Treat mobilization as two separate schedules: the resources needed to start and move the operation, and the contract milestones that release payment for that work. Build the cost from transport, setup and project-specific prestart expenses. A lump-sum bid does not reimburse each equipment trip automatically, and cumulative payment percentages are not additional installments of the same size.
A planned trip and setup to perform the work. Include travel, loading, closure setup, and the actual crew time required.
Build the estimate from moves and setup
MDOT’s 2020 Standard Specifications section 110 includes moving personnel and equipment, establishing site facilities and necessary project-specific costs incurred before pay-item work begins. Estimate those activities from the actual staging plan before selecting the bid amount.
- Count initial and planned return equipment moves, including loading and unloading time.
- Assign setup labor, temporary facilities, permits and project-specific prestart charges to one estimating account.
- Allocate recurring crew travel and site operating costs consistently so they are not also counted in production rates.
- Place removal and closeout costs in the item identified by the contract.
Separate the cost forecast from the payment forecast
MDOT’s 2020 Standard Specifications section 110 pays mobilization cumulatively at 50%, 75% and 100% of the bid amount when earned contract value reaches 5%, 10% and 25%, respectively. Those are payment milestones under that specification, not recommended percentages for estimating mobilization cost.
For a selected $20,000 mobilization item, the scheduled cumulative payments are $10,000, $15,000 and $20,000. With no prior adjustments, the successive releases are therefore $10,000, $5,000 and $5,000. Budgeting each cumulative percentage as a new payment would overstate cash receipts.
Use the contract denominator specified for the milestone
For MDOT section 110’s milestone calculation, exclude mobilization payments from the amount of work earned; keep the original contract amount as the denominator. On a $1,000,000 original contract including a $20,000 mobilization item, the 5% threshold is $50,000 of other earned work, not $49,000 from reducing the denominator by mobilization.
MDOT’s construction manual applies that calculation to the whole contract, rather than a subset of sites within it. Keep site production tied to the contract payment ledger. Reconcile the scheduled releases with the general-conditions estimate before forecasting funds available for the next phase.
A return trip can be a real cost without a new pay item
MDOT section 110 caps total mobilization payments at the bid amount even when equipment leaves and returns, work shuts down or additional work quantities are added. That clause makes the original staging assumptions financially important.
Map the moves caused by traffic stages, separated work areas and owner access windows before bidding. When a changed requirement creates another move, preserve the instruction and hauling record for the contract’s change process. A second lowboy ticket establishes an expense; the payment clause determines whether that expense changes the recoverable amount.
Distinctions
- Demobilization
- Removal and closeout can occur at a different time from initial setup. Whether their cost belongs in mobilization depends on the contract description.
- Daily travel
- Recurring travel between the yard and an operating project needs a consistent estimating home. Counting it in both crew production rates and mobilization duplicates the same expense.
Frequently asked questions
Is the lowest mobilization line the lowest project price?
No. Bidders can distribute cost among allowed pay items differently. Compare the complete scope, total bid and payment conditions, then examine whether staging assumptions cover the planned work.
Sources checked
Also defined as
- Electrical: The one-time fixed cost of bringing crews, the trailer, and equipment onto the site; demobilization is the cost of removing them
- HVAC: Bringing the crew, equipment, and temporary facilities onto the site to start work; demobilization is removing them at the end