Certificate of occupancy (CO)

A certificate of occupancy authorizes a recorded use for specific premises, which is why a ground-floor retail CO does not approve a newly fitted upper floor. New York City's Department of Buildings, the jurisdiction used below, distinguishes a final CO with no expiration date from a temporary CO that typically expires after 90 days. Match the covered floor, use and conditions to the planned move-in.

The AHJ document confirming the space meets code for its use and is legally safe to occupy

Used across 2 Anvilfield field guides, most in Concrete.
Updated

Match the certificate to the floor being occupied

Compare the issued certificate's property identifier, floor-use schedule and covered areas with the turnover plan. A document for the retail ground floor does not answer whether a newly fitted upper floor is approved. Put the relevant floor-use record in the handover file with the certificate itself.

NYC DOB directs users to BIS for CO requests before March 1, 2021, and to DOB NOW for requests on or after that date. DOB NOW exposes the certificate details and floor-use records through the property search. This split explains why an address search in only one system misses part of a building's record.

A passed inspection or an application number is evidence of progress through the approval process; the issued occupancy record is the document to retrieve. Add its issue date, covered floors and conditions to the occupancy milestone in the tenant-improvement handover.

NYC final CO, TCO, completion letter or no-objection letter

According to NYC DOB's CO guidance, a final certificate has no expiration date, while a change in use, egress or occupancy can require a current or amended certificate. A document's age alone does not establish whether it covers the present use.

NYC DOB identifies a Letter of Completion as the possible closeout document for minor alterations that do not require a new or amended CO. It also recognizes a Letter of No Objection as evidence of legal use for qualifying pre-1938 buildings that did not require a CO. These are specific local record types, each answering a different question.

As of November 5, 2026, NYC DOB's Existing Building Code FAQ identifies the 2022 NYC Construction Codes as the governing framework, including their limited allowance for applicable prior codes. The EBC takes effect for alteration applications filed on or after July 17, 2027. A future effective date does not change the code basis of a November 2026 certificate review.

Put a TCO expiration on the turnover calendar

NYC DOB's temporary-certificate page says TCOs typically expire 90 days after issuance and describes renewal when final-CO issues remain unresolved. Read the expiration on the issued document rather than treating the usual duration as the date.

A TCO expires November 5, 2026, and the tenant plans to move in November 6. The turnover register needs a renewed TCO or final CO covering November 6; a renewal application alone is not the replacement approval. NYC DOB also says a space left unoccupied for more than 30 days needs a new TCO before reoccupation, so track vacancy as well as the printed expiration.

Assign the outstanding certificate request to a named role and keep its status separate from contractor punch work. The closeout register should link the issued document, its covered spaces and its time limits so the handoff team can verify the planned occupancy against the same record.

Frequently asked questions

Does every renovation require a new certificate of occupancy?

For the NYC process described here, changes in use, egress or occupancy trigger a current or amended CO; minor alterations can close with a Letter of Completion. Use the issuing jurisdiction's record types when applying this check elsewhere.

Does a missing online CO prove that an old building has no lawful use?

No. NYC recognizes qualifying pre-1938 buildings without a CO and provides a Letter of No Objection process. Search the relevant record system and establish which documentation applies to that building.

Sources checked

Also defined as

  • Datacenter: The AHJ's legal permission to occupy the space, issued against passed final inspections; may be temporary with conditions

Where this shows up

Next step: Track public fit-out work

Back to the full field glossary