Field glossary · method

Free cooling

Free cooling substitutes an outdoor heat sink for some or all mechanical refrigeration. Determine the usable weather limit from the required supply condition and the heat-transfer approaches. A plant needing 60°F water with a 7°F tower approach and 3°F exchanger approach needs about 50°F outdoor wet bulb for full waterside economizing. Fans, pumps, and tower water treatment remain part of the operating cost and service scope.

Rejecting heat using cool outside air or a low wet-bulb instead of running mechanical chillers, which lowers power and water

Used across 2 Anvilfield field guides, most in Datacenter.
Updated

Calculate the outdoor condition that can make your water

For a plant requiring 60°F supply water, allow 7°F for tower approach and 3°F for heat-exchanger approach at the operating load. Full economizer cooling then needs approximately 50°F wet bulb or lower: 60 - 7 - 3 = 50°F. A dry cooler uses outdoor dry-bulb temperature in the corresponding balance. Keep those weather variables separate.

Approaches change with load, flow, fouling, and fan operation. Use the equipment selection at the proposed condition, then compare measured inlet and outlet temperatures with that selection. Connect this temperature balance to the economizer changeover sequence: a favorable outdoor reading still has to overcome both heat-transfer approaches before the water reaches its target.

Choose wet bulb or dry bulb for the equipment being tested

DOE's July 2024 design guide treats airside and waterside economizers as different cooling arrangements. Log the weather variable that drives the installed heat exchanger, together with the temperatures on both sides. Comparing a tower's leaving water with outdoor dry bulb gives the wrong approach measurement.

ArrangementMeasurements that explain the limit
Cooling tower plus water-to-water exchangerOutdoor wet bulb, tower leaving water, and exchanger secondary supply.
Dry cooler serving a closed loopOutdoor dry bulb and fluid inlet/outlet temperatures.
Airside economizerOutdoor and return-air conditions, mixed-air temperature, and the permitted humidity or enthalpy limits.

Screen annual hours without promising annual savings

DOE's July 2024 data-center design guide identifies climates below 55°F wet bulb for at least 3,000 hours per year as particularly suited to waterside economizing. This is a screening criterion, not a command to enable every economizer at 55°F.

DOE also identifies chilled-water loops designed for 50°F supply or warmer as especially effective applications for waterside free cooling. A higher usable supply temperature widens the weather window. Calculate full and partial operating hours from the site's weather data and the actual water-temperature requirement.

Count the power that remains when the compressor stops

ENERGY STAR distinguishes integrated waterside economizers, which precool water before it reaches the chiller, from arrangements that replace chiller operation when conditions permit. That distinction matters when counting savings: partial compressor unloading contributes useful hours even when the economizer cannot carry the entire load.

Suppose compressor power falls by 80 kW while economizer pumping and fan power increase by 12 kW. Net savings are 68 kW; over 2,000 operating hours they total 136,000 kWh. Use those measured or selected equipment powers in the energy calculation. A compressor-off status by itself does not quantify the plant's net reduction, and a cooling tower still has a water balance to maintain.

Distinctions

Free cooling versus heat recovery
Economizing reduces the work of rejecting heat. Heat recovery delivers that heat to another use; the receiving load and temperature requirement determine its value.

Frequently asked questions

Is 55°F the correct free-cooling enable setpoint?

Only when the selected equipment and required supply temperature support it. DOE uses that wet-bulb value for climate screening; control settings come from the plant temperature balance and sequence.

Sources checked

Also defined as

  • Cooling a data center with cool outdoor air or water so the chiller compressor runs less or not at all

Where this shows up

Next step: Map economizer service accounts