Schedule of values
A schedule of values (SOV) allocates contract selling price to billing items; a $100,000 equipment line with $55,000 of installed work and $5,000 of eligible stored materials shows 60% completion on AIA G703S-2017. Calculate the draw from eligible completed-and-stored value, then apply the contract's retainage terms. Cost to complete and installed quantities need separate records because a billing percentage measures neither remaining cost nor physical production.
The line-item breakdown of a subcontract that a pay application bills against by percent complete
The SOV is an allocation, not a standard AIA form
AIA's instructions for G703S-2017 expressly state that AIA does not publish a standard schedule-of-values form. G703S is the contractor-subcontractor continuation sheet that uses the submitted value breakdown to report payment progress. Distinguish the agreed allocation from each month's application against it.
A line called electrical rough-in represents its assigned share of the contract price. Its scheduled value includes the commercial allocation agreed for that work, so subtracting incurred labor cost from that value does not produce a cost-to-complete forecast. The subcontractor management guide covers review of the trade's billing.
Installing stored equipment does not earn its value twice
AIA G703S-2017 moves the value of previously stored materials into current-period completed work when those materials are installed, while removing the same value from materials still stored. Prior completed work carries forward separately. The transfer changes where value appears without creating a second entitlement to payment.
A $100,000 equipment line has $20,000 installed and $30,000 stored at the first cutoff. During the next period, $25,000 of that stored equipment is installed and $10,000 of additional installation work is earned. Installed value reaches $55,000, remaining stored value is $5,000, and the cumulative completed-and-stored total reaches $60,000. The gross increase available for billing is $10,000, before retainage and other payment adjustments.
With a contract requiring 10% retainage on both completed work and eligible stored materials, retained value rises from $5,000 to $6,000 between those cutoffs. The current request is $10,000 of additional completed-and-stored value minus $1,000 of new withholding, or $9,000, assuming the earlier application was paid in full. Deducting the whole cumulative $6,000 again would withhold earlier retainage twice.
| Billing measure | First cutoff | Next cutoff |
|---|---|---|
| Scheduled contract value | $100,000 | $100,000 |
| Installed value to date | $20,000 | $55,000 |
| Materials still stored | $30,000 | $5,000 |
| Completed plus stored value | $50,000 | $60,000 |
| Value-based completion | 50% | 60% |
Why 60% on the pay application is not a field quantity
AIA G703S-2017 calculates percentage completion by dividing completed-and-stored value by scheduled value. In the equipment line above, that gives $60,000 / $100,000 = 60%. Installed value alone is 55% of the scheduled amount, and neither percentage establishes a count of devices installed or tested.
Attach physical production measures separately, such as installed units or accepted test points, when the owner needs installation progress. The billing-backup guide connects those field records to the application. Subtracting $60,000 from the scheduled $100,000 leaves $40,000 of unearned contract value; it does not predict the remaining contractor cost.
Off-site material needs a contractual payment basis
FAR 52.232-5(b)(2), May 2014, permits off-site material in progress-payment estimates only when the contract specifically authorizes it and the contractor supplies satisfactory evidence of title and intended use on that contract. A purchase order or supplier invoice alone does not establish all of those conditions.
Identify the material allocation and its supporting ownership records before including it in the stored-value total. Apply the contract's retainage terms after establishing the eligible payment amount.
Distinctions
- G703 versus G703S
- AIA lists G703-1992 with G702-1992 for owner-contractor payment applications and G703S-2017 with G702S-2017 for contractor-subcontractor applications. The S identifies the payment relationship; the 2017 subcontractor form does not replace the 1992 owner-contractor form.
- Cost-loaded schedule
- A cost-loaded schedule assigns value to activities over time. An SOV assigns contract value to billing portions. A cross-reference between their identifiers lets progress reports reconcile without assuming that each billing line is one schedule activity.
Frequently asked questions
Should each change order rewrite the original SOV lines?
AIA's G703S-2017 instructions describe separately listing changes, either on a separate continuation sheet or at the end of the original breakdown, as the usual practice. Preserve the link from each added amount to its executed change.
What prevents a stored-material carry-forward error?
Roll prior installed work into prior completed value, then reconcile the stored balance against installations and new eligible deliveries. Carrying the previous completed-and-stored total forward as installed work would count the remaining stored material again.
Sources checked
Also defined as
- Plumbing: The line-item breakdown of the contract price used to bill progress; retainage is calculated and shown against it on the pay application.