Oversubscription
A leaf with 24 server ports at 25 Gb/s and four 100 Gb/s uplinks has 1.5:1 oversubscription: 600 Gb/s of server capacity shares 400 Gb/s upstream. Remove one uplink and the ratio becomes 2:1 without adding a server. A power-planning ratio needs the same state label: provisioning 1,250 kW against a 1,000 kW post-reserve budget is 1.25:1. These are capacity commitments; measured traffic and power draw belong in separate utilization records.
Ratio of aggregate server-facing bandwidth to aggregate uplink bandwidth; equal capacity does not exclude congestion
Calculate the ratio after an uplink fails
Cisco Live 2026 session BRKDCN-2967 bases the ratio on port counts multiplied by port speeds. Build the field worksheet from uplinks that are actually forwarding, recording their operational speed and the failure state being tested beside the spine-leaf topology. A reserved or disconnected cage contributes zero to the worksheet.
Using Cisco's formula, Anvilfield's 24-port example divides 24 × 25 Gb/s by 4 × 100 Gb/s in normal operation, then by 3 × 100 Gb/s with one uplink unavailable: 1.5:1 and 2:1 respectively. At 300 Gb/s offered to those uplinks on the same port-rate basis, the lost link consumes all 100 Gb/s of aggregate spare capacity.
| State | Uplink capacity | Oversubscription | Uplink load at 300 Gb/s offered traffic |
|---|---|---|---|
| Four uplinks available | 400 Gb/s | 1.5:1 | 75% aggregate |
| One uplink unavailable | 300 Gb/s | 2:1 | 100% aggregate |
A 25% capacity loss raises loading by one-third
Cisco Live 2026 session BRKDCN-2967 assigns a 25% capacity impact to losing one of four equally provisioned spines and a 12.5% impact to losing one of eight. Those percentages describe capacity removed. With demand unchanged, the four-spine case multiplies utilization by 1/0.75, or about 1.33. In the worked leaf, 75% aggregate loading consequently becomes 100%.
The topology also determines where that displaced traffic goes. RFC 7938, section 3.2.4 describes two parallel uplinks to one spine: losing one can shift its traffic onto the other and create heavy congestion when path selection ignores the reduced bandwidth. An aggregate ratio can miss this unequal loading. Check each surviving path, rather than assuming that all available bandwidth forms one perfectly shared pool.
Translate power oversubscription percentages correctly
Google's ASPLOS 2020 power-oversubscription paper reports production oversubscription of 25% or higher using a medium-voltage sharing plane and priority-aware power capping. The reported increase came from combining a larger sharing domain with controls that throttle workloads by priority.
The percentage convention matters: 25% above a 1,000 kW budget means 1,250 kW provisioned, or 1.25:1. It does not mean that 25% of the provisioned load is unsupported: 250/1,250 is 20%. State the denominator beside every percentage so a planning sheet and a control policy describe the same commitment.
Carry both normal and failed-state budgets into the power-capping policy. In the same worked case, an 800 kW post-failure budget changes the 1,250 kW commitment to 1.5625:1. The inventory has not grown; the denominator has shrunk. This calculation uses the remaining power budget, rather than treating a redundant server power supply as additional IT demand.
Distinctions
- Utilization
- Utilization divides measured traffic or load by available capacity over a stated interval. Oversubscription compares provisioned capacities. Changing the workload changes utilization without changing the port inventory.
- Headroom
- At 300 Gb/s offered traffic, this leaf retains 100 Gb/s of aggregate headroom with four uplinks and zero with three. An oversubscription ratio needs a demand figure alongside it to show that margin.
Frequently asked questions
Does 2:1 oversubscription cut every server's speed in half?
No. It expresses aggregate capacity. An individual transfer still depends on its receiver, selected path and competing traffic. The ratio does not allocate an equal share to each server.
Should I add transmit and receive bandwidth together?
One-direction accounting gives 600/400 = 1.5; counting both directions gives 1,200/800 = 1.5. A false 3:1 comes from crossing those accounting bases: 1,200/400. Mark the worksheet 'per direction' or 'bidirectional' so both sides use comparable Gb/s totals.
Sources checked
- Cisco Live 2026 BRKDCN-2967, Simple Leaf Spine with a Touch of ToR: ratio formula and spine-failure capacity
- RFC 7938, August 2016, sections 3.2.2 to 3.2.4: Clos capacity and failure redistribution
- Google Research, ASPLOS 2020: Data Center Power Oversubscription with a Medium Voltage Power Plane and Priority-Aware Capping
Also defined as
- Provisioning more nameplate IT than the installed power could serve if everything ran at worst case at once