Field glossary · business
Payment bond
A payment bond gives eligible unpaid labor and material claimants recourse against the surety named on a particular contract. The contracting tier determines the notice route. On federal Miller Act work, a supplier to a first-tier subcontractor faces a 90-day notice deadline as well as the separate one-year lawsuit limit. Obtain the executed bond before extending credit, then calendar notice and court filing separately from the surety's claim review.
A surety bond posted on public and some private jobs that backs payment to subs and suppliers; on public jobs the bond claim replaces the lien.
How to get the bond before the invoice is overdue
FAR 52.228-12, dated December 2022, directs a prime to supply its payment-bond copy promptly to a prospective subcontractor or supplier requesting it on a contract containing that clause. Put the request under the federal contract number and reconcile the returned bond's principal and surety with the proposed purchase order. A capacity letter cannot supply those contract-specific identifiers.
40 U.S.C. 3133(a) permits an applicant to obtain a certified bond and contract copy from the contracting agency using an affidavit of furnishing and nonpayment, or an affidavit that the applicant is being sued on the bond. Use the prime's copy for pre-job credit setup and the agency's certified copy when the statutory evidentiary route is needed.
What belongs in a federal bond notice?
For a supplier hired by the electrical subcontractor rather than the bonded prime, 40 U.S.C. 3133(b)(2) makes the prime the recipient of the required notice. The deadline is 90 days after the claimant's last furnishing for the claim. State the amount with substantial accuracy and identify the party supplied; retain written third-party delivery verification or evidence of service by the statute's alternative summons method.
Build the amount from the ledger: 28,000 dollars of unpaid furnishing minus a 2,000-dollar credit leaves a 26,000-dollar balance. Attach the invoice and credit references so the amount is reproducible. Preserve the delivery record with the notice, separate from the email that first asked the project manager about payment. The mechanics-lien and notice guide covers the broader collection workflow.
Three federal clocks belong on the collection calendar
40 U.S.C. 3133(b)(1), (2) and (4) create three different timing questions: when nonpayment permits suit, whether a second-tier claimant served notice, and whether suit was filed before the outside limit. The 90-day waiting period is not permission to postpone a notice that is due within 90 days.
Keep last furnishing, notice delivery and lawsuit filing in separate date fields. Negotiating with the prime or exchanging documents with the surety does not itself satisfy the statutory filing requirement. A first-tier subcontractor and its supplier therefore need different notice checklists even when their last delivery occurred on the same day.
| Event under 40 U.S.C. 3133 | Federal timing |
|---|---|
| Unpaid claimant becomes eligible to sue | Not paid in full within 90 days after last furnishing for the claim |
| Claimant contracting with a subcontractor, without a contract with the prime, notifies prime | Within 90 days after last furnishing for the claim |
| Claimant files the civil action | No later than one year after its last labor or material furnishing |
Can the subcontract waive Miller Act suit rights?
Under 40 U.S.C. 3133(c), a waiver of the federal payment-bond civil-action right must be written, signed by the affected claimant and executed after that claimant has furnished labor or material. An advance waiver buried in the subcontract does not satisfy that timing condition.
Read a later payment release against the account it settles. Identify its covered period and payment amount before reconciling the remaining receivable. The bond file and the surety underwriting file serve different purposes: one establishes security for a specific contract, while the other supports the contractor's ability to obtain bonds.
Distinctions
- Bond claim versus lawsuit
- Sending a demand to the surety starts a claim review. It does not itself commence the civil action that preserves a court remedy.
Frequently asked questions
Does emailing the surety replace notice to the prime contractor?
The federal second-tier notice described above is directed to the bonded prime. Keep that recipient and delivery proof distinct from the surety's claim correspondence.
Sources checked
Also defined as
- Guarantees you pay subs and suppliers, the protection they have on public work in place of a lien