Preliminary notice

Preliminary notice tells the owner which contractor or supplier is furnishing to the job and establishes coverage for later payment remedies. Late service has different consequences by jurisdiction: California's private-work notice reaches back 20 days, while Florida's notice to owner has a 45-day limit that can close earlier at final payment. Separate furnishing dates from invoice dates so the office can identify the protected portion of an account, not just whether a notice exists.

The early notice (also called prelien notice or notice to owner) sent near the start of a job to preserve the right to lien; required in many states.

Used across 2 Anvilfield field guides, most in Electrical.
Updated

What a late California notice still protects

California's Contractors State License Board explains that a subcontractor or material supplier serving a late preliminary notice retains lien coverage for furnishing within the preceding 20 days and afterward. Earlier furnishing falls outside that protected period. This makes late service materially different from abandoning notice altogether.

A supplier first delivers on September 1 and serves notice on September 30. The 20-day lookback reaches September 10. With 8,000 dollars delivered September 1, 6,000 on September 12 and 4,000 on September 25, the furnishing inside that window totals 10,000 dollars; the earlier 8,000 falls outside it. Date each delivery line rather than assigning the entire 18,000-dollar order to its first shipment.

CSLB's checklist gives subcontractors and material suppliers 20 days from beginning work or delivering material to serve timely notice. Sending the notice when the account reaches its first collection reminder is already behind that furnishing-based schedule.

Florida has a 45-day limit and an earlier cutoff

Florida Statutes 713.06(2)(a), in the 2026 statutes, requires the notice for lienors covered by that section except laborers. Service must occur before furnishing or within 45 days after furnishing begins, and before the owner's final disbursement after the contractor's statutory final-payment affidavit. The laborer exemption and the final-payment cutoff both belong on the intake checklist.

The same Florida subsection makes untimely notice a defense to enforcement for a claimant required to serve it. Unlike California's rolling coverage window, Florida's rule does not preserve later deliveries merely because they occurred within 45 days before service. Obtain the owner's identity and notice-of-commencement information while the first delivery is being scheduled.

Keep the notice record separate from the debt record

Florida Statutes 713.06 expressly distinguishes notice to owner from a lien or an encumbrance on the property. Notice tells the owner who is contributing to the improvement; the later claim documents address the unpaid debt.

Use separate fields for first furnishing, notice service, proof of service and amounts still due. That keeps the collection process from overwriting the event that began the notice clock. The mechanics-lien guide connects this early record to later recording, enforcement and waiver decisions.

Distinctions

Notice to owner versus payment demand
A notice can precede any invoice or default. A demand asks for payment of an existing balance; sending one does not establish that the statutory early notice was served.

Frequently asked questions

Does a purchase-order date start the notice period?

The cited California and Florida rules use furnishing events. Preserve the first delivery or work record instead of substituting the date that purchasing approved the order.

Does the notice go only to the owner?

Florida Statutes 713.06(2)(a) also requires copies up the contracting chain for specified sub-subcontractors and suppliers. Identify who hired the furnishing party before choosing recipients; a mailing addressed only to the project manager does not establish that the required parties were served.

Sources checked

Also defined as

  • Plumbing: An early notice to the owner that preserves lien rights; deadline varies by state