Rigid / PCC pavement
Rigid or PCC pavement is a concrete slab system whose repair scope depends on measured support and joint behavior. PCC means portland cement concrete. A falling-weight deflectometer can compare the loaded and unloaded sides of a joint: 6 mils on the unloaded side divided by 10 mils on the loaded side gives 60 percent load-transfer efficiency. Retain both deflections, since a high ratio can also occur when both slabs move excessively.
A portland cement concrete slab that carries load by beam action, as opposed to flexible asphalt
Measure movement across the joint, not just the joint step
The 2022 Concrete Pavement Preservation Guide evaluates joint load transfer with a falling-weight deflectometer, which applies a measured load while sensors record slab movement. It calculates deflection load-transfer efficiency as unloaded-side deflection divided by loaded-side deflection, multiplied by 100. A joint with 6 mils unloaded and 10 mils loaded has 60 percent efficiency; a mil is 0.001 inch.
The CP Tech Center's 2022 guide recommends load-transfer testing below 70°F because warmer, tighter joints can change the result. It also recommends testing both sides and using the lower efficiency. Preserve pavement temperature and loading direction with the readings so two visits can be compared meaningfully. Identify the concrete pavement system and whether the tested joint has dowels before comparing its response with adjacent joints.
Separate lost load transfer from concrete deterioration
FHWA's Concrete Pavement Rehabilitation and Preservation Treatments guide identifies deflection load transfer of 70 percent or less as a condition where load-transfer restoration is effective when substantial structural life remains. Its screening guidance pairs average joint faulting of 0.10 to 0.15 inch with fewer than 10 percent cracked slabs. These are treatment-selection indicators from that guide, rather than new-pavement acceptance tolerances.
A sound slab with a poorly transferring joint presents a different repair than concrete breaking down through its depth. Map cracking, faulting and surface deterioration individually. Grinding changes the riding profile, while dowel-bar retrofit changes load transfer. A smooth surface after grinding does not establish that the supporting joint mechanism has been restored.
A high efficiency can still accompany excessive slab movement
Two sides moving 40 and 36 mils yield 90 percent load-transfer efficiency, yet both exceed the peak corner deflection of less than 25 mils recommended in the CP Tech Center's 2022 guide. The guide also recommends limiting the difference across a loaded joint to 5 mils or less. Here the difference is only 4 mils: the ratio and differential look favorable while absolute movement still flags a support problem.
Give each repair location a slab identifier and keep separate quantities for surface area, full-depth area, dowel locations and support correction. Mark which existing joints must continue through the repair. This lets an estimator price the measured failure mechanism without treating every distressed slab as the same repair.
Distinctions
- Flexible pavement
- A flexible pavement distributes load through an asphalt and granular layer system. A concrete overlay over asphalt still requires identifying which layer and interface provide the designed structural action.
Public concrete-pavement repair programs also appear in PorchRocket Bid Control, where board-meeting and capital-plan signals identify agency work ahead of the bid notice.
Frequently asked questions
Does PCC mean prestressed concrete pavement?
Here PCC identifies portland cement concrete pavement. Prestressing is a separate structural system and must be identified explicitly in the pavement design.