SPCC

SPCC stands for Spill Prevention, Control, and Countermeasure. For EPA-regulated, non-transportation facilities, the capacity triggers are more than 1,320 U.S. gallons aboveground or more than 42,000 gallons completely buried, after applicable exclusions, together with a reasonable discharge pathway to navigable waters or adjoining shorelines. EPA counts aboveground containers of at least 55 gallons by capacity. A partly filled tank therefore contributes its capacity, not just today's oil inventory, to the applicability calculation.

Spill Prevention, Control, and Countermeasure plan under EPA 40 CFR 112 for aboveground oil over 1,320 gallons aggregate

Used across 2 Anvilfield field guides, most in Plumbing.
Updated

Count storage capacity before choosing a plan

EPA's SPCC Guide for Facilities bases the inventory on container capacity. Twenty-four non-exempt 55-gallon oil drums total 1,320 gallons and do not cross the aboveground threshold; a twenty-fifth makes 1,375 gallons and crosses it. Five-gallon pails are excluded from that count. This calculation addresses the capacity test; the site's jurisdiction and discharge pathway determine applicability with it.

40 CFR 112.1 excludes completely buried tanks subject to all technical requirements of federal Part 280 or an approved state UST program. It also excludes permanently closed containers and other specified categories. Document those exclusions in the inventory instead of dropping every underground tank. EPA's guide directs the discharge-pathway assessment to ignore manmade barriers such as dikes, so installed containment does not establish exemption.

EPA's September 2025 factsheet includes mineral and synthetic oils, vegetable oils and animal fats. Inventory lubricating and cooking-oil operations alongside the generator fuel. Use the fuel-storage guide for the tank-system context, then record capacity and exemption status for each container.

Tier I, Tier II and professional-engineer certification

EPA's qualified-facility criteria set the aggregate aboveground ceiling for self-certification at 10,000 gallons, inclusive, plus the discharge-history test below. Tier I additionally limits every individual aboveground oil container to 5,000 gallons or less. An otherwise qualified facility with a larger single container is Tier II.

Two 5,000-gallon tanks satisfy both Tier I capacity limits. A 6,000-gallon tank and two 2,000-gallon tanks total the same 10,000 gallons but require the Tier II route if self-certifying. Count the rest of the facility's non-exempt oil containers before treating either tank arrangement as the complete total.

EPA offers Tier I facilities the Appendix G template. Tier II self-certification uses a plan addressing the applicable general and facility-specific provisions; certain alternative measures require PE certification of the affected portions. Self-certification is optional, and state engineering rules still apply. A facility that fails the qualified-facility criteria needs a PE-certified plan.

Which spill history prevents self-certification?

EPA's qualified-facility factsheet screens for either one discharge exceeding 1,000 gallons or two discharges each exceeding 42 gallons within any twelve-month period. Review the three years preceding self-certification; for a facility operating less than three years, 40 CFR 112.3(g)(2) instead uses its history since becoming subject to the rule.

These quantities measure oil reaching navigable waters or adjoining shorelines. Record the total release and the amount reaching those waters separately. EPA excludes discharges caused by natural disasters, acts of war or terrorism from this qualification test. Its thresholds determine certification eligibility, not whether a smaller spill has reporting duties.

Tank changes can require action before the five-year review

40 CFR 112.5 requires review at least every five years, with a signed record of the decision to amend or retain the plan. Field-proven prevention technology that would significantly reduce discharge likelihood triggers an amendment within six months of that review, followed by implementation as soon as possible and within six months of preparation. EPA's plan-review FAQ confirms that an unchanged plan does not automatically require another PE seal.

A facility change materially affecting discharge potential has its own clock under 112.5(a): prepare the amendment within six months, then implement it as soon as possible and no later than six months after preparation. Technical amendments require PE certification unless the qualified-facility provisions permit self-certification. Keep tank and piping changes with the plan's amendment record and the inspection-program records.

Containment volume follows the largest tank and rainfall

For ordinary onshore bulk-oil storage, 40 CFR 112.8(c)(2) sizes secondary containment to the largest single container's full capacity plus sufficient precipitation freeboard. The capacity of the whole tank group is a different quantity. Show the largest tank, usable containment volume and rainfall allowance in the calculation; a fixed 110 percent entry does not establish the required rain allowance.

EPA's facility guide separately describes general containment at oil-transfer points, based on the likely release there. A delivery connection outside the tank dike needs its own spill-control provision. Loading and unloading racks have additional requirements under 112.7(h), so identify a rack separately from an ordinary transfer point.

Frequently asked questions

Do I submit an SPCC plan to EPA for routine approval?

EPA's September 2025 factsheet says routine plan submission is not required. Keep the certified plan implemented and available for inspection; EPA can request it during an inspection or after a spill. This differs from the separate Facility Response Plan submission requirements.

Sources checked

Also defined as

  • Datacenter: The EPA Spill Prevention, Control, and Countermeasure rule and the written plan it requires for oil storage