Field glossary · business
Retainage
Retainage is the $5,000 held from a $100,000 approved progress payment when a 5% deduction is authorized. That amount represents earned work awaiting a contract or statutory release condition. Record the eligible deduction base, accumulated balance and release trigger separately. Stopping deductions on later applications changes future receipts; releasing the balance pays money already withheld. Federal and state rules determine which treatment the owner can authorize.
A percentage, often 5 to 10 percent, held back from progress payments until project closeout
Federal progress payments are not automatically reduced
For federal fixed-price construction payments to the prime contractor, FAR 52.232-5(e), the May 2014 clause published in FAC 2026-01, requires full progress payment when the contracting officer finds satisfactory progress and permits withholding up to 10% when progress is unsatisfactory. The maximum is a permitted response to performance, rather than a standing deduction from every federal construction payment.
At substantial completion, FAR 52.232-5(e) directs release of withheld funds beyond the amount needed to protect the government. It also calls for payment without percentage retention for an accepted, completed building or other division whose price is separately stated in the contract. Identify that separately priced division when preparing a release request.
FAR 52.232-5(g) excludes reimbursable performance- and payment-bond premiums from the clause's retainage provisions after the contractor provides evidence of payment to the surety. That exclusion changes the withholding base. Carry the premium backup as a distinct payment item rather than applying a blanket percentage to the entire request.
Oregon's public-work cap and late-completion reduction
Oregon Revised Statutes 279C.570(7), in the 2025 edition, caps agency retainage from a public-improvement progress payment at 5%. The same subsection authorizes elimination of retainage on remaining monthly payments after 50% completion when progress is satisfactory; that route requires the contractor's written application with written surety approval. Stopping future deductions and releasing accumulated retainage are different cash events.
At 97.5% completion, ORS 279C.570(7) also gives the agency discretion to reduce the retained balance to the value of unfinished contract work without a contractor application. On a $2 million contract at that milestone, unfinished work is $50,000. If $97,500 has accumulated through a 5% hold on $1.95 million of earned work, reduction to $50,000 releases $47,500.
Keep the jurisdiction and contract category beside the rate in the retainage register. Oregon's 50% milestone concerns remaining payments; its 97.5% provision concerns the accumulated balance. A release forecast needs the agency's decision as well as the percentage complete.
Calculate eligible withholding before forecasting the receipt
A federal progress request totals $150,000, including $10,000 of eligible bond-premium reimbursement supported by the paid surety invoice. If the contracting officer imposes the maximum 10% hold for unsatisfactory progress, the applicable base is $140,000, the hold is $14,000 and the payment is $136,000. Applying 10% to all $150,000 would overstate withholding by $1,000.
Enter the authorized base and accumulated held balance separately in the payment-application backup. A reduction in the deduction rate changes later applications; a release of previously held funds needs its own balance movement. Tie that movement to the accepted division or completion evidence in the closeout record. This makes the forecast reproduce the actual clause rather than a remembered percentage.
Frequently asked questions
Does the federal bond-premium exclusion cover stored equipment too?
FAR 52.232-5(g) names bond premiums. Stored-material eligibility is addressed separately in paragraph (b), including conditions for off-site materials. Approval to bill stored equipment does not itself give that equipment the bond-premium exemption from retainage.
Sources checked
Also defined as
- HVAC: The percentage of payment the owner withholds, often 5 to 10 percent, until completion and closeout conditions are met
- Datacenter: A percentage, commonly 5 to 10, held back from each payment and released at closeout, also called retention