Rough-in fixes a fixture’s concealed connection coordinates and the work needed to reach them, including piping, supports, and access for later trim. A usable dimension includes its reference surface and the selected fixture model. Moen MT692C, for example, allows a supply centerline 1 to 2 inches behind the finished wall; a change in finish thickness consumes that setting range without moving the valve.
The drain, vent, and supply piping set to a fixture in the open wall and floor, tested and inspected before the surfaces close
What belongs in a fixture rough-in record?
Give each fixture tag its own connection record instead of one generic wall dimension. Include the selected model, service connections, centerline coordinates, reference planes, finish revision, and the space needed to join and support the piping. That record connects layout, material ordering, and the later trim package.
Break the estimate into concealed connections, support and protection, testing, and fixture or trim setting. A fixture-count allowance that covers only stub-outs misses work when a selected model needs a carrier, different valve body, or relocated access. Tie substitutions to the affected fixture tags so the revised quantity has an identifiable location.
- Fixture tag and exact rough-body and trim model.
- Horizontal and vertical connection coordinates with named datums.
- Finished-wall and floor buildup with drawing revision.
- Measured installed coordinates and remaining trim adjustment.
Build the finished-wall plane into the valve setting
Moen instruction sheet MT692C, issued November 2002, sets the supply-piping centerline between 1 and 2 inches behind the finished wall for its listed PosiTemp valves. Moen MT692C uses the plaster-ground face as the finished-wall reference, including tile, and shows a 1¾-inch reference dimension.
Carry the instruction identifier with the selected valve rather than using that legacy sheet as a brand-wide depth rule. Keep the rough-body and trim instructions together because trim fit depends on both components.
Turn a finish revision into a measured change
A valve set 1¼ inches behind the planned finish becomes 2⅛ inches deep when the finish assembly grows by ⅞ inch. That exceeds MT692C’s 2-inch maximum by ⅛ inch. Put the revised depth and the selected remedy on the fixture record before the finish conceals the connection.
Use a straightedge at the revised finished-wall plane to measure the actual centerline setback. Record the backer, waterproofing, setting bed, and tile buildup that produced it; a dimension from the stud face alone cannot reconstruct that plane.
Choose an extension by valve, trim, and installation date
Moen’s extension chart lists kit 96945 for most PosiTemp trims and kit 193114 for Doux, Flara, and Colinet. For Weymouth and Arris, Moen’s chart assigns 96945 to installations before 2018 and 193114 to installations after 2018. The trim name alone can therefore leave the order unresolved.
Save the valve identification, trim model, installation date, measured depth, and finish designation with the order. An extension repairs a supported depth mismatch; the record still needs to identify crooked positioning or missing support as separate corrections.
The inspection guide follows the permit stages, while the fixture-setting guide covers fixture installation. Use the model-specific coordinate record to reconcile an inspected rough with the trim actually delivered.
Frequently asked questions
Is the plaster guard always flush with the stud face?
No. The guard’s relationship to the completed wall comes from the valve instructions. A stud-face measurement is useful only after the full finish buildup has been accounted for.