Demand charge
A demand charge applies the tariff's demand rate to a billed capacity quantity, such as the month's highest 15-minute average kW or a historical minimum. The highest instantaneous logger reading is not necessarily that quantity. Identify the averaging interval, eligible hours and ratchet before calculating a reduction: a 1,100 kW measured peak still bills at 1,600 kW when that historical floor governs.
A bill component based on the highest demand in the period, not on total energy used
Rebuild the average over the billing interval
Alberta's Utilities Consumer Advocate describes demand meters that retain the maximum average power over a 15- or 30-minute interval. Use the interval in the applicable service terms. A short event contributes energy within that interval; the maximum instantaneous reading does not automatically become the interval average.
A 15-minute interval containing five minutes at 600 kW and ten minutes at 200 kW averages 333.3 kW: (600 x 5 + 200 x 10) / 15. Its energy is 83.33 kWh. A logger showing only the 600 kW maximum cannot reconstruct that billing quantity without the duration and the rest of the interval.
A historical ratchet can set the billed floor
Pacific Northwest National Laboratory's FEDS guidance describes a typical demand ratchet using 80% of the highest peak in the previous eleven months as a comparison floor. The applicable tariff establishes the actual percentage and lookback. A lower measured peak can leave billed demand unchanged while that historical floor remains binding.
With a 2,000 kW historical peak and an 80% ratchet, the floor is 1,600 kW. Reducing the current monthly peak from 1,400 to 1,100 kW still leaves 1,600 kW as the determinant under that comparison. Track the historical peak and when it leaves the lookback window alongside the current interval data.
Separate time-of-use demand from other demand components
DOE's utility-rate guidance distinguishes time-of-use demand charges based on maximum demand during specified hours from non-coincident demand charges and other tariff components. A load shift out of one window can reduce one charge while leaving another unchanged. List each billed determinant with its measurement window before calculating the result of a storage or scheduling change.
Size the energy needed to sustain the demand cut
A 50 kW reduction lasting the full 15-minute billing interval delivers 12.5 kWh at the billing meter. That energy must cover the actual interval setting the peak; a new peak in the next interval can become the bill's determinant. Compare the grid-flexibility dispatch with the timestamps in the metering record, and test each tariff demand component separately.
Distinctions
- Energy charge
- Bills kWh or another energy quantity accumulated over time. Demand billing uses a specified rate of consumption or capacity determinant.
- Contracted capacity
- A reservation or minimum obligation defined by the agreement. It can constrain the bill even when the measured monthly peak falls.
Frequently asked questions
Can a five-minute power spike affect a demand charge?
It contributes to the average in the applicable demand interval. Its billed effect depends on its duration, surrounding load and the tariff determinant.
Will reducing kWh always lower demand charges?
A reduction outside the governing demand interval or window can lower energy use while leaving the billed peak or ratchet unchanged.
Sources checked
- Alberta Utilities Consumer Advocate: Understanding small business demand meters, 15- and 30-minute averaging
- Pacific Northwest National Laboratory FEDS: demand-ratchet definition and typical 80% eleven-month comparison
- DOE FEMP: Evaluating Your Utility Rate Options, distinct demand-charge components
Also defined as
- Electrical: A utility charge based on peak kW draw in a billing period, separate from the kWh energy charge
- A utility charge tied to the site's peak power draw, separate from the energy used