ANVILFIELD Try FieldOS

Field glossary · business

Schedule of values (SOV)

Use a schedule of values (SOV) to reconcile scheduled price, installed work and eligible stored material on each pay application. For a $100,000 contract with $60,000 completed and stored, G703 column H totals $40,000 remaining. At 5% retainage, G702's balance including retainage is $43,000. A stored-material transfer changes billing categories without earning the same equipment value twice, so billing progress and installed progress need separate readings.

The contract broken into billable line items that add to the contract sum; basis of the pay application

Used across 2 Anvilfield field guides, most in Electrical.
Updated

Carry stored materials forward in the right place

AIA's G703-1992 instructions carry the previous application's columns D plus E into the current column D. Previously stored material from F stays outside that carry-forward. Moving the entire previous completed-and-stored total into D would treat stored equipment as installed work.

AIA's G703-1992 instructions move material value from column F to column E when the material is incorporated into the project. That transfer records installation without creating a second payment for the same material. Reconcile it by the equipment or material identifier used in the billing-backup record.

Follow a $30,000 material balance into installation

The SOV for a $100,000 contract previously totals $20,000 of installed work and $30,000 of stored material, or $50,000 completed and stored. During the next period, the crew incorporates $20,000 of that stored material and completes another $10,000 of installation work. No new material enters storage.

The current application carries $20,000 as prior installed work, recognizes the $20,000 material transfer plus $10,000 of new installation in current work, and leaves $10,000 stored. Only $10,000 of additional gross value has been earned; the transferred $20,000 was already inside the preceding $50,000 total.

Leaving the entire $30,000 in storage while adding the same $20,000 to completed work would report $80,000 cumulatively. The $20,000 overstatement comes from duplicate material value, even though every underlying supplier invoice is genuine. Correct the movement between categories on each affected line.

Current application column totalAmountReconciliation
C, scheduled value$100,000Contract sum allocated across SOV lines
D, previous completed work$20,000Prior installed amount only
E, work completed this period$30,000$20,000 transferred material + $10,000 installation
F, presently stored$10,000$30,000 prior storage - $20,000 incorporated
G, completed and stored$60,000D + E + F
H, scheduled value remaining$40,000C - G, excluding retainage

Why $40,000 remaining becomes $43,000 with retainage

AIA G703 calculates each line's billing percentage as completed and stored value divided by scheduled value. Across this SOV, $60,000 divided by $100,000 reports 60%, including $10,000 still stored. Installed-work value alone is $50,000, or 50%. Carry an installed-quantity or milestone measure beside the billing percentage so the report identifies what is physically in place.

AIA's payment-application instructions distinguish G703 column H from G702 line 9. In this $100,000 contract, 5% retainage on $60,000 is $3,000. G703 H remains $40,000; G702 line 6 is $57,000 earned less retainage, and line 9 is $100,000 - $57,000 = $43,000 including retainage. Neither remaining contract value is a construction cost-to-complete forecast.

With the same 5% retainage on the previous $50,000 application, the preceding certificate was $47,500. AIA's G702 line 8 calculation now produces $57,000 - $47,500 = $9,500 due. Use previous certified amounts for this subtraction, even if collection is late; track that receivable separately in cash flow and WIP management.

Storage eligibility and certification need separate evidence

On a contract incorporating FAR 52.232-5, May 2014, paragraph (b)(2) permits off-site material consideration only with specific contract authorization and satisfactory evidence of the contractor's title and intended use on that contract. An invoice and an SOV entry do not establish those conditions by themselves.

AIA's G702-1992 instructions require the architect to explain a certification differing from the application and initial changed figures on G702 and G703. Retain the submitted application and the certification together. Carry the accepted figures into the next reconciliation so a rejected stored-material amount does not quietly reappear as previously approved work.

Distinctions

Cost to complete
Forecast the labor, purchases and subcontract cost needed to finish. Neither the $40,000 remaining scheduled value nor the $43,000 balance including retainage measures that cost; both derive from the selling-price allocation.
Unpaid receivable
An amount already billed or certified but still uncollected. Late collection does not create additional completed work on the next application.

Frequently asked questions

Should paid stored material disappear from the next pay application?

No. Under G703-1992, it stays in the presently stored balance until incorporation into the work. Payment alone does not change its physical status.

Can a line be 60% billed when less than 60% is installed?

Yes, when contract-eligible stored material is included. Show that material separately and explain the installed-work measure so the progress report and the payment application describe their different bases accurately.

Sources checked

Also defined as

  • Datacenter: The contract sum broken into billable line items, the basis billed against each period

Where this shows up

Next step: Build a bid packet

Back to the full field glossary