Bond strength

Bond strength identifies the stress reached when a tested assembly separates, together with where it broke. SFRM fireproofing is usually reported in psf; concrete-repair pull-offs commonly use psi. The 2024 IBC sets a 150 psf SFRM floor and higher requirements for applicable high-rise buildings. A 600 psf result clears the 430 psf high-rise threshold but falls short of the 1,000 psf threshold above 420 ft. A repair pull-off needs a different test method and failure interpretation.

Adhesion and cohesion of SFRM to the steel, tested to ASTM E736, with the IBC minimum rising by building height

Used across 2 Anvilfield field guides, most in Concrete.
Updated

Read an SFRM result against the building requirement

Under 2024 IBC Section 1705.15.6, an in-place SFRM bond result must reach at least 150 psf. Where the high-rise provisions of Section 403 apply, Table 403.2.3 raises the requirement to 430 psf through 420 ft and 1,000 psf above that height, measured from the lowest fire-department vehicle access level. These same provisions appear in New York's published 2024 building code. The approved fire-resistance design and project specification also belong in the acceptance record.

A 600 psf pull is 600 / 144 = 4.17 psi. At a 200 ft building governed by Section 403, it clears the code's 430 psf threshold; at a 450 ft building, it misses 1,000 psf. Preserve building height, governing requirement, test location and units on the fireproofing inspection record. A converted number without those fields cannot resolve acceptance.

SFRM and concrete repairs use different tensile tests

ASTM E736/E736M-19(2023) tests SFRM by pulling perpendicular to its backing. ASTM C1583/C1583M-25 addresses prepared concrete surfaces and repairs or overlays. Neither test result supplies an adhesive anchor's design bond stress: that value belongs to the evaluated anchor system, its installation conditions and its load-transfer model.

Average pull-off results only within one failure mode

ASTM C1583/C1583M-25 requires a failure mode for each individual pull-off result and permits averaging only results with the same failure mode. A spreadsheet that averages every pull in an area can conceal that some specimens measured concrete tensile strength while others measured interface separation.

Three pulls return 210 psi and 230 psi with substrate failure, and 120 psi at the repair interface. The substrate-failure group averages 220 psi. The 120 psi interface result remains a separate result; combining all three into 186.7 psi mixes different measured properties. Preserve the individual results and fracture photographs when interpreting the finished repair.

A substrate break puts a lower bound on the bond

ASTM C1583/C1583M-25 states that the test measures the weakest of the repair, interface and substrate tensile mechanisms. If the substrate breaks at 220 psi while the interface remains intact, the interface sustained that stress. Its ultimate bond strength was not measured. Reporting 'bond strength = 220 psi' without the failure location discards that distinction.

A 220 psi substrate break corresponds to 31,680 psf, but converting it into SFRM units does not make it an E736 result. Keep the test method beside the units when comparing products. A tensile pull-off, an anchor bond calculation and a roof uplift rating load different areas and measure different failure mechanisms.

Distinctions

Adhesion
Separation occurs between materials at an interface. Cohesive failure occurs within one material; a pull-off result must identify which mechanism governed.
Compressive strength
Crushing resistance does not establish direct tensile adhesion to a substrate. A high compressive-strength repair mortar still needs the specified bond evidence.

Frequently asked questions

Can a strong pull-off result prove the whole repair is bonded?

It establishes a result at the tested location and for its observed failure mode. Retain the location map and individual results so the reviewer sees the tested distribution rather than an area-wide claim based on one pull.

Sources checked

Also defined as

  • The stress the cured adhesive transfers between the rod and the concrete wall, in psi or MPa