Field glossary · method
Peak shaving
Peak shaving lowers the highest demand seen at a specified meter or supply point by reducing load, moving it to another time, or supplying it from storage or generation. For a battery, kW determines the reduction and usable kWh determines its duration. Cutting 1 MW for 15 minutes requires 250 kWh delivered at the AC boundary. The tariff's measurement interval and any demand ratchet determine whether that reduction changes billed demand.
Trimming the grid draw during the highest-demand hours by supplying part of the load from on-site generation or batteries
Match the battery dispatch to the billing interval
DOE FEMP's utility-rate guidance distinguishes facility demand charges from charges based on the facility's contribution to the utility system peak. Identify which charge the dispatch targets before selecting its schedule. The local facility maximum and the utility's system maximum can occur at different times.
FEMP describes interval data commonly supplied hourly or in 15-minute increments. For a 15-minute demand interval, supplying 1 MW from a battery for five minutes and supplying nothing for the remaining ten reduces the interval average by only one-third of a megawatt. A full 1 MW reduction across that interval requires 250 kWh at the AC delivery boundary.
Size the depth and the duration separately
To hold a 3 MW site at 2 MW for 30 minutes requires 1 MW of discharge power and 500 kWh delivered to the site. Holding that same reduction for two hours needs 2 MWh. The inverter rating answers the first question; the usable discharge-energy rating answers the second.
The System Advisor Model battery-dispatch documentation constrains operation by minimum and maximum state of charge and available battery capacity. It distinguishes available capacity, which changes with degradation, from nominal capacity. Use the energy available above the operating reserve at the expected battery condition when calculating the duration.
Prove the reduction through charging and recovery
The U.S. Energy Information Administration identifies peak shaving and electricity-price arbitrage as separate storage uses. Moving energy into a cheaper period and reducing the highest demand interval produce different billing results even when the same battery performs both functions.
Overlay site demand, battery AC charge power and battery AC discharge power on one timestamped series. A charging rebound that establishes a higher demand maximum can erase the intended reduction. Compare the entire billing window. Preserve this meter-level result with the dispatch record in the grid-flexibility guide.
Why a lower monthly peak can leave billed demand unchanged
DOE FEMP identifies demand ratchets that carry a percentage of previous months' peaks into the billing calculation. Under a tariff billing the greater of the current maximum or 80 percent of a previous 3.5 MW peak, the historical floor is 2.8 MW. Shaving this month's measured maximum to 2 MW leaves billed demand at 2.8 MW while that historical peak remains in the look-back window.
Distinctions
- Peak smoothing
- Smoothing short load swings reduces the ramp or instantaneous peak seen by equipment. Billing demand is the average over the tariff measurement interval.
Frequently asked questions
Does doubling battery energy double the peak reduction?
It doubles discharge duration at the same power if the added energy is usable. Increasing the reduction in kW also requires sufficient inverter power and an interconnection that permits that dispatch.
Sources checked
Also defined as
- Using stored energy to serve the top of a peak so the source and the breaker see a flatter draw