Field glossary · process
Punch list
A punch list records incomplete or deficient contract work that must be resolved for the relevant completion or acceptance milestone. Its legal and commercial effect comes from the contract, not from the spreadsheet's title. Distinguish a correction to contracted work from an owner-requested addition, and identify who can verify completion versus who can authorize a change in scope or price.
The list of incomplete, deficient, or damaged contract work at substantial completion, with a party and date per item
A punch item needs a contract basis
Record the drawing, specification, approved submittal, or contract requirement behind a disputed item. A room identifier and photograph locate the condition; the requirement establishes what must change. Separate missing contracted work from a request for a different finish, added device, or upgraded performance.
FAR 52.246-12(d), the August 1996 Inspection of Construction clause, denies an inspector authority to change specification terms without the contracting officer's written authorization. On a contract containing that clause, a punch comment does not by itself authorize additional paid scope. Preserve the requested change and its contract basis for the person authorized to resolve it.
Inspection readiness affects cost and schedule
FAR 52.246-12 permits charging the contractor additional inspection or testing costs when work is not ready at the specified time or a previous rejection makes reinspection necessary. A reported 'complete' item should therefore have enough internal evidence to justify calling the reviewer back.
GSA clause 552.246-72, Final Inspection and Tests, September 1999, requires notice at least 10 calendar days before the stated readiness date. It also calls for final inspection and tests to begin within 10 calendar days after that date unless the contracting officer finds the work unready. Track these as separate dates on contracts using the clause; the advance-notice deadline is not the inspection-start date.
Connect notice and readiness dates to material deliveries, access, and witness availability in the punch-list turnover schedule. An internal completion report should arrive early enough to resolve those dependencies before the final-inspection notice commits the contractor to a readiness date.
Keep correction, verification, and acceptance distinct
Keep separate timestamps for the installer's correction report, the designated reviewer's verification, and the authorized party's acceptance. Attach the evidence to the action it supports. A photograph uploaded by the installer records a reported correction; it should not populate an owner-acceptance field automatically.
Under FAR 52.246-12, government inspection does not itself constitute or imply acceptance. That distinction is especially useful when a contractor must demonstrate that concealed or corrected work was inspected but final acceptance has not yet occurred.
Close an item with evidence that answers the actual requirement: a measured result for a performance deficiency, the revised document for a record deficiency, or a photograph where appearance is the issue. If another item depends on the correction, retain that dependency until its own verification is complete.
Distinctions
- Change order
- A change order alters the contract through its authorized process. A punch list identifies work against the existing requirements.
- Warranty claim
- A warranty claim follows the applicable warranty obligations and timing. An unresolved completion item does not become a different obligation merely because occupancy begins.
Frequently asked questions
Does a short punch list prove the project is substantially complete?
The contract’s completion criteria govern. One remaining item can block an intended use or required milestone; many minor finish items can have a different effect. Record the consequence, not only the item count.
Sources checked
Also defined as
- Datacenter: The list of incomplete or deficient items found near completion that must be corrected before final acceptance; also called a snag list