ANVILFIELD Try FieldOS

Plumbing

Construction retainage and retention field guide for getting paid

Get the held-back money: know the rate, negotiate the cap and step-down at signing, request early release of finished scope, have closeout ready, and track retainage receivable by job.

RetainageRetentionGetting PaidCash FlowPlumbing

Direct answer

Retainage, also called retention, is a percentage of each progress payment the owner or general contractor holds back until the work is accepted, commonly 5 to 10 percent but it varies by contract and state. Because that held-back amount often equals your profit, managing the rate, the cap, and the release decides whether the job actually made money.

Key takeaways

  • Retainage, also called retention, is a percentage of each progress payment held back until the work is accepted, commonly 5 to 10 percent.
  • The held-back 5 to 10 percent often equals or exceeds the entire job profit, so the job makes money only when retainage is released.
  • Negotiate a cap or step-down at signing, commonly dropping from 10 to 5 percent at 50 percent complete; it is nearly impossible to win later.
  • Track retainage receivable by job (rate, total held, release conditions, expected date) and chase a releasable unpaid hold like any overdue balance.
  • Mechanics lien and payment bond deadlines can run on unpaid retainage, so calendar them against the release date and escalate before they expire.

Retainage, and why the last 5 to 10 percent is the part that matters

Retainage, also called retention, is the slice of every progress payment that the owner or the general contractor keeps instead of paying you, and holds until the work is finished and accepted. You bill 100. You get paid 90 or 95. The rest goes into a pile that grows all job long and does not come back until the end, sometimes long after your part of the work is done and tested.

Here is the part that catches contractors. On a job priced at a normal margin, that withheld 5 to 10 percent often equals or exceeds the profit on the whole job. The money you paid out, material, labor, the supply house, is already gone. The amount still sitting in someone else's account is the part you were supposed to keep. So the job does not really make money until the retainage comes home, and whether it comes home on time, in full, and without a fight is decided by the contract you signed and how you managed it.

This guide is the back half of getting paid on bigger work. The accounts-receivable and collections guide covers invoicing fast and working the aging on the day-to-day balances. The mechanics-lien and preliminary-notice guide covers the security behind the money. Retainage sits across both: it is a receivable you have to track and chase like any other, and the lien or bond clock can run on it the same as the rest of what you are owed.

This is general education, not legal or accounting advice

Read this before the rest. This guide is general education about how retainage works in the trades. It is not legal advice, it is not accounting advice, and nothing in it is a substitute for your contract, your state's law, or a professional who knows both.

Retainage is set two ways, and both vary. The contract decides the rate, the cap, the release conditions, and the timing for your specific job. State law sets limits on top of that, especially on public work, and the limits differ from one state to the next on the maximum percentage, the release deadline, interest on late release, and whether the money has to sit in escrow. A practice that is normal in one state can be illegal or unenforceable in the next.

So every number in this guide is a common figure, not your figure. When you see a percentage or a timeline here, treat it as a starting point and confirm the real one against your contract and your state's statute. For the rate, the cap, and the release terms, the contract controls. For the legal deadlines and interest, a construction attorney licensed where the project sits is the right source. For how it lands on your books and your taxes, ask a CPA. Confirm with the contract and the state, every job.

Why retainage decides whether the job made money

Retainage hurts in a way a normal slow payment does not, because it is structural and it lasts for months. A late invoice is one balance you can chase. Retainage is a cut taken off every single payment, building the whole length of the job, and held until the very end.

Three things make it sting. First, the held-back percentage is usually about the size of your profit, so until it releases you have financed the job and earned nothing. Second, it ties up cash for a long time, often well past the day your scope was finished, which is cash you cannot use to make payroll or take the next job. Third, it flows downhill: the general contractor holds it from you, the owner holds it from the general, and a slow release at the top freezes everyone below.

The contractors who get paid treat retainage as money they manage on purpose, not money they hope shows up. They negotiate the rate and the cap before signing, they request release of finished scope without waiting for the whole job, and they track every held-back dollar by job so none of it goes quiet. The ones who lose it accept whatever the contract says, forget the running total, and discover at the end that their margin has been parked somewhere for a year.

What is retainage in construction?

Retainage is a percentage withheld from each progress payment and released after the work reaches completion and is accepted. It is the contract's security that you finish the job and close out the punch list. The owner or the general contractor holds the money to make sure you finish: do the work, fix the deficiencies, hand over the closeout documents, and you get the held-back balance.

It shows up on the payment application as its own line. On the common AIA forms, the G702 and G703, retainage is calculated on the work completed and stored materials and subtracted before the current payment is figured, so the application itself shows how much is being held this period and how much has piled up to date. ConsensusDocs forms handle it the same way under their own clauses. Whatever the form, the contract language is where the actual rate and the release rules live.

Retainage is not a penalty and it is not a dispute. It applies to good work, on schedule, with nobody unhappy. That is what trips people up: the money is held even when everything is going right, which is exactly why it is so easy to lose track of and so important to manage from the first pay application.

How much retainage is withheld?

Retainage is commonly 5 to 10 percent of each progress payment, but that is a range, not a rule, and your number comes from the contract and your state's law. A 10 percent hold on a job run at a 10 percent margin means your entire profit is the retainage. A 5 percent hold on the same job means half your profit is parked. The rate is not a detail. It is the size of the bet.

State law often caps it, especially on public work. States split roughly between capping retainage at 5 percent and capping it at 10 percent on public projects, some cap private work as well, and a few restrict retainage heavily or prohibit it on most jobs. California, for example, caps retainage on private projects at 5 percent as of 2026, and New Mexico bars it on most public and private work. These rules change and they vary by state and by whether the job is public or private, so confirm the cap that applies to your job rather than assuming the number on the last contract carries over.

Read the rate before you sign, not after the first pay application surprises you. If the contract says 10 percent and your state allows less, the lower legal cap may control, but do not rely on that. Get the number right in writing, and confirm both the contract figure and your state's limit.

Negotiate a cap or a step-down

The single best move on retainage happens before the job starts: cap it or step it down in the contract. Many contracts allow variable retainage, where the rate drops once the job is partly done, commonly from 10 percent to 5 percent at 50 percent complete, or stops being withheld at all once you pass a milestone. Some states even require a reduction. Illinois, for instance, requires a step-down to 5 percent at 50 percent completion on covered work.

There are two levers. A cap puts a ceiling on the total dollars held, so once the pile reaches the cap they stop adding to it even as you keep billing. A step-down cuts the rate at a milestone, so the back half of the job is held lighter than the front. Either one frees real cash, and on a long job the difference is large. The contractor who negotiated a 5 percent cap and the one who accepted an uncapped 10 percent are running very different bank balances on the same work.

Ask for it at signing, in writing, because it is nearly impossible to win later. Nobody reduces retainage in the middle of a job out of goodwill. On the AIA continuation sheet there is even a column for line-item variable retainage when the contract allows it. Whether you can cap or step down, and on what terms, depends on the contract and the state, so put the language in the deal and confirm what your state requires or allows.

Retainage flows down the chain, both ways

Retainage runs downhill through the whole contract chain. The owner holds it from the general contractor, the general holds it from you, and you can hold it from your own subs. Whatever rate gets withheld from you, you are usually able to withhold the same from the tier below, which is how the risk passes down instead of stacking on one party.

You sit on both sides of it at once. As a sub, you have retainage held from your payments, and that is the money you are chasing. As the party hiring sheet-metal help, a fixture-setting crew, or a directional-boring sub, you can hold retainage from them. Matching the two matters: if 10 percent is held from you but you pay your subs in full, you have taken on their share of the risk and financed it with your own cash. If a sub then walks before closeout, you are out the money you held back from no one.

The clean practice is to mirror your prime contract down to your subs so the hold passes through rather than landing on you. Match the rate, the release conditions, and the timing, so you are not releasing a sub's retainage before the general releases yours. State law sometimes limits how much you can hold from subs or when you must release it, so confirm your subcontract terms and your state's rules before you set the number.

Retainage on the schedule of values and your cash flow

Retainage is a line on the schedule of values, and it is a hole in your cash flow that you have to plan around. Every pay application shows the work completed, the percentage held, and the running total retained, so the gap between what you earned and what you collected is visible from the first draw. The trouble is that the gap is real money you have already spent on labor and material, sitting unpaid until the end.

Job-cost the retainage as the financing cost it is. You bought the copper, the fixtures, and the pipe, you ran the payroll, and a slice of the payment that should have covered it is being held for months. On a long job that is a meaningful amount of working capital tied up the whole time, and you need a line of credit or enough cash to carry it without choking the next job. The accounts-receivable guide covers the broader cash-flow trap, that profit on paper is not cash in the bank, and retainage is one of the biggest reasons the two diverge on construction work.

Plan for it at takeoff, not at the closeout meeting. If you know 10 percent of every draw is going to be held for a year, that is part of the cost of the job and part of what your pricing and your credit line have to cover. Treat it as a knowable, financeable gap, and confirm the treatment with your bookkeeper.

When is retainage released?

Retainage is released when the contract's release conditions are met, which usually means the work is accepted. The common triggers are substantial completion, a closed punch list, final inspections passed, the closeout documents delivered, and lien waivers signed up and down the chain. Until those are satisfied, the holder has a contractual reason to keep the money, so the release is really a checklist you have to finish, not a date that arrives on its own.

Many contracts release in stages. A common structure is to release part of the retainage at substantial completion and the rest after the punch list is closed and closeout is delivered. Others hold the whole amount until final acceptance. Public jobs often release on a statutory timeline tied to acceptance or completion. The exact triggers and the order they come in are set by the contract and, on public work, by state law.

The practical lesson is that release is a process you drive, not a payment you wait for. Know which conditions trigger your release, finish them deliberately, and submit the release request with the documents attached so the holder has no reason to stall. Confirm the actual conditions and timeline in your contract and your state's rules.

Release triggerWhat it usually meansWhat to have ready
Substantial completionWork usable for its intended purpose, minor items leftCertificate or sign-off, updated pay application
Punch list closedAll listed deficiencies corrected and verifiedSigned punch list, photos of corrected items
Final inspectionsAuthorities and owner accept the workInspection sign-offs, test reports
Closeout documentsRecord set delivered to ownerAs-builts, O&M manuals, warranties
Lien waivers exchangedOwner protected against downstream claimsConditional waiver now, unconditional after funds clear

Substantial completion is the milestone to know

Substantial completion is the point where the work is finished enough to be used for its intended purpose, even though minor items remain on the punch list. It matters because many contracts tie the start of retainage release to it, along with other clocks like warranties and the deadline to finish the punch list.

On a lot of jobs, this is where the first chunk of retainage frees up. Reach substantial completion, get it certified or signed off, and the contract may release part of the hold while keeping a smaller amount against the open punch items. That is why pinning down the date and getting the sign-off in writing is worth the effort. A vague, undocumented substantial-completion date is a release you cannot start.

What counts as substantial completion, and what it releases, is defined by your contract and sometimes by state law. The owner and the design team usually have to agree it has been reached. Do not assume your read of it matches theirs. Get the milestone documented, and confirm what it triggers under your contract.

Can you get retainage released early?

Often, yes, and asking is one of the most overlooked moves in the trades. If your scope finishes early, which on a plumbing or mechanical job it frequently does because the rough-in and the underground go in long before the building is done, many contracts let you request release of your portion without waiting for the entire project to close out. Your work is done, tested, and inspected. There is no reason your money should sit for another eight months while the finishes go in upstairs.

The request has to be made, in writing, with the proof attached. Submit your completed scope, the inspection sign-offs, your closeout documents for that work, and the lien waivers, and ask for early or partial release of the retainage on your portion. A general contractor will not volunteer it, but a clean, documented request for a finished and accepted scope is hard to refuse, and refusing it may run into prompt-payment rules in some states.

Do not wait for the whole job. The early-finishing trades carry the most retainage for the longest time precisely because they are done first and paid last. Whether early release is available, and on what terms, depends on the contract and the state, so check the language, build the request into your closeout for each scope, and confirm what your state's prompt-payment law allows.

A tiny punch item can hold a large retainage

The punch list is where retainage gets stuck, and the math is brutally lopsided. A single open item worth a few hundred dollars can hold tens of thousands in retainage hostage, because the contract conditions release on the punch being closed, not on the dollar value of what is left. One missing escutcheon or one trim piece on backorder, and the whole hold sits there.

So close the punch fast, and close it for real. Get the list, schedule the corrections, fix them, and get each one signed off with proof. Photograph the corrected work. A punch item the owner cannot verify is closed is a punch item that stays open, and an open punch is your retainage frozen. Treat the punch list with the same urgency as a callback, because in cash terms it is bigger than most callbacks.

When a hold is plainly out of proportion, push back. If the punch is essentially complete and the holder is sitting on the full retainage over one trivial item, many contracts and some state laws limit holding amounts that far exceed the value of the remaining work. Document that your scope is done, request release of the disproportionate amount, and if it stays stuck, treat it as the overdue receivable it is. Confirm what your contract and state allow on disputed or disproportionate holds.

Closeout documents gate the release

Retainage waits on closeout, so the paperwork is part of getting paid, not an afterthought. The contract usually conditions the final release on delivering the record set: as-built drawings showing what was actually installed, operation and maintenance manuals for the equipment, warranties, test and inspection reports, and the final lien waivers. No closeout package, no release, no matter how good the work was.

The trades lose weeks of release time here, because closeout gets treated as cleanup after the crew has moved to the next job. The as-builts never got marked up, the O&M manuals are scattered across email, and the warranty letters were never collected. Now the office is reconstructing a record set under deadline while the retainage sits.

Build closeout as you go. Mark up the as-builts as the work changes in the field, collect the submittals and warranties when the equipment arrives, and keep them on the job record instead of in a truck. When your scope is done, the package is mostly assembled and the release request can go out with it attached. Confirm exactly which documents your contract requires for release, because the list varies by job and by owner.

State prompt-payment and retainage laws

On top of the contract, your state's prompt-payment and retainage laws set rules the contract cannot override, and they are the part most contractors never read. These statutes can cap the maximum retainage percentage, set a deadline for releasing it after acceptance or completion, require interest when the release runs late, and impose extra rules on public jobs. Nearly every state has prompt-payment law of some kind, and the details differ in every one.

The variation is wide enough that a habit from one state will get you in trouble in the next. Release deadlines on public work are often measured in a set number of days after completion or acceptance. Interest for wrongful or late withholding runs at different rates by state, and some statutes award attorney fees to the party who prevails. Some laws require the general contractor to pass retainage down to subs within a set number of days of receiving it from the owner.

Treat the statute for the state where the project sits as the authority that overrides any number in this guide. Know your state's maximum percentage, the release timeline, whether interest accrues on a late release, and the rules that differ between public and private work. This is a topic to set up once with a construction attorney licensed in your state, then run the same way on every job. Confirm every deadline and rate against current state law before you rely on it.

Public jobs run on their own retainage rules

Public construction usually has the most protective retainage rules, and you should know them because they work in your favor. On public work, retainage is often capped at a lower percentage than private jobs allow, released on a statutory timeline rather than whenever the owner gets around to it, and in some states held in an interest-bearing escrow account so the money earns while it waits.

The specifics are state and project specific. Several states require retainage on certain state-funded projects to be deposited in escrow, and a number of states cap public retainage at 5 percent. Florida, for example, sets a tight window for the public entity to pay the remaining balance after substantial completion and the punch list. These are common patterns, not universal ones, and the dollar limits and day counts change.

If you are on a public job, find out which statute governs, what the cap is, what the release deadline is, and whether the money is in escrow earning interest you are entitled to. Confirm it with the contract, the public owner's terms, and a construction attorney, because the rules that protect you only help if you know them and ask.

Retention bonds and securities in lieu of cash

Some contracts let you swap the cash retainage for something else, which frees the money. A retention bond, also called a retainage bond, is a surety bond that stands in for the held-back cash, so the owner gets equivalent security and you get paid in full as the job goes. Some contracts and statutes also allow securities, like a deposit of bonds or a letter of credit, in place of retainage.

The trade is cost against cash flow. A retention bond carries a premium, so you are paying to free up money that is your own profit, and whether that math works depends on how long the retainage would otherwise be held and what that cash is worth to you. On a long job where a large amount would sit for a year or more, the premium can be cheaper than financing the gap. On a short job it rarely pays.

Availability is the catch. Not every contract or state allows a bond or securities in lieu of retainage, and the option has to be in the deal. Ask about it at contract time, price the bond with your surety, and confirm with your attorney that the substitution is allowed and how it is documented. It is a tool worth knowing exists, used where the numbers justify it.

Track retainage receivable by job

The most common retainage failure is the simplest: nobody tracks it. Because it builds quietly across many pay applications and is not due until some far-off date, the running total falls off the radar, and a contractor can have a serious amount of money held across several jobs without a clear picture of how much, on which jobs, or how old it is. It is real money, and it is easy to forget.

Track it as its own line, by job, the way you track any receivable. For every project, you want the rate being held, the total retained to date, the release conditions, the expected release date, and the status of your closeout. Age it the same way you age invoices, because retainage that has been releasable for ninety days and is still unpaid is an overdue balance, not a someday balance. The contractors who track it collect it. The ones who do not leave money on the table every year and never know how much.

This is where a field tool earns its place. With FieldOS, the job record that holds the visits, the photos, the inspections, and the closeout documents is the same place the retainage and its release conditions live, so the held amount, the proof the work is done, and the release request all sit on the job they belong to instead of scattered across spreadsheets and inboxes. When a release is due, the documentation is already in one place. Confirm how the tracking lines up with your accounting setup with your bookkeeper.

Collecting overdue retainage

Once retainage is releasable and the holder is sitting on it, chase it like any other overdue receivable, because that is what it is. The reflex is to treat retainage as patient money that shows up eventually, but a hold that has met its release conditions and gone unpaid is simply a late balance, and the longer it sits the harder it gets. Work it on a schedule: a release request with the documents, a follow-up, a firm call, then escalation.

The clock is the part that bites. The mechanics lien and payment bond deadlines can run on unpaid retainage the same as on any unpaid balance, and a long retainage hold can quietly push you past a lien or bond deadline while you wait politely. The lien guide covers this in depth, and the trap is real: you assume the retainage is coming, the months pass, and the right to secure it expires behind you. On a public job, the payment bond claim has its own notice and suit deadlines that apply to retainage too.

So preserve the security early and watch the clock. Track the release date against the lien or bond deadlines for the job, request release in writing the moment the conditions are met, and if it stays unpaid, escalate before the deadline rather than after. Whether and how the lien or bond clock applies to retainage is state specific, so confirm the timing with a construction attorney rather than assuming you have time.

Negotiate the terms at contract time, not at the end

Every favorable retainage term is won at signing and almost none of it later. At contract time you hold the cards: the owner or general wants you on the job. Once you have signed and the work is in the ground, you have given that advantage away, and asking for a lower hold or an earlier release becomes a favor instead of a deal.

Put the terms you want in the contract. A cap on the total dollars held. A step-down that cuts the rate at a milestone like 50 percent complete. A clear right to early or partial release of your scope when it finishes ahead of the job. A defined list of exactly what closeout documents trigger release, so the holder cannot invent new conditions at the end. And the option of a retention bond in lieu of cash if the numbers favor it. Each of these is normal to ask for, and each one is money.

The estimating side matters here too. If you are stuck with a high uncapped hold you could not negotiate out, that financing cost is part of the job and belongs in the price. Better to negotiate the terms down, but if you cannot, at least price the carry. Confirm what your contract allows and what your state requires before you sign, because the contract is where this is decided.

Retainage on the books and at tax time

Retainage has its own place on the books, and getting it right keeps your financials honest about cash. Money held back from you is usually recorded as retainage receivable, an asset, separate from your regular receivables because it is not yet due. Money you hold back from your subs is recorded as retainage payable, a liability, until you release it. Keeping the two separate shows what is really collectible now versus what is parked until closeout.

The timing is the part that surprises people. Under current revenue standards, the accounting guidance contractors work under, you generally recognize revenue as you perform the work, not when the retainage is collected, so you can report a profit on a job while a chunk of the cash is still held. Profit on paper, cash not in the bank, is exactly the gap retainage creates, and it is why a profitable year can still feel tight. How the held amount is classified, whether it is a straightforward receivable or a contract asset, depends on whether your right to it is unconditional, which is a detail your accountant handles.

Tax treatment follows its own rules and depends on your accounting method and your situation. This is a place to ask a CPA, not to guess. Have your accountant set up retainage receivable and payable accounts, produce the balances by job, and advise on the revenue and tax timing. The bookkeeping makes the held money visible, which is the first step to collecting it.

Common mistakes

  • Not tracking retainage receivable by job, so a large held balance goes quiet and unchased.
  • Accepting a high, uncapped rate at signing without negotiating a cap or a step-down.
  • Letting a tiny open punch item hold the entire retainage instead of closing it fast.
  • Waiting for the whole job to close to release your scope that finished months early.
  • Missing the mechanics lien or payment bond deadline that runs on unpaid retainage.
  • Having no closeout documents ready, so the release stalls on missing as-builts and waivers.
  • Paying subs in full while a hold is taken from you, financing their share with your cash.
  • Treating retainage as patient money instead of an overdue balance once it is releasable.

What to document on retainage

Retainage release is won on the record. The job that can produce the rate held, the running total, the dated closeout package, and the release request it sent is in a different position than the one working from memory at the closeout meeting. Capture it as the job runs, not when the release is overdue. Every figure and deadline below varies, so confirm the contract and the state for your job.

ItemActionNote (confirm the contract and state)
Retainage rate and capRecord the percentage held and any cap or step-downRate and cap are set by the contract and state limits
Running total retainedTrack held to date by job on every pay applicationThis is real money easy to forget; age it
Release conditionsList exactly what triggers release for this contractOften substantial completion, punch, closeout, waivers
Substantial completion dateGet the milestone certified or signed off in writingMay release part of the hold; confirm what it triggers
Closeout packageAssemble as-builts, O&M, warranties, test reportsBuild it as you go; the release gates on it
Early release requestSubmit in writing when your scope is done and acceptedAvailable on many contracts; confirm yours and the state
Lien or bond deadlineCalendar it against the expected release dateThe clock can run on unpaid retainage; ask an attorney

Field and office checklist

0 of 10 complete

Want this checklist to run itself on every job — with photo proof and a signed record crews can hand the customer? That's FieldOS.

Standards, references, and where to get the rules right

The first authority is your contract. The retainage clauses in the standard families, the AIA documents and the G702 and G703 payment forms, and the ConsensusDocs agreements, set the rate, the cap, the release conditions, and the timing for your job. Read those clauses before you sign, because that is where the rate and the release terms are actually decided, and a number in this guide is no substitute for the language in your deal.

The second authority is your state. Prompt-payment and retainage statutes set the maximum percentage, the release deadline, interest on late release, and the rules for public work, including escrow requirements on some state-funded jobs. There is no national version, and the figures differ enough that you confirm the statute for the state where the project sits, every time. Treat the day counts and percentages in this guide as common figures, not your figures.

Three habits matter more than any single citation: negotiate the rate and the cap at contract time, track retainage receivable by job so none of it goes quiet, and request early release of finished scope while watching the lien or bond clock. For the legal deadlines and the subcontract terms, a construction attorney licensed in your state is the right source. For classification, revenue timing, and tax, ask a CPA. Nothing here is legal or accounting advice, and the contract and the state control.

Terms and definitions

Retainage carries its own vocabulary, and the same idea shows up under different names across a subcontract, a pay application, and your accounting software. These are the terms used in this guide. Confirm how your contract and state define each one.

Retainage / retention
A percentage withheld from each progress payment until the work is accepted; commonly 5 to 10 percent, but set by the contract and state.
Variable retainage / step-down
A contract term that reduces the retainage rate, or caps it, at a milestone such as 50 percent complete; some states require it.
Substantial completion
The point where the work is usable for its intended purpose with minor items remaining; often the milestone that starts retainage release.
Retention bond
A surety bond posted in lieu of cash retainage so the held money is freed while the owner keeps equivalent security; availability varies by contract and state.
Prompt payment law
State statutes setting payment and retainage release deadlines and interest for late or wrongful withholding; nearly every state has one and the details differ.
Schedule of values
The line-item breakdown of the contract price used to bill progress; retainage is calculated and shown against it on the pay application.
Retainage receivable / payable
Retainage held from you is an asset (receivable); retainage you hold from subs is a liability (payable); ask a CPA about classification and timing.

Related tools

Calculators and readiness checks for this work

Compare your options

FAQ

What is retainage in construction?

Retainage, or retention, is a percentage of each progress payment that the owner or general contractor holds back until the work is accepted, as security that you finish the job and close the punch list. It is commonly 5 to 10 percent, but the rate, cap, and release terms vary by contract and state.

How much retainage is withheld?

Retainage is commonly 5 to 10 percent of each progress payment, but the figure is set by your contract and limited by state law. Many states cap retainage on public work, some cap private work too, and a few restrict it heavily. Read the contract and confirm your state's limit before you assume a number.

When is retainage released?

Retainage is typically released after the work is accepted, which the contract usually ties to substantial completion, a closed punch list, final inspections, closeout documents, and signed lien waivers. Some contracts release part at substantial completion and the rest after closeout. The exact triggers and timeline are set by the contract and state law.

Can you get retainage released early?

Often yes. If your scope finishes early, many contracts let you request partial or early release of your portion rather than waiting for the whole project to close. Put the request in writing with your closeout documents and lien waivers. Whether early release is allowed depends on the contract and state law.

Can retainage be reduced partway through a job?

Many contracts allow variable or step-down retainage, where the rate drops, often from 10 to 5 percent, once the job reaches a milestone such as 50 percent complete. Some states require a reduction. Negotiate the cap and step-down at signing, since it is nearly impossible to win later. Confirm your contract and state.

Do I have to withhold retainage from my subcontractors?

You do not have to, but if a general contractor withholds from you, you can usually withhold the same from your subs so the risk flows down instead of sitting on you. Match your prime contract terms. Confirm what your subcontracts and state law allow, since some states limit holding from subs.

What happens to retainage on a public project?

On public work, retainage is often capped and released on a statutory timeline, and some states require it held in an interest-bearing escrow account. Prompt-payment laws may add interest if release runs late. The cap, timeline, and escrow rules are state specific, so confirm them with the contract and a construction attorney.

Can I get retainage released without putting up cash?

Some contracts allow a retention bond or securities in lieu of cash retainage, which frees the held money while giving the owner equivalent security. Availability depends on the contract and state law, and the bond carries a premium. Ask about it at contract time and confirm with your surety and attorney.

Does the lien deadline apply to retainage?

It can. Unpaid retainage is still money owed, and the mechanics lien or payment bond clock may run on it the same as any balance. Do not let a long retainage hold quietly push you past a deadline. Track it, chase it like a receivable, and confirm the timing with a construction attorney.

How is retainage handled on the books?

Retainage held from you is usually booked as retainage receivable, an asset, and retainage you hold from subs as retainage payable, a liability. Under current revenue standards you may report profit on work before the retainage is collected, so cash lags. Ask a CPA about classification and tax timing.

People also ask