Field glossary · business
RFI
RFI stands for request for information; on construction jobs, track it with separate dates for issue, first reply and usable resolution. AIA G716-2004 accepts requests in either direction among owner, architect and contractor. A federal preaward RFI instead gathers market information, with responses that cannot form a contract under FAR 15.201(e). Closing a construction RFI records an answer while any related price or time adjustment follows its own authorization process.
Request for information, the formal question whose answer often moves the work; its number ties to the resulting red-line
An RFI can run in more than one direction
AIA G716-2004 allows the owner, architect and contractor to request information from one another during construction. Its sender and receiver fields therefore identify the actual exchange; the form is not limited to a contractor asking an architect for a detail.
An owner requesting a contractor's proposed access sequence and a contractor requesting a missing penetration dimension both need a clear response, but they have different responsible parties. Keep the recipient's role with the record when transferring RFIs between systems. The RFI and submittal process guide covers project routing.
Requested reply date, first answer and usable answer
AIA's G716-2004 instructions tie the requested reply date to the contract or a reasonable expectation; the form establishes no fixed seven-day or fourteen-day response allowance. A software default in that field is a requested date, not evidence of an agreed review period.
Measure first response separately from resolution. An RFI sent October 22, first answered October 26 and fully resolved October 29 has a four-calendar-day first response and a seven-calendar-day resolution time. If the October 26 reply requests another dimension, closing the request that day would hide the three days still needed to obtain a buildable answer.
Retain the original issue date when reopening an incomplete answer. Add a revision or follow-up date without replacing the starting timestamp. The document-control guide addresses distribution after the answer is usable, and the record-drawing guide carries its permanent reference.
Question closed, change approval still open
AIA G716-2004 provides places for known cost and time effects in both the sender's recommendation and receiver's response, but neither field grants authority to increase price or duration. Keep the impact description attached to the answer without treating it as an approved adjustment.
An equipment-dimension RFI is resolved on October 29, while its linked proposal requests $2,500 and two additional days. Record the question as resolved, the proposal as pending, and the approved contract sum and time at their existing values until the adjustment is authorized. Separate question and change-order identifiers let the answer-time report close without hiding the unresolved commercial item.
Report aging without hiding the oldest question
Four open RFIs aged 2, 4, 6 and 18 days have a mean age of 7.5 days and a median age of 5 days. Neither figure identifies the 18-day item or says whether it blocks tomorrow's work. Report the oldest age and the affected activity alongside the average.
Keep the populations separate. Open-item age is time still waiting as of the report date; resolution time belongs to requests already resolved. Combining the two makes a report change merely because requests move between statuses. Publish the count behind each metric so a week with one answered request is not mistaken for the performance of the entire log.
Distinctions
- Federal market-research RFI
- FAR 15.201(e) states that responses to a planning RFI are not offers and cannot be accepted to form a binding contract. The agency is collecting price, delivery, capability or other market information. Enter that notice into procurement research separately from RFIs administering an awarded construction contract.
- RFI in electrical noise discussions
- RFI also abbreviates radio-frequency interference. A reference beside EMI or an isolated-ground discussion concerns electrical noise rather than a construction question register.
Frequently asked questions
Must every RFI use AIA G716?
No. G716-2004 is an available construction-administration form, while the project sets its document requirements. FAR 15.201(e) prescribes no required format for federal market-research RFIs.
Does an early answer count as a resolved RFI?
Only when it supplies the information needed to answer the recorded question. Retain separate dates for a partial reply and resolution so the response-time report reflects the information actually delivered.
Sources checked
Also defined as
- Request for information, a formal tracked question to the design team about a conflict, a gap, or a field condition