ASTM E814: F and T ratings, leakage, and firestop submittals
ASTM E814-26 tests penetration firestop systems under furnace and hose-stream exposures. Keep flame resistance, reported as F, separate from the T rating's temperature limit: a listing with a 2-hour F result and a 1-hour T result supports different durations for those hazards. Select the required ratings from the governing code and the installed configuration from the listing. Air leakage, water containment, and movement need their own documented results.
Applies to
Firestop manufacturers use the method to develop tested systems; designers specify the required performance; installers and inspectors reconcile the selected listing with the installed opening. It becomes a project requirement through the applicable building-code provisions and construction documents. A laboratory report establishes tested performance, while the approved system detail identifies the installation to reproduce.
Key topics
Read the F and T durations as separate results
ASTM E814-26 identifies F and T as separate ratings, and UL Solutions describes the T criterion as a maximum temperature rise of 325°F above the initial temperature. On a listing reporting F = 2 hours and T = 1 hour, the second hour of flame protection does not supply a second hour of temperature protection. Enter both durations on the penetration schedule, then compare each with the project's required ratings. Keep the tested assembly and penetrant description beside those numbers so the schedule identifies a reproducible system. ASTM rating basis; UL rating definitions
Which penetrations fall outside E814?
ASTM E814-26 leaves out membrane openings in load-bearing walls and those tested within E119 floor-ceiling or roof-ceiling assemblies. A recessed box that stops inside a barrier therefore needs a different review from a pipe passing through it. Mark that distinction on the opening schedule before choosing a submittal route. E814 also does not establish post-fire serviceability: retain an exposed seal's original listing as the starting record for its repair decision, rather than treating an intact surface as evidence of continued performance. ASTM scope
Air, water, and movement need separate evidence
UL Solutions reports L-rating leakage at 0.30 inch water-column pressure difference, using ambient and/or 400°F air. Its Class 1 W-rating test holds a 3-foot water head for 72 hours without passage, then conditions the specimen before fire and hose-stream testing. UL associates the M rating with movement testing under ASTM E3037. These designations answer different questions. A cable opening beside a critical equipment room could need fire, leakage, and water results; record each specified rating with its test conditions instead of accepting an hourly fire rating for all three. UL supplemental ratings
Hose-stream survival is not support-system qualification
The hose stream imposes an impact, erosion, and cooling exposure on the tested assembly. ASTM E814 expressly leaves out forces caused by falling debris or failed cable supports. Keep the firestop detail and the service-support detail coordinated: a compliant seal does not establish that an unsupported tray, pipe, or conduit will remain in the position represented by the test. This distinction is especially useful at dense service openings where separate trades supply the seal and the supports. E814 limitations
How it is used in the field
Build the opening schedule around the required evidence. Give each penetration its location, assembly reference, selected listed system, required fire rating, and any separately specified leakage, water, or movement rating. Leave supplemental-rating fields marked as not specified when the design does not require them; do not populate them from a generic product brochure.
At submittal review, reconcile the actual rating line with the performance schedule. A listing that reports an ambient L result alone does not document an elevated-temperature result. A water-rated configuration also needs its own installation conditions carried into the approved detail. Record these distinctions before procurement makes substitution difficult.
For closeout, retain the system revision, approved deviations, installation photographs, and inspection disposition under the same opening identifier. After a fire, reopen that record for damage assessment and repair selection. The original acceptance record documents what was installed; it is not permission to leave an exposed system in service.
Frequently asked questions
Does an E814 fire rating include smoke leakage?
An E814 F or T duration does not establish an L rating. The submittal needs the specified leakage result, test temperature, and pressure. Keep a blank leakage field unresolved when the design requires one; a fire-test duration cannot fill it.
Can a W-rated firestop replace a waterproofing detail?
Use its documented water exposure for the specific opening. The W designation does not establish roof drainage, long-term immersion resistance, or the performance of adjacent waterproofing transitions.