Retainage / retention
Retainage, also called retention, is earned payment held for completion: a 10% hold on $194,000 of eligible work leaves $19,400 still owed for that work. FAR 52.232-5 excludes reimbursed bond premiums from this base and permits withholding for unsatisfactory progress. Carry the eligible base, governing clause and release trigger with the balance; the federal 10% ceiling does not require a deduction from every draw.
The percentage of payment withheld until completion, commonly reduced at substantial completion and released at final; set by contract and statute
Federal retainage starts with the progress finding
FAR 52.232-5(e), May 2014, requires full progress payment when the contracting officer finds progress satisfactory and permits withholding up to 10% when progress is unsatisfactory. The percentage is a ceiling for that circumstance. It does not turn every federal construction draw into a 90% payment.
Under FAR 52.232-5(e), completion and acceptance of a separately priced building, public work or other contract division triggers payment for that completed work without percentage retention. A finished electrical package qualifies when it is an accepted division with its own price stated in the contract; a separate line in an internal trade budget does not establish that status. The retainage management guide covers the collection process around those amounts.
FAR 52.232-5(e) also requires release at substantial completion of previously withheld funds beyond the amount the contracting officer considers adequate to protect the Government. Track that release separately from final payment under paragraph (h), which requires completion and acceptance of all work, a properly executed voucher and the specified release of claims.
Remove bond-premium reimbursement from the base
FAR 52.232-5(g) exempts the portion of a progress payment attributable to performance and payment bond premiums from the clause's retainage provisions. Reimbursement follows evidence of full payment to the surety and the contractor's request.
A $200,000 payment request includes $6,000 of qualifying bond-premium reimbursement. With unsatisfactory progress and a 10% hold on the remaining eligible work, retainage is ($200,000 - $6,000) x 0.10 = $19,400. The payment after that deduction is $180,600. Applying 10% to the whole request would withhold an extra $600 from the exempt premium.
Show the exempt amount and the retained work as distinct calculations in the billing backup. This preserves the reason for the difference between the invoice total and the withholding base.
Which event starts a DOT-assisted retainage clock?
FAA's Airport Improvement Program Handbook, Order 5100.38D, Change 1 (2019), Table 5-22, requires sponsors holding retainage to ensure that the prime contractor's subcontract retention percentage does not exceed the sponsor's percentage. A 5% sponsor hold therefore does not support a 10% subcontract hold under that FAA requirement.
The FAA table describes a 30-day release period after satisfactory subcontract completion. For DOT-assisted contracts, 49 CFR 26.29(b) sets out three recipient methods, including an incremental-acceptance method with a different payment trigger. Record the applicable method and its trigger alongside the deadline.
| 49 CFR 26.29(b) method | Retainage arrangement | Subcontract release trigger |
|---|---|---|
| Paragraph (b)(1) | Recipient holds none and prohibits prime retainage | No subcontract retainage to release |
| Paragraph (b)(2) | Recipient holds none; prime holds subcontract retainage | Within 30 days after satisfactory subcontract completion |
| Paragraph (b)(3) | Recipient holds retainage and makes incremental acceptances | Within 30 days after recipient pays retainage to the prime for the accepted work |
Document completion at the subcontract's own boundary
49 CFR 26.29(c) defines satisfactory subcontract completion by accomplishment and documentation of all subcontract tasks, and treats work covered by the recipient's incremental acceptance as satisfactorily completed. Keep that evidence identifiable within the larger closeout package, with acceptance and payment dates recorded separately.
49 CFR 26.29(f) extends the prompt-payment and retainage requirements to lower-tier subcontractors. The prime-to-subcontractor register therefore does not capture every release obligation on a job with further subcontract tiers.
Distinctions
- Retainage balance versus unearned contract value
- A ledger with $9,000 held from past draws and $40,000 still to be earned contains two different collection conditions. Releasing the $9,000 settles a past withholding; billing the $40,000 requires further eligible work or materials.
- Bond premium versus retention bond
- The $6,000 exemption in the federal draw reimburses a paid performance/payment-bond premium. A retention-bond offer addresses the separate $19,400 held balance through an agreed security substitution, rather than reimbursement of that premium.
Frequently asked questions
How do I check a retainage-only release?
Reconcile opening retained balance plus new withholding minus releases to the closing balance. With $24,000 opening retainage, no new withholding and a $15,000 release, $9,000 remains held. The release reduces that balance without adding installed work.
Are federal procurement and airport grant payments the same system?
No. FAR 52.232-5 governs contracts containing that federal procurement clause. The FAA provisions address Airport Improvement Program sponsors and their construction contracts. Classify the funding and contract arrangement before selecting the payment rule.
Sources checked
- FAR 52.232-5: May 2014 clause, paragraphs (e) and (g), FAC 2026-01
- FAA Order 5100.38D, Change 1 (2019): chapter 5, Table 5-22, contract retainage limitations
- FAA AIP Handbook index: current Change 1 handbook and draft 5100.38E status
- eCFR: 49 CFR 26.29(b), (c) and (f), current text checked November 5, 2026
- GovInfo: 49 CFR 26.29, October 1, 2025 annual edition, official PDF of the verified provisions
Also defined as
- Plumbing: A percentage withheld from each progress payment until the work is accepted; commonly 5 to 10 percent, but set by the contract and state.
- The percentage withheld from each payment as security, released at completion or a milestone per the contract