Workmanship warranty
A workmanship warranty assigns responsibility for correcting covered installation defects. Record its start event and repair history, because substantial completion, final acceptance, and later corrective work can start different clocks. AIA A201-2017 generally gives one correction year without restarting it for repairs; FAR 52.246-21 starts a new warranty year for repaired or replaced work. Neither clock alone describes every surviving contract obligation.
Your promise that the install was done correctly. Covers your labor and your details, commonly for about a year, but your contract controls the scope and the term.
What event starts the correction period?
AIA A201-2017 Section 12.2.2.1 generally starts the one-year correction period at substantial completion, subject to designated portions and specified commencement dates. FAR 52.246-21, Warranty of Construction (March 1994), starts its one-year warranty at final acceptance, or at earlier government possession for the part taken over.
These are different contract triggers, so a register labeled only completion date is incomplete. Identify the contract form, the controlling milestone, the covered portion, and the document establishing that date. A roof, an occupied wing, and the final accepted project can have different records. Use the closeout guide to connect them to the turnover package.
Does corrective work restart the warranty clock?
Under AIA A201-2017 Section 12.2.2.3, corrective work does not extend the correction year. FAR 52.246-21(d) gives repaired or replaced work a one-year warranty measured from its repair or replacement date. The repaired scope needs its own entry when that federal clause applies.
Under AIA A201-2017 Section 12.2.2.2, the correction year for original work first performed after substantial completion runs from that portion's actual completion. Record that date separately from a repair to work already completed, even when both happen on the same return visit.
A repair in month nine under the two forms
Take work reaching both substantial completion and final acceptance on November 5, 2026, followed by a corrective repair on August 5, 2027. Under unmodified A201's correction-period provisions, that repair does not move the original November 5, 2027 end date. Under FAR 52.246-21(d), the repaired work carries its warranty through August 5, 2028.
The later federal date applies to the work repaired or replaced, rather than restarting every component's warranty. Keep the original defect report, written notice, exact repair scope, repair date, and acceptance evidence together. A building-level anniversary field alone loses the distinction. Read any issued special warranty alongside the contract before entering the applicable date.
The correction year does not define every claim deadline
AIA A201-2017 Section 12.2.5 separates the correction year from time limits on other contract duties. FAR 52.246-21(j) preserves rights under the applicable inspection-and-acceptance clause. For construction, FAR 52.246-12(i) specifies latent defects, fraud, and gross mistakes amounting to fraud among the exceptions to final acceptance. An ordinary mistake is not automatically within that last exception.
Distinguish that correction obligation from a separately issued product or system warranty. The roof warranty guide explains the coverage documents; the warranty cost guide tracks the resulting expense. The date register identifies which promise a particular repair is being handled under.
Distinctions
- Design life
- A design-life statement describes expected service under stated conditions. It does not identify the repair remedy, responsible party, notice process, or contractual start date that makes a warranty usable.
Frequently asked questions
Does an AIA correction claim need notice before the year ends?
A201-2017 Section 12.2.2.1 calls for prompt notice and an opportunity to correct during the correction year, with waiver consequences if the owner fails to provide them. Keep discovery, notice, response, and repair dates in separate fields; a dated repair invoice alone does not establish when notice was given.
Sources checked
Also defined as
- Roofing: Coverage for the installation obligations accepted by the issuing contractor
- The contractor's coverage of installation quality, commonly a one-year correction period set by the contract