Field glossary · component

Stress cone

On a shielded MV cable, a stress cone is the termination's field-grading element, which can be a concealed tube rather than a cone-shaped part. Prysmian's ColdFit design uses a high-permittivity tube; its PICT15X1-CF fits 0.57 to 0.98 inch insulation and PICT15X2-CF fits 0.67 to 1.10 inches. A 1.02 inch cable therefore fits the second range even though both are 15 kV indoor products. Sheds describe the outer surface; they do not identify the grading mechanism.

The geometric or stress-relief device that spreads the field at the shield cutback so the insulation is not overstressed

Used across 2 Anvilfield field guides, most in Electrical.
Updated

Select the body by insulation diameter

Prysmian's ColdFit catalog specifies an insulation-diameter range of 0.57 to 0.98 inch for PICT15X1-CF and 0.67 to 1.10 inches for PICT15X2-CF. A prepared diameter of 1.02 inches exceeds the first range and falls within the second. That resolves the diameter check; the voltage, shield construction, and connector still determine the complete order.

Prysmian bases its conductor-size columns on AEIC CS8 compressed-conductor cable dimensions and directs users of other constructions to verify the actual insulation diameter. A schedule that lists only AWG or kcmil leaves that fit decision unresolved. Put the measured insulation diameter beside the chosen body number on the preparation record for the termination and splicing work.

Why Class 1 does not identify outdoor duty by itself

Prysmian identifies both its outdoor PCT and indoor PICT ColdFit terminations as IEEE 48 Class 1; the indoor PICT15 has no sheds. A Class 1 designation therefore does not establish that a particular termination is an outdoor product. Read the environmental application alongside the class and the dimensions.

IEEE 48-2020 remains the current termination standard; its public scope excludes separable insulated connectors. A submittal for an elbow therefore needs its own accessory standard rather than IEEE 48 alone. Enter the complete body designation and indoor or outdoor application in the MV cable test record, alongside the termination class.

Creepage distance and strike distance on a cut sheet

Nexans's June 2020 AFS sheet separates insulation fit, strike distance and creepage for two 24 kV outdoor bodies. Creepage follows the insulating surface around the sheds; strike distance is the shorter air path between the conductive ends. Neither number locates the insulation-shield cutback.

A prepared cable diameter of 28 mm exceeds the AFS 20.1 range and fits AFS 20.2. The latter also increases strike distance from 295 to 325 mm and creepage from 567 to 598 mm. Record all three dimensions: choosing by voltage or by apparent housing size alone misses a documented difference between these bodies.

Nexans 24 kV bodyInsulation diameter (mm)Strike distance (mm)Creepage (mm)
AFS 20.117.0 to 27.0295567
AFS 20.220.9 to 35.0325598

Count bodies, connectors and earthing parts separately

For a three-end assembly, the Nexans AFS ordering diagram shows three termination housings, three connectors, three earthing contacts and one earthing collar, plus sealing mastic and instructions. Those are separate material-list items. A takeoff line that says only 'three stress cones' leaves the connector and earthing quantities unrecorded.

Describe the cable's metallic construction on that takeoff as well. The concentric-neutral record identifies wire count and gauge; the termination drawing identifies the earthing parts that join it. Keep mechanical cable supports on their own line, since the field-grading body is not a strain-relief clamp.

Distinctions

Stress-control tube
Prysmian's ColdFit assembly uses a high-permittivity tube beneath the housing. The stress-control element can therefore be concealed inside a termination with no externally visible cone.
Weather shed
A shed changes the external surface path. Counting sheds does not reveal the internal grading material or confirm the fit against the cable insulation.

Frequently asked questions

Can I identify the stress cone by the outside diameter?

The housing diameter describes the outside envelope. Select the accessory using its specified cable-insulation range and construction, then use the external dimensions to confirm physical clearance.

Is the creepage dimension the length to strip the cable?

No. Creepage is an external insulation-path dimension. Strip lengths locate the cable layers within the particular termination and come from that assembly's installation drawing.

Sources checked

Also defined as

  • Datacenter: Geometric stress relief that extends the grounded shield in a cone so the field spreads and the peak stress at the cutback drops

Where this shows up

Next step: Map substations and owners

Back to the full field glossary