. Keep floors separate and retain smaller remaining areas in the inspection plan. The IFC's 2025 overview identifies witnessed installation and destructive verification as alternative routes. Price the selected route with access and repair work; photographs of completed seals are not witnessed installation.

Inspection authority stays outside product selection

ASTM E2174-24 states that its practice does not provide a basis for selecting installers or products and does not establish the inspected systems' performance criteria. The accepted inspection documents supply the configuration to be verified. FCIA's presentation also distinguishes inspection from supervising the installer or selecting the system. Resolve a missing approved configuration through the design and approval process before presenting the opening as ready for acceptance.

Measure seal depth at the bond, then record the repair

The International Firestop Council's April 2012 destructive-testing guidance locates sealant-depth measurements at points of adhesion, rather than at the middle of the seal. It also calls for verification of packing type, density, compression, fiber orientation and depth. Use product-specific shrinkage information when comparing cured measurements with a listing's wet application depth. Record the sampled opening and its reinstatement so a compliant seal opened for measurement is not handed over damaged.

How it is used in the field

On a 9,000-square-foot floor, contractor A installs 40 penetrations of one system and contractor B installs 10 of the same system. Applying FCIA's stated 2 percent destructive basis with the minimum of one per system-and-contractor population produces at least two locations: one from each contractor. Taking 2 percent of the combined 50 and opening only one would erase the second population. Under the stated 10 percent observation basis, the corresponding counts are four and one.

Maintain the population register as installation proceeds. Add the floor, location identifier, listed system or accepted judgment, installer, installation date and selected verification route. Mark the sample locations and retain the method used to choose them. If another contractor later completes a group of openings, add that work under its own installer identity rather than quietly expanding the first contractor's accepted count.

Coordinate installation observation while the backing and seal depth remain visible. For post-installation work, provide the access and repair scope associated with the selected sampling plan. The pathway guide addresses cable routes and penetrations; the inspection register should connect those locations to the specific work observed or opened.

Close each sampled location with its measured findings, any correction, the reinstatement after destructive examination and the inspector's disposition. Keep newly installed openings outside the earlier accepted population until their inspection is resolved. The report should identify the boundaries of the work it covers, including floors or areas still awaiting access.

Adoption

New York's 2025 Building Code, Section 1705.18, requires special inspection in high-rise buildings, Risk Category III or IV buildings, and fire areas containing Group R occupancies with occupant loads greater than 250. For penetration systems tested and listed under Sections 714.4.1.2 and 714.5.1.2, Section 1705.18.1 requires an approved agency using E2174. Chapter 35 names E2174-20a. Keep that adopted reference separate from active E2174-24 and the 2023 FCIA sampling explanation when identifying the project's inspection basis.

Frequently asked questions

Is a photograph of every completed seal the same as installation observation?

Photographs identify visible conditions but do not themselves document that the inspector observed the required construction during installation. Report the actual verification method and locations against the accepted inspection plan.

Can all contractors using one firestop system share one sample count?

FCIA's cited sampling explanation identifies type by system and installing contractor. Preserve those populations separately when planning and documenting the specified coverage.

Does E2174 assign a fire rating to the installed product?

The practice verifies installation against inspection documents. Its public significance section expressly excludes establishing system performance criteria; the approved system evidence supplies the required performance basis.