Electrical
Construction cash flow and WIP management field guide
Construction runs on cash, not paper profit. Read the WIP to catch underbilling and margin fade early, bill early and often, and collect fast, including retainage and change orders.
Direct answer
Construction is a cash-flow business, and profitable contractors still go broke because cash leaves for labor and material weekly long before it arrives, billed monthly and paid in 30 to 60 days with retainage held back. The work-in-progress schedule tells the truth: it shows whether each job is overbilled or underbilled.
Key takeaways
- Construction cash goes out weekly for labor and material but comes in monthly, paid net 30 to 60, so profitable contractors still go broke.
- The work-in-progress (WIP) schedule shows job by job whether you are overbilled (billed ahead of work) or underbilled (work ahead of billing); run it at least monthly.
- Underbilling is the top hidden cash drain: any job where percent complete by cost runs ahead of percent billed is funding the owner's project with your money. Find it and bill it.
- Cost-to-cost percent complete equals cost incurred to date divided by total estimated cost at completion; 600,000 of 1,000,000 is 60 percent complete.
- Retainage, commonly 5 to 10 percent held until work is accepted, is usually your largest tied-up receivable, so track it as its own line by job.
Cash flow management, and why profitable contractors go broke
Construction is a cash-flow business before it is anything else. You can finish a job at a healthy margin, show a profit on every line of the income statement, and still miss payroll, because the money goes out the door for labor and material every week while it comes back in monthly, gets paid 30 to 60 days after that, and has retainage held on top. Profit is an accounting opinion. Cash is a fact.
The tool that tells you the truth, job by job, is the work-in-progress schedule, usually just called the WIP. It lines up what each job has cost, how complete it is, and how much you have billed, and it shows whether you are ahead of your billing or behind it. Read it right and it warns you about trouble months before the bank balance does.
This guide covers how the cash actually moves, how to read a WIP, the difference between being overbilled and underbilled, and the billing and collection habits that keep money in the account. Two pieces sit next to this one. The held-back money has its own guide on retainage, and the right to get paid has its own guide on mechanics liens and preliminary notices. The accounting method itself belongs to your construction CPA. The WIP and percentage-of-completion are their lane.
Profit is not cash
The number that kills contractors is not the margin. It is the cash. Firms go under while profitable on paper more often than they go under losing money, because a paper profit does not pay a Friday payroll. The income statement recognizes revenue as you earn it, not as you collect it, so a job can post a gross profit in the same month the bank account drops.
Picture two contractors who both report the same profit for the year. One billed on time, collected fast, and kept the held-back money moving. The other did the same volume of work but billed late, let receivables age, and financed the gap out of the operating account. Same profit. One has cash and one is borrowing to make payroll. The accounting cannot tell them apart. The bank statement can.
This is why the office cannot run the company off the profit-and-loss alone. Profit answers whether the work was priced and built right. Cash answers whether the company survives long enough to collect on it. Both matter, and on a growing book they pull in opposite directions, because every new job spends cash before it returns any.
The gap between cash out and cash in
The gap is a timing problem, and it is structural, not a sign you did anything wrong. Cash goes out fast and comes in slow. Labor hits weekly. Material and rented equipment hit on their own terms, often net 30 if you have credit and cash on delivery if you do not. Against that, you bill once a month, the pay application takes time to certify, the owner pays on net 30 that behaves like net 45 to 60, and retainage is held out of every check until the end.
Add it up and the money you spent in week one can be 90 days or more from landing in the account. That window is the gap you finance, every job, with your own working capital or a line of credit.
The shape of it follows the job's S-curve. Spending starts slow at mobilization, ramps hard through the middle when the crew is at full size, then tapers at closeout. Collections trail that curve by the billing-and-payment lag the whole way. The widest point of the gap is usually mid-job, at peak manpower, which is exactly when a second or third job is also ramping. That is the squeeze that catches growing contractors: more work, more profit coming, no cash to run it.
The WIP schedule is the truth-teller
The WIP schedule is one row per active job and a handful of columns that, read together, tell you whether the job is feeding cash or draining it. The four inputs are the contract value including approved change orders, the total estimated cost at completion, the cost incurred to date, and the amount billed to date. From those it computes percent complete, earned revenue, and the gap between what you have earned and what you have billed.
That last gap is the whole point. If you have billed more than you have earned, the job is overbilled. If you have earned more than you have billed, it is underbilled. The WIP is where you find that out before it becomes a cash event.
Run it monthly at a minimum, and on troubled jobs more often. The discipline that makes it useful is honesty in two numbers: the real cost to date and a straight estimate of the cost still to come. Garbage in those columns and the WIP lies to you in a comforting direction. A field tool like FieldOS that ties labor hours, material, and billing to the job in real time gives the office current numbers to build the WIP from, instead of cost data that is three weeks stale by the time it is keyed in. The format and the accounting method are your construction CPA's call. Reading it and acting on it are yours.
Overbilled vs underbilled
Every job on the WIP lands on one side of a line: billings in excess of costs, or costs in excess of billings. The words are a mouthful, so the trade says overbilled and underbilled. They are opposites, and they mean opposite things for your cash.
Overbilled, billings in excess of costs, means you have billed ahead of the work in place. The cash feels good, but you have not earned it yet. You owe that work, and the money sitting in the account is borrowed from the back end of the job.
Underbilled, costs in excess of billings, means the work is ahead of the billing. You did it, you paid for it, and you have not invoiced it. That is your cash financing the owner's project. It is the leak that sinks profitable companies.
Most healthy contractors run modestly overbilled across the book, by design, because a small overbilled position front-funds the cash gap. The danger sign is a job that swings the wrong way over time, or a company-wide underbilled position that means you are bankrolling your customers.
| Overbilled (billings in excess of costs) | Underbilled (costs in excess of billings) | |
|---|---|---|
| Plain meaning | Billed ahead of the work | Work ahead of the billing |
| Cash effect | Cash in hand now | Your cash funding the job |
| The catch | Not earned, owed back in work | Real profit and cash not yet collected |
| What it signals | Front-funded, watch the job-end runway | Billing is behind, find it and bill it |
Underbilling is the hidden cash drain
Underbilling is the number-one hidden cash drain in construction, and it hides because it does not show up as a loss. The job is still profitable. You just have not billed for what you built, so your money is sitting in the owner's project instead of your account.
It creeps in quietly. The crew got ahead of the schedule and the billing did not catch up. A change order is in place but never got priced and added to the pay application. Costs ran heavier early than the billing curve assumed. Stored material is on site and paid for but left off the requisition. Each one is work you have funded and not invoiced.
The WIP is where you catch it. Any job where percent complete by cost is running well ahead of percent billed is underbilled, and the dollar gap is cash you are owed and have not asked for. The fix is not complicated. Find it and bill it. Add the missed scope, the approved changes, and the stored material to the next pay application. Chronic underbilling across several jobs at once is how a company with a full backlog and good margins runs out of money.
Overbilled cash is borrowed cash
Being overbilled is normal and often smart, but it is borrowed cash, and contractors get in trouble when they forget that. Billing ahead of the work front-funds the cash gap, which is fine. Spending that cash as if it were earned profit is not, because the back end of the job still has to be built with no billing left to cover it.
The trap is the front-loaded job at closeout. You weighted the early billing, collected well, and felt flush. Now you are at 90 percent complete with only the hard, slow, low-margin work left, the punch list and the closeout, and you have already billed nearly the whole contract. Real cost is still going out and almost no cash is coming in. The job that looked best in month two strangles you in month ten.
Read the overbilled position on the WIP as a liability, because that is what it is. It is a measure of work you owe. Keep enough billing runway at the end of each job to cover the cost of finishing it, and do not let an overbilled balance on one job paper over an underbilled mess on another.
How is percent complete figured?
Percent complete is what turns cost and billing into a read on the job, and the common way to figure it is the cost-to-cost method: cost incurred to date divided by the total estimated cost at completion. Spend 600,000 of an estimated 1,000,000 and the job is 60 percent complete. Multiply that percentage by the contract value and you have earned revenue, the revenue the accounting recognizes whether or not you have billed or collected it.
The method is only as good as the denominator. The total estimated cost has to be honest and current, including approved change orders and a real estimate of what is left. If your estimate to complete is stale, the percent complete is wrong, the earned revenue is wrong, and the job's over- or underbilled position is wrong in a way that flatters you. That is how margin fade hides.
Percentage-of-completion is an accounting method with rules around it, and the exact application, the contract-by-contract treatment, and the financial statements belong to your construction CPA and the contract terms. Your job in the field and the office is to feed it accurate cost and a straight estimate to complete. Cost-to-cost is the usual input method, but some contracts and some scopes are measured other ways, so confirm the method with your accountant.
The schedule of values
The schedule of values is how the contract gets carved into billable line items, and it is the basis of every pay application you submit. Each line gets a dollar value, the values add to the contract sum, and each month you bill the percent complete of each line. Build the SOV right and billing is straightforward. Build it carelessly and you fight your own paperwork every month.
A good SOV has enough lines to bill the work the way it actually goes in, with the early scope broken out so you can bill it as you complete it. Lump too much into one big line and you cannot bill it until the whole line is done, which strands cash. Break out mobilization, submittals, and major material so the early cash is billable when the cost is real.
Stored material gets its own treatment. Most contracts let you bill for material delivered to the site and properly stored and protected, ahead of installing it, which pulls that cash in sooner. It usually takes backup, proof of delivery, and sometimes proof it is paid for and insured. The contract spells out the rules, so read them before you assume the stored-material line will pay.
Front-loading the schedule of values
Front-loading means weighting the early line items of the SOV so the billing runs a little ahead of the cost early in the job. Done within reason it is a legitimate cash tool, because it offsets the mobilization and ramp-up spending that hits before any real billing would otherwise land. Done greedily it is a problem, for you and for the owner.
The honest version weights the early work where there is real value to weight: mobilization, submittals, the front-end engineering and material buys that genuinely happen early. The owner's architect or construction manager reviews the SOV and will push back on values that do not match the work, and a pay application that smells front-loaded gets bounced or slows down certification. Overdo it and you have set the back-end trap on yourself, with no billing left to finish the job.
The line to hold is this: weight the early items where the cost is genuinely early, and do not borrow so far forward that the closeout cannot pay for itself. Front-loading is a timing tool, not free money. The work still has to get built against a contract that is already mostly billed.
Bill early, often, and clean
The single most reliable cash habit in construction is to bill on time, every time, for everything you have earned. The pay application goes in the day the billing window opens, not whenever the office gets to it, because a pay app submitted a week late is a month late getting paid. Cash you do not bill is cash you are lending the owner for free.
Bill for everything in place. The completed percent of every SOV line, the stored material the contract allows, and every approved change order. Money left off the requisition is the underbilling that drains the account, and it is the easiest dollar in construction to lose, because nobody stole it. You just did not ask for it.
Accuracy is part of speed here. A pay application that ties out, with the math right and the backup attached, gets certified and paid. One with errors gets kicked back and waits another cycle. So the habit is both: bill early and bill clean. Run the billing off current job costs, which is where a field tool that keeps cost and completion current earns its keep, because you cannot bill accurately off numbers you do not have yet.
The pay application and the AIA forms
The pay application is the formal request for payment, and on most commercial work it follows the AIA G702 and G703 format or something close to it. The G702 is the summary: the contract sum, change orders, the total completed and stored, retainage, and the balance due. The G703 is the continuation sheet, the line-by-line schedule of values with the percent and dollar complete for each line this period.
Get it right or it bounces. The totals on the summary have to tie to the continuation sheet and to the prior period. The architect or construction manager certifies it, and they will refuse to certify over simple math errors, unapproved or unpriced change work, stored material without backup, or values that look front-loaded. Every bounce is another billing cycle of delay, which is real cash.
Most pay applications also require lien waivers with the requisition, conditional on the current payment and unconditional for the prior one. Sign those carefully, because a waiver can sign away the right to get paid for work you have not actually collected on. The mechanics-lien and preliminary-notice guide covers how waivers and lien rights interact. Keep the waiver you sign matched to the payment you actually received, not the one you were promised.
Collect fast, and protect the right to collect
Billing is half the job. Collecting is the other half, and it is where the cash actually shows up. Submitting the pay application and then waiting quietly is how net 30 turns into 60 and 90. Track every receivable, age it, and work the phone the day an invoice goes past terms.
An aging report by job and by customer tells you where the money is stuck before it becomes a crisis. The owner who slow-pays the first requisition will slow-pay all of them unless you make payment a conversation from the start. Standard terms in the industry are net 30, but the reality for many subs is closer to 56 days, so manage to the reality, not the contract's optimistic number.
What you have on a customer who will not pay is your lien rights, and those rights depend on paperwork you do at the start of the job, not the end. The preliminary notice sent on day one and the deadlines that follow are what give the unpaid invoice teeth. On public jobs the lien attaches to a payment bond instead of the property. The mechanics-lien and preliminary-notice guide walks through preserving that right. Protect it on every job, because the threat of a lien collects more bills than any phone call.
Retainage is your biggest tied-up receivable
Retainage is the slice of every payment the owner or general contractor holds back until the work is accepted, commonly 5 to 10 percent, and it is usually the largest single chunk of cash you have tied up at any moment. Five percent across a whole book of work is often more than a year's profit, sitting in someone else's account until substantial completion.
On the WIP and the cash forecast, retainage has to be tracked as its own receivable, job by job, because it does not behave like the rest of the billing. You earn it as you go but you cannot collect it until the end, sometimes long after the work is done, while you wait on closeout, the punch list, and the owner's process. Forget to bill the retainage release and it just sits there.
Because it ties up so much for so long, retainage is worth managing actively: negotiating the rate and a cap up front, requesting early release of completed scope where the contract allows, and having closeout ready so nothing delays the release. That is its own discipline, and the retainage and retention guide covers the rate, the caps, the step-downs, and how to get finished scope released early. Track every held-back dollar so none of it gets forgotten.
The change-order cash leak
Unbilled change-order work is a direct hole in your cash, because it is work you are funding with nothing coming back. The field gets a verbal go-ahead or a get-it-done, the crew builds it, and the cost lands in your job cost while the billing does not, because the change was never priced, approved, and added to the contract. That is underbilling created on purpose, one change order at a time.
The cost of this is twofold. The cash is out with no billing against it, and the margin on the extra work erodes or vanishes if it is ever settled at all. Work performed on a handshake gets disputed at closeout, when your bargaining position is gone and the owner is looking for givebacks.
The discipline is simple to say and hard to hold: price the change, get it approved in writing, get the contract value and the SOV updated, then build it and bill it. Free work is not goodwill, it is unfunded cost. If schedule pressure forces the crew to start before the paperwork catches up, price it and put the owner on written notice so the billing can follow. Track open change orders the way you track receivables, because that is what they are.
Margin fade, and catching the loser early
Margin fade is the quiet erosion of a job's profit from the margin you estimated to the margin you actually finish with, and the WIP is where you catch it early, while you can still do something. It shows up as the estimated cost to complete creeping up month over month, which drops the projected profit on the job a little at a time until the cushion is gone.
The causes are the usual ones: labor running over the estimated hours, material bought higher than bid, rework, scope creep, and change-order work done but not priced. Labor productivity is usually the earliest warning, a crew running 20 hours over at the halfway mark, and it shows in the cost-to-cost percent complete before it shows anywhere else.
The reason the WIP beats the year-end financials is timing. Run it monthly and a job's fade announces itself in month four, when you can re-sequence, tighten the crew, settle the changes, or at least stop the bleeding. Wait for the closeout numbers and you find out the loser was a loser after the money is spent. Catch the fade while the job is still running. The honest input that makes this work is the estimate to complete, which is the next section.
The cost to complete
The estimate to complete is an honest answer to one question: what will it cost to finish the work that is left. Not what is left in the budget, what it will actually take, in real dollars, from here to done. It is the single most important number in the WIP and the one contractors fudge most, because an optimistic estimate to complete makes every job look better than it is.
Cost spent to date is a fact you can pull off the books. Cost to complete is a judgment, and it has to be made by someone who knows where the job actually stands, usually the PM and the field, not the office working off the original budget. The original estimate is a starting point, not the answer, because the conditions changed the day the job started.
This number drives everything downstream. It sets the total estimated cost, which sets percent complete, which sets earned revenue and the over- or underbilled position, and it is what surfaces a loss while you can still react. A job where the estimate to complete keeps climbing is a job in trouble, and an honest cost to complete is what tells you early instead of at closeout.
The cash forecast
A cash forecast projects the money in and the money out, by week or by month, across every active job, so you can see the crunch before you are in it. The WIP tells you where each job stands today. The forecast tells you what the bank account does over the next 8 to 13 weeks, which is the horizon that matters for making payroll.
Build it from the real timing, not the optimistic version. Lay out the cash going out, payroll, material, subs, and overhead, against the cash coming in, the billings you expect to collect and when they will actually land given how each owner really pays, plus the retainage you expect to release. The gaps jump out: the week three jobs are all at peak labor and no big collection lands until the following month.
A forecast is what turns a surprise into a plan. See the gap four weeks out and you can pull billing forward, lean on a slow-paying customer, draw on the line of credit deliberately, or slow a start. See it the morning payroll is due and your only options are bad ones. The contractors who do not get caught are not the ones with the most cash. They are the ones who saw the gap coming.
The line of credit and working capital
A line of credit is the working capital that bridges the gap between cash out and cash in, and on a growing book you will use one, because growth eats cash faster than profit replaces it. Every new job spends before it collects, so the more work you take on, the more bridge financing the timing gap demands, even when every job is profitable.
The line is a tool, not free money. You pay interest on what you draw, so borrowed cash carries a cost that comes straight off the job's margin, and a company that lives permanently maxed out on its line is usually masking an underbilling or collection problem rather than funding healthy growth. Use the line to cover timing, not to cover losses.
The bank that extends the line will want to see your WIP and your cash forecast, because those are what tell them whether the gap is a timing issue they can safely bridge or a hole that will not close. A clean, current WIP is what gets you the credit and the rate. The same numbers that run the company are the ones that finance it.
What the surety and the bank read
On bonded work the surety underwrites your capacity to finish jobs, and they read your WIP and your financials harder than your banker does. Bonding capacity, the size and number of jobs they will bond, rests on your working capital, your net worth, and the story your WIP tells about how you run jobs. A messy WIP, big swings between over- and underbilled, jobs fading, and that capacity tightens or disappears.
A clean WIP does the opposite. Jobs that track close to their estimates, a sensible billing position, an honest cost to complete, and the surety reads a contractor in control of the work, which is what they are betting on when they back your bonds. The same goes for the bank. The WIP and the cash forecast are the documents the relationship runs on.
The practical lesson is that the WIP is not just an internal tool, it is the financial face you show the people who fund and bond you. Keep it accurate and current as a matter of course, because the time you need bonding capacity or a credit increase is the worst time to be cleaning up the numbers. The surety, the bank, and your construction CPA all read the same WIP. Give them one they can trust.
What to document
The cash side of the business runs on a short list of documents, and the company that keeps them current makes money the company that keeps them in someone's head loses. Keep the WIP, the schedule of values for each job, the pay applications and their backup, the accounts-receivable aging, the open change-order log, the cost to complete by job, the cash forecast, and the retainage receivable by job. Each one feeds the next.
The reason to keep them current rather than catching up at quarter end is that stale numbers hide the exact problems they exist to surface. A WIP built off cost data three weeks old cannot warn you about the job fading today. This is where tying the field to the office matters: a tool like FieldOS that captures labor, material, and progress against the job as it happens gives the office live cost to build the WIP and the billing from, instead of numbers that are old before they are entered.
| Document | What it is for |
|---|---|
| WIP schedule | Over/underbilled position and fade, job by job |
| Schedule of values | Basis of every pay application |
| Pay applications and backup | Billing on time and getting certified |
| AR aging by job and customer | Collecting fast, finding stuck money |
| Open change-order log | Pricing and billing change work, not funding it |
| Cost to complete by job | Honest percent complete and early loss warning |
| Cash forecast | Seeing the cash crunch before it hits |
| Retainage receivable by job | The held-back money tracked so it gets collected |
Field checklist
Want this checklist to run itself on every job — with photo proof and a signed record crews can hand the customer? That's FieldOS.
Common mistakes
- Reading the profit-and-loss and assuming cash in the bank, when profit is earned and cash is collected.
- Not running a WIP, so over- and underbilling and margin fade stay invisible until closeout.
- Chronic underbilling that quietly finances the owner's project with your working capital.
- Billing late or sloppily, so pay applications bounce and net 30 stretches to 60 or 90.
- Building change-order work on a handshake without pricing, approving, and billing it.
- Carrying an optimistic cost to complete, so the margin fade is caught after the money is gone.
- Spending an overbilled balance as if it were earned, then running out of billing at closeout.
- Letting retainage sit untracked until it is forgotten.
Standards and references
There is no building code for cash flow. The authorities here are your construction CPA, the contract, and the surety and bank, and each governs a different piece.
The accounting method, percentage-of-completion, the cost-to-cost calculation, how the WIP is built, and how over- and underbillings hit the financial statements, is your construction CPA's territory and follows the applicable accounting standards. Cost-to-cost is the common input method, but the right treatment for your contracts is a conversation with your accountant, not a rule of thumb. The contract controls the money mechanics: the schedule of values, the billing cycle and pay-application format, the stored-material rules, the retainage rate and release, and the payment terms. Read it before you build the SOV, because the contract, not habit, sets how and when you can bill. The surety and the bank set your capacity, and they read the WIP and the cash forecast to do it.
Three things hold across all of it. Profit is not cash, and construction runs on cash flow. Run the WIP to catch underbilling and margin fade early, while you can still act. And bill early and often and collect fast, including the retainage and the change orders, because the fastest cash in construction is the cash you already earned and have not yet asked for. The held-back money has its own guide on retainage. The right to collect has its own guide on mechanics liens and preliminary notices.
Units, terms, and synonyms
The cash side of construction has its own vocabulary, and the same idea goes by more than one name across an accountant's report, a contract, and the field.
Overbilled and underbilled are the shop words for billings in excess of costs and costs in excess of billings. Percentage-of-completion is the accounting method, cost-to-cost is the usual way to measure the percent. The schedule of values, the SOV, is the billing breakdown, and the pay application, often AIA G702 and G703, is the monthly request built from it. Retainage and retention are the same held-back money. Margin fade and profit fade are the same erosion.
- Construction cash flow
- The timing of money out for labor and material against money in from billing and collection; the company runs on it
- WIP schedule
- Work-in-progress report comparing cost incurred and percent complete to billings, job by job, to show over/underbilling and fade
- Overbilled (billings in excess of costs)
- Billed ahead of the work in place; cash in hand now but not yet earned and owed back in work
- Underbilled (costs in excess of billings)
- Work ahead of the billing; your cash funding the job, real profit and cash earned but not yet invoiced
- Percentage of completion
- Accounting method that recognizes revenue as work is earned, commonly measured cost-to-cost
- Cost-to-cost
- Cost incurred to date divided by total estimated cost at completion, the usual percent-complete input
- Schedule of values (SOV)
- The contract broken into billable line items that add to the contract sum; basis of the pay application
- Front-loading
- Weighting early SOV line items so billing runs ahead of cost early in the job
- Margin fade
- The estimated job margin eroding toward the actual as costs run over; the WIP shows it early
- Cost to complete
- An honest estimate of what it will take to finish the remaining work, not what is left in the budget
FAQ
What is a WIP schedule in construction?
A work-in-progress schedule is a report with one row per active job that compares the cost incurred and percent complete against the amount billed. It shows whether each job is overbilled or underbilled, where margin is fading, and which jobs are feeding cash or draining it. Most contractors run it monthly.
What is the difference between overbilled and underbilled?
Overbilled, or billings in excess of costs, means you have billed ahead of the work, so the cash is in hand but not yet earned. Underbilled, or costs in excess of billings, means the work is ahead of the billing, so your cash is funding the job. Underbilling is the dangerous one.
Why do profitable contractors run out of cash?
Because profit is earned and cash is collected, and the two arrive at different times. Cash goes out weekly for labor and material long before it comes in, billed monthly, paid in 30 to 60 days, with retainage held back. A profitable job can still leave the bank account empty when payroll is due.
What is percentage of completion in construction accounting?
Percentage of completion recognizes revenue on a job as the work is earned, not when you bill or collect. The common measure is cost-to-cost: cost incurred to date divided by total estimated cost. The exact method and treatment belong to your construction CPA and the contract, so confirm them rather than assuming cost-to-cost.
How do I fix chronic underbilling?
Find it on the WIP and bill it. Any job where percent complete by cost runs ahead of percent billed is underbilled. Add the missed scope, the approved change orders, and the stored material to the next pay application, and tighten the billing cycle so the crew never gets that far ahead again.
Is front-loading the schedule of values allowed?
Modest front-loading, weighting early line items where the cost is genuinely early like mobilization and material, is common and accepted. Overdoing it is not: the owner's architect reviews the schedule of values and will reject a pay application that looks front-loaded, and you strand yourself with no billing left to finish the job.
How much retainage is held on a construction job?
Retainage is commonly 5 to 10 percent of each payment, held until the work is accepted, but the rate, cap, and release rules are set by the contract and can vary by state. It is often your largest tied-up receivable, so track it by job. The retainage guide covers negotiating and releasing it.
What is margin fade and how do I catch it?
Margin fade is a job's profit eroding from the estimated margin to the actual, usually from labor overruns, rework, or unpriced change work. The WIP catches it early, because the estimate to complete creeping up drops the projected profit month over month. Run the WIP monthly and you see the loser before closeout.
How often should I run a WIP schedule?
Run the WIP at least monthly, in step with the billing cycle, and more often on jobs that are large, fast, or already in trouble. It is only as honest as its inputs, so update the cost to date and the estimate to complete before each run. Stale numbers hide the problems the WIP exists to catch.