Interconnection queue

An interconnection queue tracks requests through a utility or grid operator’s connection process, but queue position has meaning only within that process. Generation interconnection and large-load service requests have different study rules and milestones. For a data center, the decisive evidence is the utility’s documented service arrangement, staged capacity, required infrastructure, and assigned energization schedule.

The ordered line of projects waiting for the utility or grid operator to study and approve a connection to the grid

Used across 2 Anvilfield field guides, most in Datacenter.
Updated

Which queue is actually studying the project?

FERC Order 2023-A explains a first-ready, first-served cluster-study framework for generator interconnection. It is not a national data-center load-service schedule. A campus with on-site generation and a large utility load can have distinct requests whose milestones must be tracked separately.

Dominion Energy's May 2026 large-load report describes a data-center queue with 25 GW assigned energization dates through 2031 and another 45 GW without offered connection dates. Those are Dominion's reported positions at that date, not a forecast for every service territory. They show why a request being in a queue does not establish that it has a delivery date.

A study deadline is not an energization promise

FERC's Order 2023-A describes a 150-day cluster-study period following a 60-day customer-engagement window, with another 150 days for a necessary restudy. These are generator-study process intervals. Equipment procurement, permits, network construction, and service agreements remain separate work after a study result.

Link the utility and substation delivery scope to a milestone ledger that distinguishes application completeness, study completion, agreement execution, infrastructure approval, construction, and energization. Attach the issuing utility's current document to each date instead of treating an early schedule as a permanent commitment.

Submit a load ramp that matches the construction phases

Dominion's data-center request process calls for load information including a ramp schedule and site load broken down by building where applicable. Its service guidance also describes energization in stages matching expected usage. The utility needs to understand when capacity is needed, not just the final campus total.

For a 60 MW campus opening in three 20 MW phases, track both requested and confirmed service for each block. A confirmed first 20 MW leaves 40 MW awaiting later delivery. Tie each building's occupancy milestone to its own utility capacity and energization conditions.

Campus phaseIncremental demandCumulative service required
Building 120 MW20 MW
Building 220 MW40 MW
Building 320 MW60 MW

Distinctions

Queue number versus capacity reservation
A queue identifier tracks a request. The applicable agreements and utility milestones establish what capacity and schedule have actually been committed.

Frequently asked questions

Do generation-queue totals measure waiting data centers?

No. Generation and storage requests describe proposed supply connections. Data-center demand must be established from the relevant utility or operator’s load-service records.

Sources checked

Also defined as

  • The line of projects waiting on the utility study and agreement to connect, now years long in busy markets

Where this shows up

Next step: Monitor power-asset changes

Back to the full field glossary