UL 1479: F, T, L, and W firestop ratings and test limits
UL 1479 tests penetration-firestop systems in defined fire-resistive assemblies. F ratings address flame passage and hose-stream performance; T ratings also address heat transmission. Optional L and W ratings document air leakage and water resistance. Edition 4 (2015), revised March 18, 2026, is current. Select a system with each rating the penetration requires, then match its permitted construction and materials. The 2026 scope expressly excludes chemical compatibility, which needs separate evidence.
Applies to
UL 1479 covers through penetrations in walls, floors, and floor-ceiling assemblies and membrane penetrations in fire-resistive walls. Its scope excludes outlet boxes and fittings evaluated within the rated building assembly. Designers select performance under the adopted code, installers reproduce the accepted system, and inspectors verify the installed dimensions and materials. Use the pipe firestop guide for system selection and takeoff. Keep the system identifier and required F, T, L, and W results in separate fields on the penetration register. UL 1479 scope
Key topics
F and T hours answer different acceptance questions
UL 1479 bases the F result on flame performance and the hose-stream test; the T result adds a temperature limit on the unexposed side. UL Solutions' application guide gives that limit as a 325°F rise above the initial temperature. Starting at 70°F, that rise reaches 395°F. Record the tested F and T hours independently: a submittal with F = 2 hours and T = 0 hours provides no rated duration for limiting that temperature rise, even though its flame rating is two hours. UL rating definitions; UL temperature-rise criterion, printed page 7
L ratings describe air leakage under stated conditions
UL Solutions' firestop application guide gives the L-rating test differential as 0.30 inch water column, with results at ambient and/or 400°F air temperature. Record leakage in cfm per square foot of opening, or cfm per unit for a fixed-size device, exactly as the design reports it. A 2 cfm/unit result cannot be ranked against 2 cfm/ft² without the opening area. Retain temperature and reporting basis beside the value so the smoke-control review compares the same quantity. UL leakage-rating guidance
A Class 1 W rating has a defined water-head test
UL Solutions describes a Class 1 W rating as no water passage under a three-foot water head for 72 hours at ambient conditions. UL 1479's scope specifically excludes evaluating uncured systems under that exposure. Record cure status and the actual W-rated design when a floor penetration also needs water resistance. A water-resistant sealant description alone does not establish the system rating, and the W rating does not establish resistance to every liquid found in a plant room. UL water-rating criteria; UL 1479 cure boundary
The 2026 scope separates chemical compatibility from fire testing
ULSE's March 18, 2026 revision adds an explicit statement that UL 1479 does not address chemical compatibility among materials in the penetration-firestop system. Obtain compatibility information for the actual pipe, insulation, coatings, sealants, and adjacent materials involved. The system's fire-test evidence cannot fill that separate question. Preserve the manufacturer's compatibility response with the approved design so a later material substitution reopens the correct review. Publisher's 2026 revision summary
Hose-stream performance distinguishes certification routes
UL Solutions' certification-mark guidance explains that UL 1479 includes a hose-stream test, while the European EN 1366 penetration tests do not require it. Certification to one route therefore does not by itself establish the other route's performance. State the test reference required by the project and obtain the corresponding design and certification. Keep structural member fireproofing in its own assembly review; its evidence does not establish a penetration-firestop rating. UL's test-route comparison
How it is used in the field
Add separate columns for required and listed F hours, T hours, L leakage and test conditions, W classification, and compatibility evidence. A lower T rating can be overlooked when the register has only a single column marked 'fire rating.' Resolve that discrepancy against the adopted code and its applicable exceptions before approving the design or closing the opening.
During submittal review, reconcile the system design with the wall or floor construction, penetrating item, insulation, supports, dimensions, and closure materials. Keep product identification and the tested-system drawing together. A material's certification mark and the system's installed configuration answer different acceptance questions.
Preserve installed photographs, material batches, design identification, inspection records, and resolved deviations in the turnover log. Reopen the system selection after a cable addition, insulation change, or replacement penetrant. Following a fire, replace or obtain an accepted repair design: UL 1479 does not establish that an exposed firestop remains acceptable for reuse. UL's post-fire scope limit
Adoption
UL Solutions' application guide identifies ASTM E814 and UL 1479 as the penetration-firestop test routes referenced by Section 714 of the 2021 IBC. The adopted code sets the required ratings and exceptions. ASTM E2174-24 addresses field verification of installed firestop systems and identifies its reference in IBC Chapter 17. Use the applicable inspection documents to verify installation; an inspection report does not establish a new laboratory rating. ASTM E2174 scope
Frequently asked questions
Does UL 1479 determine cable ampacity inside the seal?
The scope excludes the ampacity of conductors encased in firestop materials. Include the electrical design and applicable conductor requirements in the review when the penetration arrangement affects heat dissipation.
Does a waterproof firestop label establish chemical compatibility?
The W rating addresses water resistance under its stated test conditions. Chemical compatibility is expressly outside UL 1479's scope. Obtain the compatibility evidence for the actual materials and exposures rather than transferring the water-test result to that question.