Field glossary · method
Maturity method
The maturity method produces a concrete strength estimate whose audit trail includes a temperature history, a mixture calibration, the calculation settings and the index units. ASTM C1074-19e1 is the active practice as of November 5, 2026. Continued hydration and supplementary evidence of the field concrete's strength potential are necessary conditions for using the result. Preserve the raw temperature readings so another technician can reproduce the index.
Estimating in-place strength from the time-temperature history at a sensor
Recalculate the time-temperature factor from the log
FHWA's November 2005 TechBrief FHWA-IF-06-004 calculates Nurse-Saul maturity from successive temperature-time intervals and assigns no strength-gain contribution to time at or below the datum temperature. Write the accumulation as M = sum[max(Tavg - T0, 0) x delta t]. Tavg is the interval's average concrete temperature, T0 is the calibrated datum, and delta t is its duration. Celsius readings and hourly durations produce degree-Celsius-hours.
Sum the contributions of successive intervals. Multiplying the latest temperature by the entire elapsed time assigns today's temperature to hours that actually ran colder or warmer. An export should retain the start time, interval lengths and datum setting alongside the temperatures. The maturity field guide covers building the mixture relationship and using it in the placement workflow.
A dashboard refresh does not establish the logging interval
NIST's 2001 paper The Maturity Method: From Theory to Application recommends logging at intervals no longer than 30 minutes during the first 48 hours when establishing the laboratory strength-maturity relationship. Audit the stored timestamps in both calibration and field records. An hourly dashboard update identifies upload frequency, not the temperature sampling interval.
A missing upload and a missing measurement leave different records. Locally stored readings can fill a communication gap after retrieval; an interval with no measured temperature cannot be reconstructed from the last displayed value. Identify gaps in the exported log before comparing an independently calculated index with the software result.
Carry the index units and the tested strength property together
ASTM C1074-19e1 specifies SI units for determining the maturity index but permits other strength units when establishing the strength-maturity relationship. Keep the index axis, the strength axis and the parameter settings on the calibration record. Changing a display from MPa to psi changes the reported strength units; it does not select a different maturity function.
FHWA-IF-06-004 describes calibration using either compressive cylinder tests or flexural beam tests. Label which property the curve predicts. A compressive-strength estimate does not become a flexural result merely because both are reported in psi. Match the property to the opening requirement described in the concrete pavement guide.
Why a hot start can mislead later strength predictions
NIST's 2001 maturity review reports that higher early curing temperatures can produce higher initial strength but lower later strength at equal maturity indices. This crossover effect means equal accumulated indices do not guarantee equal later-age strengths after different early temperature histories. Arrhenius equivalent age does not eliminate that later-age effect.
Retain the initial temperature traces for the placement and the calibration specimens beside the predicted strength. The mass concrete guide addresses the separate peak-temperature and temperature-difference controls that a high maturity reading does not satisfy.
Attach curing and batch verification to the strength estimate
ASTM C1074-19e1 makes continued cement hydration a condition of the estimate and calls for supplementary evidence of the field concrete's strength potential. A logger in concrete that has dried out still accumulates a temperature index; the displayed number does not establish the strength that developed. Record the curing condition with the temperature export.
NRMCA's CIP 39, revised in 2019, describes supplementary testing before critical construction operations. Attach the verification test and batch identifier to the maturity estimate used for a stripping or loading decision. Keep that evidence with the cylinder testing records.
Distinctions
- Equivalent age
- An Arrhenius calculation reports time at a stated reference temperature. An output of 24 equivalent hours cannot be substituted for 24°C-hours on a Nurse-Saul temperature-time-factor calibration.
Field example
A placement log contains 12 hours averaging 10°C followed by 12 hours averaging 20°C, with a calibrated datum of 0°C. The Nurse-Saul index is (10 - 0) x 12 + (20 - 0) x 12 = 360°C-hours. Using only the latest 20°C reading for all 24 hours gives 480°C-hours, overstating the accumulated index by 120°C-hours, or one third. Read strength from the curve at 360°C-hours; the index error is not an equal percentage error in strength.
Frequently asked questions
Can two maturity readings be compared if one is in days and one in hours?
For a Nurse-Saul index using the same temperature scale and datum, multiply degree-Celsius-days by 24 to obtain degree-Celsius-hours. This time-unit conversion does not convert a temperature-time factor into Arrhenius equivalent age. Preserve the function name with the value.
Does doubling the maturity index double concrete strength?
No. The measured strength-maturity relationship sets the strength at each index. Read each value from that curve instead of applying a proportional strength increase to the index increase.
Sources checked
- ASTM C1074-19e1: active edition verified November 5, 2026; scope 1.3 and limitations in 5.3
- NIST, Carino and Lew, 2001: The Maturity Method: From Theory to Application, laboratory logging intervals and crossover effect
- FHWA-IF-06-004, November 2005: Maturity Testing for Concrete Pavement Applications, datum cutoff and strength properties
- NRMCA CIP 39, 2019 revision: Maturity Methods to Estimate Concrete Strength, parameter selection and supplementary testing
Also defined as
- Paving: Estimating in-place strength from the slab's time-and-temperature history under ASTM C1074
- Estimating in-place strength from the temperature history, per ASTM C1074