PPC
Seven assignments delivered as promised from a frozen list of ten commitments produce 70 percent PPC, or Percent Plan Complete. Each assignment earns one point only when finished by its promised handoff; labor hours and contract value do not weight the score. Record unplanned work separately. Retain the completed and committed counts when combining weeks so a small week's percentage does not outweigh a larger week's commitments.
Percent Plan Complete, the count of tasks finished as promised divided by tasks promised for the week
Score the promised day as well as the promised finish
Lean Construction Institute's 2023 Last Planner Standard Work defines a completed assignment as 100 percent complete on the day stated. A task promised for Wednesday and finished Friday therefore misses that promise even though it finishes within the reporting week. Preserve the promised date when the weekly record is updated.
Ten assignments promised, seven finished on their stated days, two finished late and one unfinished produce 70 percent PPC. An additional unplanned assignment does not raise the numerator to eight. Log that extra output separately so the team can see both production accomplished and reliability of the original commitments.
Combine weeks using the original counts
Combine the underlying assignment counts when reporting several weeks. This comparison shows how an unweighted average of the displayed percentages overstates the combined result:
Keep the completed and committed counts next to each plotted percentage. The denominator also exposes a team that improves its apparent score by promising very little. Pair PPC with the planned quantities and milestone obligations in the look-ahead plan so a reliable promise set still advances the project.
The arithmetic mean of 80 and 75 percent is 77.5 percent. It answers a different question because it weights the five-assignment week equally with the twenty-assignment week.
| Period | Completed as promised | Committed | PPC |
|---|---|---|---|
| Week 1 | 4 | 5 | 80 percent |
| Week 2 | 15 | 20 | 75 percent |
| Combined | 19 | 25 | 76 percent |
Use the benchmark to improve the planning system
Lean Construction Institute gives 75 to 90 percent as the high-performing team average in its 2023 PPC standard work. That published range is more specific than treating 80 percent as a universal pass mark. Review the recurring reasons for misses and whether the team is making the required work ready.
LCI's design-phase Last Planner guidance places constraint identification and mitigation alongside weekly work planning. Assign each missed commitment a specific reason and a person responsible for removing the recurring constraint. Do not change last week's promised scope merely because the reason is understandable; the missed promise is the information the next planning cycle needs.
Distinctions
- Physical percent complete
- A quantity or value measure weights the amount of work. PPC weights each promised assignment equally.
- Pay-per-click
- Marketing PPC describes purchased advertising clicks. It is unrelated to the Last Planner commitment metric.
Frequently asked questions
Does a 90-percent-finished task earn partial PPC credit?
No. Under LCI scoring, an assignment earns credit only when it is completely finished as promised. Break a large assignment into meaningful, agreed handoffs before commitment if separate completions need separate credit.
Sources checked
Also defined as
- Concrete: Percent plan complete: committed activities finished as planned divided by committed, times 100
- Percent plan complete: committed activities finished divided by total committed