Look-ahead
A look-ahead is the make-ready layer between a phase schedule and crew commitments. It gives upcoming tasks time to lose their constraints, then records which tasks reach the weekly plan. A useful sheet retains the original target week, readiness evidence and later disposition of each task, allowing the foreman to distinguish work prepared in advance from work added at the last moment.
The three to six week window pulled from the CPM that the field builds from, with constraints cleared and crews assigned
Choose a horizon that exposes the slow constraint
Ballard and Tommelein's 2020 Last Planner System benchmark, published in 2021, describes typical look-ahead periods of 3 to 12 weeks, depending on the lead time needed to remove constraints. The horizon is therefore a response to the work's preparation time rather than a fixed industry number.
Separate the planning window from the commitment window. A task listed farther out still needs enough definition to identify a missing approval, material or access arrangement. Conversely, adding detailed crew assignments to distant work does not remove the uncertainty about whether that work will be ready.
Give each task a stable identifier, target week, blocking condition, release owner, release date and evidence of readiness. A formwork package awaiting an approved opening layout stays blocked until that drawing is issued; changing its color on the plan does not close the constraint. Retain the old target week when it moves.
Use two denominators to expose different failures
Ballard and Tommelein define Tasks Anticipated as the tasks common to an earlier plan and the current target-week plan divided by the tasks in the current plan. It answers how much of this week's intended work was seen in advance.
In Ballard and Tommelein's benchmark, Tasks Made Ready divides the tasks shared by earlier and later plans for a target week by the tasks in the earlier plan. It shows how much of the earlier intended work survived into the later plan. Keep task identity stable: splitting one old task into several new task IDs can change the percentages without changing readiness.
| Target-week task comparison | Tasks Anticipated | Tasks Made Ready |
|---|---|---|
| Earlier plan: 12 tasks; final plan: 10; shared: 8 | 8 / 10 = 80% | 8 / 12 = 66.7% |
| Question answered | How much final work was seen in advance? | How much earlier planned work reached the later plan? |
Preserve dropped tasks and late arrivals
Archive each weekly version and record why tasks were added, deferred or replaced. A constraint log can appear clean simply because blocked tasks were deleted from the schedule. Retaining the earlier plan makes that failure visible instead of rewarding a tidier page.
The Lean Construction Institute defines the look-ahead as a plan updated weekly to expose upcoming activities and prepare them for their intended week. Keep archived task sets with the CPM and look-ahead schedule so an analyst can reconstruct the preparation history of a missed commitment.
Distinctions
- Weekly work plan
- The commitments selected for execution. It supplies the later task set in a make-ready comparison.
- Percent plan complete
- Measures whether promised work was finished. A team can complete its weekly promises while repeatedly replacing the work it originally expected to do.
Field example
In that 12-task earlier plan, four tasks disappear before the weekly commitment and two new tasks enter. Record each dropped task's blocker and each added task's origin. The 80% anticipation result and 66.7% make-ready result locate different planning losses even if the crew later achieves 100% PPC on its ten commitments.
Frequently asked questions
Does high PPC prove the look-ahead is working?
PPC tests delivery against the chosen commitments. Anticipation and make-ready measures test how those commitments developed. Keep both views so easy replacement work does not conceal persistent preparation failures.
Sources checked
Also defined as
- Electrical: A short rolling schedule, often two to three weeks, listing upcoming work and what must be made ready before each task can begin
- Datacenter: Rolling 3 to 6 week short-interval schedule pulled from the master into the field