Labor budget
A labor budget converts quantity and allowed effort into an hour limit: 800 supports at 0.75 labor-hour each authorize 600 hours. If 320 supports consume 300 hours, the same pace forecasts 750 hours for the package. Keep the 600-hour baseline and 750-hour forecast separate so a spending balance does not hide the 150-hour overrun.
The hours and production rate the estimate assigned to the work, against which the crew's actual units per labor hour are measured
Why 300 unspent hours do not mean 300 hours to finish
NASA's EVM tutorial permits accomplishment to be measured in labor-hours when that is the planning basis. For this installation package, earned hours credit each accepted support at its original 0.75-hour allowance, regardless of the time actually consumed.
The project estimate assigns 0.75 labor-hour to each of 800 cable-tray supports, giving a 600-hour installation budget. At the reporting date, 320 accepted supports have consumed 300 hours. The completed work earns 320 x 0.75 = 240 hours, and the earned-to-actual ratio is 0.80.
NSF's EVM Gold Card calculates budgeted work remaining as budget at completion minus cumulative earned value. Here that is 600 - 240 = 360 hours. Subtracting the 300 actual hours from the 600-hour budget leaves 300 unspent hours, a different balance.
The 480 remaining supports need 450 hours at the observed 320 / 300 supports per labor-hour. NSF's actual-plus-estimate-to-complete structure therefore gives 300 + 450 = 750 forecast hours. The original budget is short by 150 hours even though half of it is still unspent.
Calculate the output needed to recover the budget
Finishing 480 supports inside the 300 unspent hours requires 1.60 supports per labor-hour. The observed rate is 320 / 300 = 1.07, rounded. Recovery therefore requires a 50% improvement over the unrounded observed output. A promise to 'get back on budget' needs a changed work arrangement capable of producing that gain.
Remaining work earns 360 baseline hours. Finishing it in 300 actual hours requires an earned-to-actual ratio of 1.20, compared with the measured 0.80. Name the change capable of that improvement, such as prefabricated brackets or removal of a recorded access delay, and measure its output separately.
Give testing, identification and closeout their own remaining allowances when they use different production measures. The accepted-quantity record in labor productivity tracking feeds this forecast; an untested installation must not silently consume a testing allowance intended for later work.
Keep scope, timecards and schedule variance aligned
Use the same cutoff for accepted quantities and posted time. Friday's installed count compared with Wednesday's timecards creates artificial efficiency. Rework consumes hours without earning the same installed quantity a second time. Approved additional scope needs a dated budget revision that preserves the original allowance and explains the change.
NASA defines earned-value schedule variance as earned value minus planned value. In a labor-hour report, the result is budgeted effort ahead of or behind plan. Turning that balance into days also needs the remaining sequence, available crews and dependencies in the foreman's work plan.
Separate hour efficiency from wage cost. Thirty-two straight-time labor-hours and thirty-two overtime labor-hours represent the same time input in a quantity report. Their payroll costs differ, so carry the applicable burdened rates into the cost forecast rather than changing the installed quantity.
Distinctions
- Staffing plan
- Assigns people and shifts to the work. More workers increase available hours but do not, by themselves, improve output per labor-hour.
- Labor forecast
- The current expectation of total hours. Retain it beside the authorized budget so expected performance and approved scope remain distinguishable.
Frequently asked questions
Can a job have hours left in its budget and still be overrunning?
Yes. The support-installation package has 300 unspent hours but needs another 450 at its measured output. The forecast identifies the overrun before the original allowance is exhausted.
Is a crew-hour the same as a labor-hour?
Count every worker's time. Four people working eight hours charge 32 labor-hours. Calling that shift eight hours without naming the four-person crew understates the time input by a factor of four.