Field glossary · measurement
Percent complete
Percent complete equals credited progress divided by the agreed total, multiplied by 100. Name what earns credit: installed units, accepted milestones, earned value or completed-and-stored billing value. On AIA G703, stored material contributes before installation, so its percentage can exceed physical progress. A report showing 48 of 60 devices installed is 80 percent installed; if only 36 have passed testing, it is 60 percent tested. Keep both denominators and the status date visible.
The portion of a line finished to date, most defensible when tied to a countable quantity rather than an eyeball
Why a G703 percentage can exceed installed progress
AIA's instructions for G703-1992 calculate the percentage as column G divided by column C, where G totals prior work, current work and presently stored materials. That billing percentage therefore includes an inventory component. Label it completed and stored rather than presenting it as installed progress.
A line with a scheduled value of 200,000, completed work worth 80,000 and eligible stored materials worth 40,000 reports 120,000 / 200,000 = 60 percent completed and stored. Installation value alone is 40 percent. Use the same currency unit for every value. Put the physical quantity or milestone beside the billing measure in the owner report.
Move material value without counting it twice
AIA's G703-1992 instructions move stored material value from column F to work completed as the material is incorporated into the project. Payment for the material alone does not remove it from F. Installation is the event that changes its classification.
In the next period, installing 20,000 of the material already billed moves that amount into current work and reduces stored materials by the same 20,000. With no added labor or other new value, total completed and stored remains 120,000 and the line remains 60 percent. Counting the transfer as another 20,000 of earned value would overstate the line.
Reconcile the acceptance basis at the cutoff date
FAR 52.232-5, May 2014, bases federal construction progress payments on contracting-officer-approved estimates of work meeting contract quality requirements. On-site stored material can be included when the contracting officer authorizes it. For off-site material, the clause also requires specific contract authorization and satisfactory evidence of the contractor's title and intended use on that contract. A delivery ticket alone does not establish those conditions.
Freeze the quantity denominator and the reporting date for each update. When an approved change adds devices, show the revised total and recompute progress against it. Separately state installed, tested and accepted quantities where those gates differ. A device placed in position and a device with completed functional tests should not silently earn the same progress credit.
Distinctions
- Percent billed
- Cumulative invoicing divided by the contract value measures billing position. It does not measure installation or payment received.
- PPC
- Percent Plan Complete counts promises finished on time; it does not weight their quantities or scheduled values.
Frequently asked questions
Can an owner report and pay application show different percentages?
Yes, when one explicitly reports installed progress and the other completed-and-stored value. Reconcile the difference in the report so the reader can reproduce both calculations.
Sources checked
Also defined as
- Progress on a scope, most defensible when anchored to a countable quantity rather than an eyeball estimate