Make-ready
Make-ready is work that removes a defined obstacle to the next installation or task. In an EV estimate, the scope must say whether a parking space receives only capacity and a pathway, a completed circuit, or an operating charging port. In crew planning, the deliverable is a task with its constraints cleared. The shared term is useful only when the handoff identifies what is complete and what remains to be bought or built.
The service, conduit, and pads built ahead of and beyond the first chargers so expansion is a connection
Specify EV-capable, EV-ready, and installed separately
DOE's Alternative Fuels Data Center describes its EV-capable and EV-ready examples using 208/240 V, 40 A circuits. Its EV-ready description includes wiring, a receptacle, and overcurrent protection. Those are the AFDC definitions used in the comparison below; the bid schedule must identify the adopted local definition where its completion level differs.
Apply the labels space by space. A 16-space plan can contain six installed ports and ten future pathways, so buying 16 chargers from the parking count would misstate the scope. Put the category and remaining work beside each space number in the charging-site scope.
| AFDC completion category | What the estimator counts | Still outside that category |
|---|---|---|
| EV-capable | Panel capacity and conduit for future circuits | Circuit wiring, receptacle, protection, and EVSE installation |
| EV-ready | Completed circuit, including receptacle and protection | EVSE installation |
| EV-installed | Installed charging equipment | Any separately scheduled future ports |
Separate future pathways from usable electrical capacity
At 32 A and 240 V, six simultaneously operating AC ports represent 46.08 kVA; sixteen represent 122.88 kVA. At unity power factor those figures are also kW delivered to the vehicles before onboard charging losses. The additional ten ports require 76.8 kVA of unmanaged supply demand. Empty raceways preserve a route for that expansion, not the electrical capacity.
Document the future operating basis as well as the ducts: simultaneous demand, the chosen managed limit, and the source equipment reserved for it. The EVSE installation guide covers commissioning the active equipment. The make-ready record needs the other endpoint too: where each future raceway terminates, what remains uninstalled, and which capacity assumption the future connection will use.
Use a measurable deliverable in the look-ahead
The Lean Construction Institute defines make-ready as removing constraints so an assignment can be performed as planned. LCI's glossary describes look-ahead windows typically spanning 3 to 12 weeks, with six weeks preferred on most projects. A planning horizon provides time to clear a constraint; it does not itself clear one.
In a six-week look-ahead, 'utility drawing accepted' and 'trench available' are separate constraints with separate owners and due dates. LCI's constraints-log definition requires a responsible individual and an agreed resolution date for each item. Link those closures to the Last Planner process before releasing the crew assignment; acceptance of the future raceways closes a construction deliverable, not every constraint on later charger installation.
Distinctions
- Pole make-ready
- Outside-plant crews use the term for work needed before an authorized pole attachment. That scope follows the pole owner and attachment design.
- EV-ready circuit
- A completed electrical circuit is a narrower, verifiable deliverable than a general promise of future expansion.
An estimator following public parking electrification can use PorchRocket Bid Control to find electrical bids and the earlier budget or board-meeting signals behind those make-ready packages.
Frequently asked questions
Does make-ready always include conductors?
No. An EV-capable scope can provide panel capacity and raceways while leaving circuit wiring for later. State the selected completion level in the schedule of work.
Can an empty conduit be counted as an installed charging port?
No. DOE defines the installed category by the presence of EV charging equipment. A future route supports a later port but is not an operating one.
Sources checked
Also defined as
- Datacenter: Clearing the constraints on a task, prior trade, material, information, access, and permit, before it is scheduled
- Conduit, panel, and capacity installed for future chargers; EV-capable, EV-ready, or EV-installed