Flood test
A flood test loads a waterproofing assembly with a measured head of water and documents any leakage during the hold. ASTM D5957-98(2021) puts the added load at about 5.19 psf per inch of depth. Specify the test bay, shallowest and deepest water levels, hold time and acceptance criteria. The waiting period for membrane cure ends before the test clock starts; it does not count toward the hold.
Filling an area to confirm whether the assembly holds water, pass or fail, not where
Which flood-test specification applies?
ASTM D5957-98(2021) covers flood testing of plaza-deck and parking-garage waterproofing on slopes no greater than 2 percent, and explicitly excludes building roofing systems. Its scope also excludes continuously submerged installations such as pools. Calling every roof or pool test an ASTM D5957 test extends the designation beyond its published scope. ASTM scope
A roofing test specification needs its own depth, duration and acceptance criteria. Use the roof leak diagnosis guide to frame that investigation and the traffic-deck guide for deck coatings; the shared use of standing water does not make the two assemblies interchangeable.
Water depth changes across a sloped deck
ASTM D5957-98(2021) describes a basic test head up to 4 inches. Sections 5.2 and 5.5 call for a licensed structural engineer to review capacity and deflection before loading, including lateral pressure on containment and existing equipment loads. Critical locations need monitoring during the test. Record the deepest water level as well as the average. ASTM load guidance
A 16 by 20 ft rectangular bay with a uniform fall of 2 inches along its 16 ft length holds 1 inch at the high edge and 3 inches at the low edge. Mean depth is 2 inches: 320 sq ft multiplied by 10.38 psf gives about 3,322 lb of water. The low edge carries 15.57 psf. Irregular falls and depressions need separate depth measurements; averaging the highest and lowest readings only works for this uniformly sloping bay.
Is a shower flood test 15 minutes or 24 hours?
Section 312.10 of the 2025 Plumbing Code of New York State specifies potable water, a watertight drain plug, at least 2 inches of depth measured at the threshold and a hold of at least 15 minutes with no evidence of leakage. A lower or absent threshold requires temporary containment to retain that depth. This New York requirement identifies the measurement location; filling to an arbitrary curb mark does not establish the required depth. ICC's published chapter
Schluter recommends at least 24 hours of KERDI curing at room temperature before filling and describes another 24 hours as a typical test hold. Cooler conditions extend the cure period. For installation completed Monday at 2 p.m., that schedule puts filling no earlier than Tuesday at 2 p.m. and completion Wednesday at 2 p.m. Record those separate timestamps with the shower-pan installation. Schluter instructions
For waterproofing within its scope, ASTM D5957-98(2021), Section 5.4, sets a pretest minimum of 24 hours after installation, increased to 48 hours when installation temperatures were below 50 F. Full cure and the manufacturer's specified waiting period also govern readiness.
What counts as a valid flood-test result?
LATICRETE TDS 169, revised July 30, 2026, specifies a 24 to 72 hour hold for horizontal applications, starting at full test depth, with continuous monitoring and inspections below at 1 to 2 hour intervals. Its successful result requires both absence of leaks and intact membrane and flashings. Visible leakage calls for immediate draining, repair and a new test. LATICRETE procedure
The same TDS uses a vertical-sided control pan at similar depth and exposure to distinguish environmental loss. A test area losing 1/8 inch while its control loses 1/16 inch has 1/16 inch of excess loss to resolve. Preserve initial and final measurements and observations below; a matched water-level loss alone does not document every acceptance criterion.
Schluter's plug check fills only the pipe and drain to about the bonding-flange elevation first. Establish that this small volume holds before filling the base, so a plug leak does not erase the main test's water-loss evidence.
Distinctions
- Plumbing rough-in water test
- The drainage-pipe test under Section 312.2 of the 2025 New York State plumbing code checks the piping system. A shower-liner test under Section 312.10 checks the completed waterproofed receptor and its drain connection. The inspection record needs to identify which assembly was tested.
Frequently asked questions
Can I top up the water during a flood test?
LATICRETE TDS 169 states that adding water after the test begins invalidates its results. Record the interruption and establish a new test period; topping up to the original mark erases the water-loss evidence.
Can I flood-test when frost is forecast?
ASTM D5957-98(2021) advises against testing when freezing is expected because ice can pull flashings from their substrate or damage inside corners. Schedule the test within a nonfreezing window.
Sources checked
- ASTM D5957-98(2021): current public scope and significance, water loading and test conditions
- ICC: 2025 Plumbing Code of New York State, Sections 312.2 and 312.10
- Schluter: shower-system water testing, KERDI cure time and drain-plug check
- LATICRETE TDS 169, July 30, 2026: Flood Testing Procedures, control pan and test interruptions
Also defined as
- Plumbing: Plugging and filling the pan to prove the waterproofing holds before tile goes down